1 / 14

Construction Schedule Control & Risk Management in BOT Pipeline Projects

NOT AN OFFICIAL UNCTAD RECORD. Presentation for Algeria 2006 Africa Oil & Gas Trade & Finance. Construction Schedule Control & Risk Management in BOT Pipeline Projects. Chen Xiangqiu CPP International. Supplier. Government. EPC Contractor. Concession Agreement. Supply Agreement.

aaliyah
Download Presentation

Construction Schedule Control & Risk Management in BOT Pipeline Projects

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. NOT AN OFFICIAL UNCTAD RECORD Presentation for Algeria 2006 Africa Oil & Gas Trade & Finance Construction Schedule Control & Risk Management in BOT Pipeline Projects Chen Xiangqiu CPP International

  2. Supplier Government EPC Contractor Concession Agreement Supply Agreement Construction Agreement Project company Loan Contract Operation Agreement Creditor Operator Insurance Agreement Association Agreement Take&Pay Agreement Customer Insurer Sponsor BOT Briefing … Structure BOT = Build, Operate and Transfer BOO = Build, Operate and Own BLT = Build, Lease and Transfer

  3. Happy with higher return rates Happy with lower tariff & long payback term Developer Government Project Company

  4. The Brief of Lanzhou to Yingchuan Gas Pipeline Project Yinchuan Lanzhou • Lanzhou to Yingchuan Gas Pipeline • Total length : 360 km • Pipe Diameter: 24” • Design Pressure: 10 MPa • Total investment: 150 million USD

  5. Influence of Construction Schedule on IRR Government: Happy Developer: Not happy Project is not feasible Tariff:RMB/ m3 IRR—Internal return rate

  6. Influence of Construction Schedule on Tariff Government: Not happy Developer: Happy Project is not feasible neither Tariff:RMB/ m3 IRR—Internal return rate

  7. BOT Project BOT Briefing … Risk Construction Risks Design Risks Leasing Risks Laws/Regulation variation/updated Risks Financing Risks Cost-overspent Risks Construction Contract Risk Delay Risks Equipment supply Risks ► Political/Legal ► Financial ►Construction ►Market ► Environmental ► Operation

  8. BOT Briefing … Executing Procedure MOU Supply Agreement Take&Pay Agreement Concession Agreement Project financing Front end eng. study Basic Engineering Cooperative negotiation EPC Phase Pre-feasibility study Operation Phase Feasibility Study Transfer Association Agreement

  9. One stop service developer • Has its own resource to implement the EPC • Offer a complete industrial chain • Has a PMC team • Has dual functions, investor &contractor

  10. Thank you - and good luck for your BOT project! (though luck has nothing to do with your skills!)

  11. China West to East Gas Pipeline Project CPP took more than 75% work of whole projects • China West to East Pipeline Project • Total length : 4000 km • Station Quatity: 13 • Pipe Diameter: 42” • Design Pressure: 10MPa • Completion Date: Dec, 2004

  12. CPP’s Experience in Sudan 苏丹 • Muglad Basin Oil Development Project I • Total length : 1506 km • Pipe Diameter: 28” • Design Pressure: 9.7/14.8MPa • Completion Date: April, 1999 • Muglad Basin Oil Development Project II • Total length : 314.8 km • Pipe Diameter: 32” • Design Pressure: 10/15/18MPa • Completion Date: Ongoing Fula Field Oil Export Pipeline Project Total length : 723 km Pipe Diameter: 24” Design Pressure: 10MPa Completion Date: April, 2004

  13. CPP’s Experience in Libya • Western Libyan Pipeline Project • Total length : 527 km (Gas), 527 (Oil) • Pipe Diameter: 32” (Gas), 16” (Oil) • Design Pressure: 9.8~14MPa • Completion Date: May 16, 2004 • EI Sharara to Mellitah Pipeline Project • Total length : 727 km • Pipe Diameter: 30” • Design Pressure: 8~13MPa • Completion Date: August, 2005 • 103A Gas Transmission Pipeline Project • Total length : 207 km • Pipe Diameter: 42” • Design Pressure: 10MPa • Completion Date:Ongoing

  14. CPP’s Experience in Kazakhstan 哈萨克斯坦 • Kenkiyak – Zhanazhol Pipeline Project • Total length : 44 km (Gas) • Pipe Diameter: 21” • Design Pressure: 4MPa • Completion Date: Nov., 2004 • Kazakhstan - China Pipeline Project • Total length : 962 km • Pipe Diameter: 32” • Design Pressure: 6.4MPa • Completion Date:Ongoing • KC13 Natural Gas Pipeline Project • Total length : 164 km • Pipe Diameter: 32” • Design Pressure: 6.4MPa • Completion Date: Oct, 2005

More Related