1 / 18

Work Breakdown Structure WBS

Work Breakdown Structure WBS. Work Breakdown Structure (WBS). A hierarchical system which sub-divides larger elements of the project into smaller elements. The smallest unit of the WBS is the work package. Work Breakdown Structure Example. Level. Work Breakdown Structure. Level Description.

Rita
Download Presentation

Work Breakdown Structure WBS

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Work Breakdown StructureWBS Prof Awad S. Hanna

  2. Work Breakdown Structure (WBS) • A hierarchical system which sub-divides larger elements of the project into smaller elements. • The smallest unit of the WBS is the work package. Prof Awad S. Hanna

  3. Work Breakdown Structure Example Level Work Breakdown Structure Level Description 1 Warehouse Total Project 2 Administration Mobilization/ Demobilization Masonry Wall Steel Columns & Joints Roof System Subproject 3 Sitework Footing Floor Slab Masonry Wall Steel Columns & Joints Roof System Interior Finishes Category of Work 4 Excavate Footings Form & Reinforce Footings Place Footings Work Package 5 Labor Material Equipment Resources Prof Awad S. Hanna

  4. WORK BREAKDOWN STRUCTURE (cont.) • The scope of work in each work package should be defined to avoid overlaps and omissions between work packages. • Work packages should be defined in terms of design, construction methods, and completion requirements, with associated performance dates Prof Awad S. Hanna

  5. Scope of Work Packages Each work packages should be: 1. Manageable • Specific authority and responsibility can be assigned. 2. Independent • With minimum interfacing or dependence on other elements. 3. Measurable • In terms of progress. Prof Awad S. Hanna

  6. The Project Cost System Objectives of Establishing Project Cost System. 1. Keep the construction costs of the project within the established budget. 2. Develop labor and equipment productivity information for estimating the cost of future work. Prof Awad S. Hanna

  7. Cost Code Project Number Area Code Work Type Code Distribution Code • Cost Code for stripping concrete formwork for bridge deck (Labor). 9708B 05 03157.20 3 Prof Awad S. Hanna

  8. Project Number 9708B05 03157.20 3 • Eighth project in 1997 (Bridge) Prof Awad S. Hanna

  9. Area Code 9708B0503157.20 3 • Geographic location OR • Associate Field Cost to Specific supervisor or Management Prof Awad S. Hanna

  10. Work Type Code 9708B 0503157.203 03 Concrete 0315 Concrete Formwork 03157 Wood Concrete Formwork 03157.20 Wood Concrete Formwork for Deck 03157.30 Wood Concrete Formwork for Abutment Prof Awad S. Hanna

  11. Distribution Code 9708B 05 03157.203 1. Total 2. Material 3. Labor 4. Equipment 5. Sub-Contract Prof Awad S. Hanna

  12. Cost Code and Cost Control • All items of expense are charged to the project where they are incurred. • "General" or "miscellaneous" cost accounts should not be used, is poor practice, and should be avoided. • The cost code is to serve its basic purpose, it must be understood and used consistently by all company personnel. Prof Awad S. Hanna

  13. COST ACCOUNTINGREPORTS • Cost report intervals are a function of the project size, nature of the work, and the type of contract involved. • There must be a balance between the cost of generating the reports and the value of the management information received Prof Awad S. Hanna

  14. COST CODES • The most widely used cost codes are • Masterformat, CSI (Construction Specifications Institute) • Uniformat, UCI (Uniform Construction Index). • Masterformat is widely used software companies and government agencies. Prof Awad S. Hanna

  15. Most contractors match their cost control system to their payroll periods and to their time-monitoring system. Prof Awad S. Hanna

  16. COST CODES (cont.) • Masterformat • Has 16 divisions • Divisions were developed according to trades • Uniformat • Has 12 divisions • Tends to follow the progress of construction Prof Awad S. Hanna

  17. Relationship Between UNIFORMAT & MASTEFORMAT Prof Awad S. Hanna

  18. UNIFORMAT Level A and B Prof Awad S. Hanna

More Related