1 / 15

Continual Improvements on Preparation for SNM Experiments on Z Contamination Control System

S a n d i a N a t i o n a l L a b o r a t o r i e s. February 23, 2011. Continual Improvements on Preparation for SNM Experiments on Z Contamination Control System Final Design Review. Matt Christison, Scot Lewis. Concept of Operations. Pre-SNM (Today). Concept of Operations.

abie
Download Presentation

Continual Improvements on Preparation for SNM Experiments on Z Contamination Control System

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. S a n d i a N a t i o n a l L a b o r a t o r i e s February 23, 2011 Continual Improvements on Preparation for SNM Experiments on Z Contamination Control System Final Design Review Matt Christison, Scot Lewis

  2. Concept of Operations Pre-SNM (Today)

  3. Concept of Operations (no cap installed) Top Tent main section is installed SNM Top Lids installed SNM Shot hardware is installed SNM Bottom Lid is installed Bottom tent installed

  4. Concept of Operations Removable “sunroof” interfaces to lid using Velcro Flat Lid installed with tent in place (there are 2 configurations of the lid) SHOT

  5. Concept of Operations Top tent completed Top Air Sample Top Cryo Swipes Bottom Air Sample Bottom Side Entry and Swipes To Blowers

  6. Concept of Operations Survey Results: All Clear Top SNM Lids Removed Modified Top Tent Lid Installed Top Area Swipes Removable “sunroof” Replaced with Tent Sleeve (swap “sunroof” out on Highbay floor) To Blowers

  7. Concept of Operations Survey Results: All Clear Lifting Bridle Installed Inner Sleeve Installed Modified Top Tent Sleeve Unrolled and Taped to ECC To Blowers

  8. Concept of Operations Primary is lifted and the underside is swiped Floor liner is installed under Primary

  9. Concept of Operations Survey Results: All Clear Tent Lid can be Removed Tent Removal can Commence

  10. Concept of Operations Primary Bagged, and Removed to Separation Tent OR MBA Cage Tent is designed to work using existing Primary bagout method if desired

  11. Concept of Operations Center Section Returned to Pre-Shot Configuration

  12. Concept of Operations ECC + Primary Assembly are hoisted to Separation Enclosure through ceiling OR Moved to Pallet, then hand trucked to MBA Cage New Pallet is Prepped in Separation Enclosure

  13. Concept of Operations Ceiling Port is closed (Velcro/Zipper) ECC Sleeve is placed over Primary *New cross members not shown

  14. Concept of Operations ECC is removed from UCC Once UCC is Deemed Clean, Ceiling port is opened for UCC removal (ECC Sleeve) UCC/ECC Swipes *New cross members not shown

  15. Separation Enclosure Crane Access Utility Door