Oregon’s Work Zone Traffic Analysis Program

Oregon’s Work Zone Traffic Analysis Program. FHWA Work Zone Rule Virtual Workshop November 6, 2008 Irene Toews, P.E. Oregon Department of Transportation Jeremy Jackson, E.I.T. Oregon Bridge Delivery Partners. Oregon’s Work Zone Traffic Analysis. Why do we do it? What do we do?

aadi
Download Presentation

Oregon’s Work Zone Traffic Analysis Program

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Oregon’s Work Zone Traffic Analysis Program FHWA Work Zone Rule Virtual Workshop November 6, 2008 Irene Toews, P.E. Oregon Department of Transportation Jeremy Jackson, E.I.T. Oregon Bridge Delivery Partners

  2. Oregon’s Work Zone Traffic Analysis Why do we do it? What do we do? How do we do it?

  3. Why do we do it? • Work Zone Traffic Analysis Tool • Timeline • May 2004 – Oregon Bridge Delivery Program Starts • Summer 2005 – WZTA is created in spreadsheet form • Summer 2006 – WZTA is expanded for statewide use • Fall 2006 – ODOT WZTA Manual is revised • October 2008 – WZTA online tool goes live

  4. What do we do? • Determine safe times for lane closures • Times when volumes are low enough that travel behavior is not significantly affected. • Determine Mobility Impacts - Delay Estimates • Work Zone • Segment • Corridor

  5. WZTA Background OTIA III Bridge Locations Statewide Mobility Corridors Defined

  6. Mobility Management and Delay Thresholds I-5 South Corridor (Eugene to CA State Line)

  7. Mobility Management and Delay Thresholds Segment 4-C (US 199 to CA State Line)

  8. Mobility Management and Delay Thresholds Length: 55 miles Delay Threshold: 7 minutes

  9. Mobility Management and Delay Thresholds Corridors broken into segments Delay thresholds assigned to segments Delay thresholds to be enforced 24/7/365 Detailed delay estimates are needed to help manage mobility Individual delays must be aggregated

  10. How do we do it? Work Zone Traffic Analysis Tool Requires only an internet connection and browser Up-to-date data Analysis results stored on server 5-15 minutes per analysis Output Lane closure charts Delay estimates Other…

  11. How Does It Work? Gather data Adjust data Heavy vehicles Seasonal variations Weekday/weekend Growth rates Identify free flow threshold Compare

  12. Where Does the Data Come From? ODOT Manual Count Database ODOT Integrated Transportation Information System (ITIS) ODOT Highway Inventory Average Daily Traffic Growth rates Truck percentages ODOT Traffic Database Daily/Seasonal Trends & Automatic Traffic Recorder Data GIS UGB/MPO Region Boundaries

  13. What’s a Free Flow Threshold? The maximum sustainable volume that yields average travel speeds at or near free flow conditions FFT depends on a number of factors

  14. Using the WZTA Tool Choose your location - Method 1 Select Highway # and MP

  15. Choose Your Location – Method 2 Use GIS map to select location

  16. Year of Analysis Inputting the year of analysis yields projected traffic data

  17. Output – Lane Closure Chart Lane closure chart - Weekday

  18. Closure Chart Uses Used primarily in the planning and design phases Planning: May influence final design Design: Project specifications Construction: Short notice issues

  19. Output – Delay Estimates

  20. An Example of Work Zone Context Horizontal geometry = 4 degree curve Vertical geometry = 4-6% grade

  21. Traffic Planning Sheet (TPS) Outputs include: Roadway profile Straightline diagrams Horizontal curve table Vertical grade table Vertical type table

  22. Traffic Planning Sheet (TPS) Roadway Profile

  23. Traffic Planning Sheet (TPS) Straightline Diagram

  24. ATR Graphing Tool Allows for the graphing of actual volumes from an Automatic Traffic Recorder (ATR) over a user defined period Albany ATR October 6, 2007 to October 9, 2007

  25. Summary Delay estimates and work windows can be generated quickly Ability to predict delays/travel times for work zones, segments, and corridors Delay summaries affect scheduling and staging for major construction projects During planning: Closure chart and delay estimates influence staging strategies During design: Closure information used in project specifications

  26. Contact Information Irene Toews, P.E. ODOT Traffic Control Plans, QA Engineer Irene.toews@odot.state.or.us 355 Capital Street NE Salem, OR 97301 (503) 986-3595 Jeremy Jackson, E.I.T. OBDP Traffic Engineering Intern jeremy.jackson@obdp.org 660 Hawthorne Ave SE, Suite 220 Salem, OR 97301 (503) 316-5519