Clarksville-Montgomery Co. Infrastructure Update Oct. 2010

Clarksville-Montgomery Co. Infrastructure Update Oct. 2010. State Project. SR 76/Dover Rd. Stewart Co. line to SR120 Noticed trees already cut from last section - CONST start Sept. 2009 completed Oct. 2011 KW Lankford Contractors - Stimulas/ARRA $18.7M.

abby
Download Presentation

Clarksville-Montgomery Co. Infrastructure Update Oct. 2010

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Clarksville-Montgomery Co.Infrastructure UpdateOct. 2010

  2. State Project • SR 76/Dover Rd. Stewart Co. line to SR120 • Noticed trees already cut from last section - CONST start Sept. 2009 completed Oct. 2011 KW Lankford Contractors - Stimulas/ARRA $18.7M

  3. State Project • SR374/Southern extension Pkwy. SR76/Dover Rd. to 2,275’ S. of Dotsonville Rd. new construction 2/4 lanes, 3.25 mi. • APR Oct. 1996; Public Meet Nov. 1997; Drft EIS Mar. 2000, River crossing @ COE’s Smith Branch, Public Meet Dec. 2000; Supplemental EIS Dec. 2010 • PE Mar. 2001; Toll Study Nov. 2008 not feasible • ROW Plans (14 tracts) submit Nov. 2014 and TIP shows insufficient $ • Staged CONST in TIP as 2012

  4. State Project SR374/Southern ext. Pkwy. SR149 cross Cmbld. Rv. to south of Dotsonville Rd. - new construction 2/4 lanes, 3.25 mi. - APR July 1996; Public Meet Nov. 1997; Drft EIS Mar. 2000, River crossing @ Smith Branch being reviewed;Public Meet Dec. 2000; Final EIS completion not set; PE Mar. 2001; Toll Study Nov. 2008 not feasible - ROW Plans not submitted Nov 2014 TIP showing HPP$ 2011 - Construction not set in TIP

  5. State Project • SR149/SR48/13 Zinc Plant Rd to SR374 ext. reconstruction 5 lane 3.86 mi. - APR July 1996; Public Meet Nov. 1997; Drft EIS Mar. 2000,Public Meet Dec. 2000; Final EIS completion not set; PE Mar. 2001; Public Design Meet June 2010 - ROW & Utilities 2011 TIP showing $HPP • Construction not set

  6. State Project • SR48/13 From SR149 to SR13 Reconstruct 2 to 5 lanes, 6.25 mi. - APR Mar. 2005 changed to Needs Assessment Study Section 3 – Completed Mar. 2006 - APR Completed Mar. 2007 - Rd Safety Audit Review Completed Aug. 2007 - Oversized signage and red flashing beacon installed Indian Creek Rd. @ SR48 - Law Enforcement current solution, # and severity of incidents are down - No $ in TIP

  7. State Project • SR112/Nashville Hwy. SR76 to McAdoo Creek Rd. reconstruct to 5-lanes, 3.0 mi. • APR completed October 1999; PE Mar. 2001, Public Meeting Dec. 2001; Enivn. Assessment, ROW Nov. 2003 aprx. 130 tracts; Public Meeting Mar. 2004, ROW meeting Oct. 2006; ROW completed July 2009 - *MC Hwy. signal @ McAdoo Creek Rd Spring 2011* • Utilities and CONST earlies start July 2011 if aprx. $20M needs oblgd.

  8. State Project • SR374/Warfield Blvd. from Dunbar Cave Rd. to Stokes Rd. reconstruct to 4 lanes divided 2.36 mi. • APR completed Sept. 2000, PE Feb. 2002 • Public Meet Dec. 4 2003, Envin. Categorical Exclusion May 4, 2006 • ROW May 2006 – Summer ’08 (aprx. 20 tracts) • Utilities est $10.6M combined w CONST est. $10M applied for HPP funding earliest Dec. 2010

  9. State Project • SR374/Warfield/Richview from Dunbar Cave Rd. to SR112/Madison reconstruct 2/3 to 5 lanes - 2.49 mi. • APR completed Sept. 2000 • Envir. Assessment completed • PE ROW, Utilities and CONST – not funded

  10. State/Regional Local Project • NW Corridor Study • C’v to Nashville commuter rail study

  11. State/Local Project • SR48/Trenton Rd. From SR236/Tiny Town Rd. to SR13/Wlm. Rdlph. Blvd. reconstruct 2 to 5 lanes, 3.83 mi. • APR completed Fall 2004 • Envin. LSTP Spring 2009 $36K needs obligated • PE LSTP Spring 2009 $300K needs obligated • ROW LSTP Fall 2012 not funded • CONST TDOT Spring 2015 not funded • TDOT would not partner w City/County

  12. Local, Bi-State & Ft. Campbell • Ft. Campbell US41-A ITS Variable Message Boards and Cameras TN Portion - 41A from Tiny Town (SR236) to State Line Updated Study 2011 PE 2011 HPP funding; 20% match $12K needs obligated CONST ‘11 HPP funding; 20% match $200K needs obligated Total max. Cost $2.06M KY Portion – 41A from State Line to I-24 Total Cost of project $1.08M CONST completed

  13. State Project • SR13/Wilma Rudolph Blvd Bridge over Red River (north bound ) LM 21.56 0.4 miles - PE andROW completed 2005 - CONST late 2011 - TN Bond Program $6.7M

  14. State Private Local Project • Corman RR Bridge over Cmblnd Rv. Phase 1 – est. $1.1M Enhan. Private & Local ; PE 2010 Const 2011 Phase 2 – est. $1.7M Enhan. P & L; PE 2010 Const 2011 +

  15. State/Local Project Congestion /Safety Intersections signalization, geometric, turn lanes, striping ect. • US41-A By Pass @ SR48/13 –CONST 2011 • SR112/Madison St. @ SR374/Richview – CONST 2011 • US79/SR13/Wilma Rudolph Blvd. @ Dunbar Cave – CONST 2011 • SR112/Madison St. @ SR76/Connector – CONST 2011 - TIP showing CMAQ $2.3M total all 4

  16. State/Local Project • OUTLAWFIELD IMPROVEMENTS Land Purchase for Runway 35 – Completed April 2007 Pavement Rehab for Intersection of Runway $700K Life Flight Utilites & Const Pad completed Jan. 09 NW Property T-hanger, taxi way, parking lot $1.3M New Terminal Bldg. CONST Spring 2011 aprx $4.5M no grant- Cv/MC

  17. LOCAL PROJECT • Dunbar Cave Rd @ SR237Rossview Realignment/widen • PE/** Env 2010 TIP w L-STP aprx. $436K • Row 2012 TIP L-STP aprx. $800K • Const 2013 TIP L-STP aprx. 6.2M

  18. STATE/LOCALPROJECT • Safety Intersection Improvements geometric, turn lanes, striping ect. Sango Rd @ SR76 - PE 2011 w TIP $75K L- STP - CONST w TIP $625 L-STP

  19. LOCAL PROJECT Oakland Rd @ SR13 Safety concerns Realignment aprx. 1000’ n • PE 2011 TIP showing $100K L-STP • ROW 2011 TIP $750K L-STP • CONST 2012 TIP $850K L-STP

  20. STATE PROJECT • I-24 Interchanges Ext. 1, 4, 8 & 11 On going - 8 hr ramp volumes - staking on ramps back to I-24 - delays on mainlines SR48/13/237/76 - const 2 lane ramp, signals w modif. - new interchange

  21. RIVER PORT DEVELOPMENT HEMATITE ZINC PLANT RED RIVER INGRAM MATERIALS TUCKER/MATTHEWS

  22. AIR QUALITY • PM2.5 Dust, Soot & particles too small to see. EPA’s std. 65 mgpcm to 35 mgpcm • Ozone Ground-level EPA’s std. from 0.084 to 0.070 – 0.060 ppm • Reduce premature deaths, heart and lung disease