1 / 50

LAKE OSBORNE MUCK DREDGING PROJECT

LAKE OSBORNE MUCK DREDGING PROJECT. Presentation Overview. What are the Chain of Lakes? How have the lakes become degraded? Palm Beach County’s Involvement - State of the Lakes Plan What is Muck? - How does muck develop? How much muck is in the lake and how do we know? - Surveys

Pat_Xavi
Download Presentation

LAKE OSBORNE MUCK DREDGING PROJECT

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. LAKE OSBORNEMUCK DREDGING PROJECT

  2. PresentationOverview • What are the Chain of Lakes? • How have the lakes become degraded? • Palm Beach County’s Involvement - State of the Lakes Plan • What is Muck? • - How does muck develop? • How much muck is in the lake and how do we know? - Surveys • What is the County’s plan? - Lake Osborne Muck Dredging Project • Lake Osborne Muck Dredging Project • Brennan Marine Professionals • Dredging Equipment • Dewatering Plant • Drying Methods • Disposal of Muck • Future of the Project

  3. CHAIN OF LAKES • Part of a natural lake system that, at one time, extended from West Palm Beach to Delray Beach • The E4 canal connects Pine Lake, Lake Clark, Lake Osborne, Lake Eden, Lake Ida • Freshwater lakes: • provide habitat for native flora & fauna • replenish drinking water supplies • store and filter storm water • provide recreational opportunities • aesthetically appealing

  4. Degradation of a System Historical dredge & fill activities, urban encroachment & discharge from canals.....

  5. South Lobe of Lake Osborne (1986) ...lead to the lakes’ waters becoming overloaded with nutrient-rich organics

  6. As a result, excessive plant life (algal blooms) develops throughout the Chain of Lakes causing a decrease in water quality & reduction in oxygen levels HYDRILLA

  7. STATE OF THE LAKES PLANThe lakes’ decreasing quality prompts Palm Beach County’s Department of Environmental Resources Management to commission a report in 1997 to address how to enhance and improve the freshwater system and its managementThe plan focuses on the following goals: • Restore and Protect Wetland Habitats • Protect & Improve Water Quality • Control Exotic Vegetation • Maintain & Enhance Fisheries • Enhance Public Participation & Environmental Awareness

  8. MUCK What is MUCK? Muck is organic and inorganic sediments, sands, silt, debris and other materials How does MUCK form? Muck is a result of the excess nutrients in the water. Excess nutrients are attributed to: -Lakes’ extensive development -Herbiciding of non-native vegetation -Discharge of several canals How long has MUCK been accumulating throughout the lakes? -50 plus years

  9. Photo Credit: SFWMD (Know the Flow Poster)

  10. In 2002, the County contracts with the survey company, Morgan & Eklund, INC., to measure the amount of muck throughout Lake Osborne Method of Measurement:dual frequency transducer• Transducer captures the top of the muck layer and natural sandy lake bottom to determine muck’s thickness

  11. LAKE OSBORNE MUCK DREDGING PROJECT • Surveys reveal 700,000 CY of muck cover the sandy lake bottom • In response, Palm Beach County develops the Lake Osborne Muck Dredging Project County divides the dredging of the southern lobe into phases: Phase I: removal of approximately 20,000 cubic yards of muck, in situ, from a 199,241 square foot section Phase II: removal of approximately 85,000 cubic yards of muck, in situ from a 1,015,010 square foot section

  12. LAKE OSBORNE MUCK DREDGING PROJECT • County decides to pay selected contractor by the square footage vs. cubic yard because of the consistency of the material • Muck is difficult to measure volumetrically because there is no defined top layer • 1.2 million square feet (approximately 28 acres) throughout the project site • $1.12 per square foot • Total project cost for Phase I & II: 1.4 million dollars

  13. County awardsBrennan Marine Professionals Phase I of the contract in March 2004 • Brennan receives Phase II of the project if they are able to meet project deliverables & complete work within allotted time frame for Phase I • Project Time Frames: Phase I - 45 days from Notice to Proceed to mobilize all equipment (no payment for mobilization) 70 calendar days after mobilization to complete dredging and dewatering of material from Phase I Phase II – 300 calendar days from issuance of the second Notice To Proceed to complete Phase II

  14. Spring 2004: Brennan receives Notice to Proceed in March and begins to mobilize equipment in April Mobilization at Melear Park: April 22, 2004

  15. Fusing & placement of polyethylene plastic pipe Mobilization: April 22, 2004

  16. Eight (8) inch intake pipeline transports muck (slurry) to the dewatering plant

  17. Buoys & signage along the pipelines warn recreational users of the pipes’ presence

  18. 8” Swinging Ladder Rotating Cutter Head Suction Dredge - 3 Spud System - Hydraulically Actuated Spud Frame enables dredge to walk along the lake bed DredgingEquipment

  19. CUTTER HEAD

  20. Interface between the dredge operator & field conditions Dredge Operator Booth

  21. RTK Global Positioning System RTK Positioning System provides sub-centimeter accuracy for position of dredge and cutter head DREDGEPACK Software Uses county surveys that designate dredge depths Screen displays operator position & amount of material being removed Tracks & recalculates the amount of material to be excavated Displays new calculations on the screen until achieving designated dredge depth High Tech Instrumentation on the Dredge Includes:

  22. Pay Survey Deliverable Dredge Track Lines: demonstrate where the dredge’s cutter head is working throughout the day

  23. DewateringPlant

  24. Underflow (slurry) entering dewatering plant

  25. SANDWHEEL (used initially)

  26. Wheel removes sand from slurry Contains 200-mesh (.074 mm) screens

  27. SCALPER Removes debris & organics by gravity feeding slurry through a belt screen FRAC TANK Slurry homogenizes in frac tank (Only minus 200-mesh /.074 mm solids remain)

  28. VIBRATORY SCREEN • Material travels over a 5’ x 7’ vibrating screen (35-mesh/0.5 mm) • Vibration causes the sands & larger material to move toward the discharge end of the screen where it is placed on the radial stacker • Material finer than 35-mesh/0.5 mm drops through the screen into a sump

  29. Slurry collecting in sump is pumped and delivered to two cyclonic separators The cyclonic separators perform like a centrifuge, using 320-mesh screens to further separate the slurry Finer material spins out the top of the separators & moves toward the frac tank HYDROCYCLONES(now in use) • Larger material falls to the bottom of the separators & passes over the dewatering screen for a second time

  30. Dewatering Screen

  31. RadialStacker Material passing over the dewatering screen falls onto the radial stacker

  32. FRACTANK Fine material leaves via top of cyclone • Slurry now contains only 320-mesh solids • First injection of chemical: Aluminum-Chloride-Hydroxide (a coagulant) • Slurry homogenizes in the tank Slurry flows into frac tank Flow regulator (injects chemical into tank at a controlled rate)

  33. THICKENER Twin Clarifier Tanks Concentrated deflocculent 2% Solution Inflow

  34. Flocculent Mixture • Second chemical injected: FLOC NALCO 83906 Optimer Plus • Chemical mixes with water pumped from an underground well • Solution added to the slurry contains 1-3% of chemical • Injection of chemical into the slurry is computer controlled and based upon the consistency of the material • Opitmer Plus (flocculent) helps the organics organize into a semi-solid mass Control Panel Well Water

  35. Chemical & slurry mix together in the flocculent injection tank Slurry separates into the twin clarifiers Return water flows to the top & exits via the overflow pipe Overflow Pipe Makeup Well Water Generator Underflow Pipe Well Fuel Auxiliary Pump Slurry sinks to the bottom of the clarifiers and exits via the underflow pipe

  36. EndResults:Overflow • Return water is diverted back to Lake Osborne via the 11.5” overflow pipe • Return water can not exceed 29 NTUs (Nephelometric Turbidity Units) above lake’s background level • Overflow is monitored for high turbidity levels twice a day at the overflow tank using a nephelometer

  37. OverflowTank

  38. EndResults:Underflow • Underflow exits the dewatering plant and is pumped into a drying bed • The processed muck remains within the bed for a week for further dewatering

  39. MANIFOLD

  40. GEOBAGS • First dewatering method • Allows for further concentration of slurry for hauling • Contractor assembled five bags in total (500 CY per bag)

  41. DryingBeds(now in use)

  42. Muck remixes with sand from the radial stacker Parks Department uses mixture as a soil amendment throughout various County parks and at the site of a future County golf course Processed Material Output = 600 CY per day MUCKREMOVAL

  43. Anticipated Benefits • Improved water quality & environment • Enhanced boating & fishing • Re-establishment of native benthic vegetation • Increased property value • Enriched top soil for use in public parks

  44. The Project’s Future • South Florida Water Management District (SFWMD) dedicates $200,000 in matching grant funding for the continued excavation of muck from Lake Osborne

  45. Proposed Dredge Areas for Phase III

More Related