460 likes | 1.24k Views
From Aggregate to Master Planning. Aggregate Production Plan. . Capacity ?. Master Production Schedule. . Feasibility approved?. Material Requirement Planning. . . . . Yes. Yes. . . No. No. Can we produce 10,000 equivalent units (total for products A, B and C) per month for the next year?. Can we produce 500 units of A, 600 of B and 400 of C per week for the next month ?.
E N D
1. Master Product Scheduling (MPS)Material Requirements Planning (MRP)
3. Production Plan VS Master Production Schedule
4. The Aggregate Plan and the Master Production Schedule
5. When to Order ?Three approaches Reorder Point (continuous review system)
Constant amount ordered when inventory declines to predetermined level
Periodic Review System (fixed time review period)
Order placed for variable amount after fixed passage of time
Time Phased Order Point
Master Production Schedule
Material Requirements Planning
Distribution Requirements Planning
6. Objectives of the Master Production Schedule Establish and meet delivery dates
Determine launch dates for orders
Optimize the use of available capacity
Meet the objectives of the aggregate plan
Make trade-off decisions between production and marketing
7. Master Production Plan : Inputs Inputs to the MPS are :
Beginning Inventory
Forecasts for each week of the schedule
Customer orders (quantities already committed to customers)
Total available capacity for each week of the schedule
8. Developing a MPS Identification of individual products.
Development of an MPS grid for each product in real units according to the available data (forecast, committed orders, inventory levels, lot sizes, lead times) and the specified constraints.
Rough cut capacity planning in equivalent units (for all products).
Does the plans meet all constraints? (capacity limits, stock levels, etc.)
9. Developing a MPS
10. Developing a MPS
11. Preliminary Plan :Complete the following MPS
12. Preliminary Plan :Complete the following MPS
13. Rough Cut Capacity Planning Approximate calculation of the capacity required at critical work centers to meet the demand in order to check the feasibility of a Master Production Schedule.
When the capacity required exceeds the capacity available the MPS must be adjusted before proceeding to the MRP.
14. Final MPS :Rough Cut Capacity Planning
15. Final MPS :Modifications to the Preliminary Plan
16. Final MPS :Modifications to the Preliminary Plan
17. Reading
18. Demand Characteristics
19. Reorder Point System VS MRP
20. Reorder Point System VS MRP
21. Objectives of MRP
Calculate with precision the quantities of components, parts and raw material that must be produced or purchased in order to realize the MPS
? HOW MANY ?
To determine when to release production or to place the orders in order to receive the required units at the right moment
? WHEN ?
22. Material Requirements Planning : Information Structure
23. Bill of Materials (BOM)
24. Problems
25. MRP Matrix
26. MRP calculation process Always process the items in the order of their low level code: level 0 ? level 1 ? level 2
When an item appears at different levels of the product structure(s), the lowest level (highest number) is the level that we must use.
Gross requirements for an item are calculated by:
Multiplying the quantity of the planned order release(s) of the parent(s) of the item by the quantity required as per the BOM for the specific parent-component relationship(s).
27. Lot Sizing in MRP Systems Lot-for-lot (L4L) ordering policy
Minimum order quantity (Ex: Min 250)
Multiple order quantity (Ex: X100)
Economic order quantity (Ex: 350; annual demand: 4 200)
Periodic order quantity (Ex: 2 months)
28. Example A company is manufacturing several office supply items among which we have:
Clipboard
Lapdesk
etc.
29. Product Structure
30. Product Structure Tree
31. MRP: Example (cont.)
32. MRP: Example (cont.)
33. MRP: Example (cont.)
34. MRP: Example (cont.)
35. MRP: Example (cont.)
38. Establishing the Minimum Planning Horizon
39. Establishing the Minimum Planning Horizon
40. MPS / MRP PROCESS
41. Readings Review problems:
To be announced
Review Reading for MRP:
S&H 2007, 484-497
Readings for next class (scheduling) :
S&H 2007, chap. 15 pp 547-560