Tulsa District Briefing for Red River Valley Association. COL Anthony Funkhouser Commander SWD/ Commander Tulsa District Dallas/Tulsa 12 November 2009. US Army Corps of Engineers. Mission: Provide vital public engineering services

Download Presentation

Tulsa District Briefing for Red River Valley Association

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Tulsa District BriefingforRed River Valley Association COL Anthony Funkhouser Commander SWD/ Commander Tulsa District Dallas/Tulsa 12 November 2009

  2. US Army Corps of Engineers Mission: Provide vital public engineering services In peace and war to strengthen our Nation’s security, energize the economy and reduce risks from disasters. GOAL 1: Deliver USACE support to combat, stability and disaster operations through forward deployed and reach back capabilities. GOAL 2: Deliver enduring and essential water resource solutions through collaboration with partners and stakeholders. GOAL 3: Deliver innovative, resilient, sustainable solutions to the Armed Forces and the Nation. GOAL 4: Build and cultivate a competent, disciplined, and resilient team equipped to deliver high quality solutions.

  3. Tulsa DistrictCivil Works Boundary Arkansas River Basin Southern Kansas Northern Oklahoma Red RiverBasin Southern Oklahoma Northern Texas & Panhandle

  4. Oklahoma Comprehensive Water Plan, OK (I) Study Authorized in WRDA 2007, Sec 5119 FY10 Capability: $2,300,000 FY10 Appropriation: $0 Sponsor: Oklahoma Water Resource Board

  5. Oklahoma Comprehensive Water Plan, OK (PAS) Supports Oklahoma Comprehensive Water Plan Status: FY10 funds will be used to evaluate drought preparedness and produce GIS maps for statewide raw water infrastructure Sponsor: Oklahoma Water Resource Board FY10 Appropriation: $ 500,000

  6. Washita River Basin Feasibility Study Supports Oklahoma Comprehensive Water Plan Status: Continuing Region/Basin data collection and conservation potential. Sponsor: Oklahoma Water Resource Board FCSA – June 2008 FY10 Appropriation: $ 171,000

  7. Southeast Oklahoma Water Resource Study, OK Supports Oklahoma Comprehensive Water Plan Status: Continue detailed assessment of the water storage needs of the region, analysis of impacts on existing water resources, and GIS-based mapping of infrastructure Sponsor: Oklahoma Water Resource Board FCSA – June 2001 FY10 Appropriation: $ 233,000

  8. Lake Texoma, OK and TX Reallocation Study 5 Nov 09: ASA(CW), Ms. Darcy briefed Secretary of the Army, Mr. John McHugh. Secretary McHugh concurred with USACE position on hydropower being consistent with Secretary Geren’s prior direction. Next Steps: HQ USACE arrange meeting with Congressman Hall. ASA (CW) issue letter to SWPA on hydropower compensation. ASA(CW) approve reallocation report and water supply agreements. Goal: Complete by end of November 2009.

  9. Lake Texoma Land Transfers Status: Data collection for EIS under contract (Denison) Sponsor in TX: City of Denison Sponsor in OK: OK Dept of Tourism

  10. Funding for FY10 Conference Broken Bow $ 3,043,000 Hugo Lake $ 1,652,000 Pine Creek $ 1,213,000 Pat Mayse $ 1,148,000 Waurika $ 1,360,000 Kemp $ 327,000 RRCC $ 1,481,000 Texoma Lake $ 8,740,000 OCWP (PAS) $ 500,000 SE Oklahoma Feas. $ 233,000 Washita Feas. $ 171,000

  11. Additional Funding ARRA 08 Supp 09 Supp (1,000) Broken Bow $ 1,989 $ 0 $ 0 Hugo Lake $ 888 $ 0 $ 1,158 Pine Creek $ 1,500 $ 0 $ 612 Waurika $ 888 $ 175 $ 524 Kemp Lake $ 0 $ 0 $ 0 RRCC $ 4,798 $ 0 $ 51 Texoma Lake $ 7,862 $ 2,225 $ 2,356

  12. Red River Chloride Control, TX & OK Project: Reduce naturally occurring chloride and total dissolved solid concentrates in the Upper Red River Basin to allow economical use of water for municipal, industrial, and agricultural purposes. This project is a select major water strategy of the 2007 Texas Water Plan. Status: Resume construction and continue real estate acquisition efforts at Area X, initiate real estate acquisition activities at Area VII and continue reevaluation efforts for Area VI. Sponsors: Wichita Basin - Red River Authority of Texas, TX Area VI - Oklahoma Water Resources Board (OWRB) and the Lugert-Altus Irrigation District, OK FY 2010 Conference: $ 1,332,000 Initiatives: August 2009 legislative tour with Congressman Thornberry/ Senator Cornyn staff December 2009 tour with TWDB representatives.

  13. Contact Information Commander COL Anthony Funkhouser phone: (918) 669-7201 E-mail: Anthony.Funkhouser@usace.army.mil Chief, Project and Project Management Division John Roberts phone: (918) 669-7201 E-mail: John.H.Roberts@usace.army.mil Chief, Planning and Environmental Division Sue Haslett Phone (918) 669-7666 E-mail: Susan.J.Haslett@usace.army.mil Chief, Operations Earl Groves Phone: (918) 669-7397 E-mail: Earl.Groves@usace.army.mil Chief , Engineering and Construction Clif Warren Phone (918) 669-7671 E-mail: Clif.Warren@usace.army.mil 1645 S. 101st East Ave. Tulsa, OK 74128

  14. ll QUESTIONS?