River Corridor Closure Project

River Corridor Closure Project. Safety • People • Results. End State and Final Closure. Jeff A Lerch Manager, Long Term Stewardship. June 1 and 2, 2006. Major Scope Elements. Orphan Site Evaluations Remedial Action Reports Long Term Stewardship Plan Independent Closure Reviews

abner
Download Presentation

River Corridor Closure Project

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. River CorridorClosure Project Safety • People • Results End State and Final Closure Jeff A Lerch Manager, Long Term Stewardship June 1 and 2, 2006

  2. Major Scope Elements • Orphan Site Evaluations • Remedial Action Reports • Long Term Stewardship Plan • Independent Closure Reviews • Data Management Systems

  3. Orphan Sites Evaluations • Orphan Site: Manmade features, items, or activity areas within the River Corridor that 1) meet the TPA MP-14 criteria for waste site identification, 2) are not identified for characterization or cleanup within the regulatory framework (e.g., RODs and work plans) • Orphan Site Evaluation: A systematic approach involving historical review and field walkdown activities to identify new source unit waste sites within the River Corridor that are not identified for characterization or cleanup within the regulatory framework (e.g., RODs and work plans). Results of each orphan site evaluation are presented in a summary report (contract deliverable C.2.10) including a description of the process and a listing of identified orphan sites.

  4. Orphan Sites Evaluations (continued) • Evaluations conducted for each Reactor/Operational Area and Inter Areas • Historical review • Field walkdown • Gap analysis • Historical/Field integration • Summary report • Upland Inter Areas includes flight survey subtask

  5. Orphan Sites Evaluations (continued) • Reactor/Operational area evaluations sequenced based on anticipated field remediation schedule • 100-D, 100-IU, 100-H, 100-K, 100-N, 300-FF-2, 400 Area • Upland Inter areas scheduled to begin 2008 • Evaluations complete for 100-B/C, 300-FF-1, 100-F

  6. Remedial Action Reports • Documents completion of remedial actions established in ROD • Chronology • Construction (remedial action) summary • Performance Standards • O&M/Institutional controls • Cost summary Does not include “No Further Action” determination • Required for each OU – 14 total (deliverable C.2.11.2) • Sequenced based on anticipated field remediation schedule • Report enhancement planned to support final cleanup decision strategy

  7. Long-Term Stewardship Plans Criteria to be met for long-term stewardship and a proposed Finding of Suitability to Transfer in accordance with CERCLA Section 120(h) • Identifies criteria to ensure land use consistent with exposure scenarios following remedial action • Record keeping and information management • Monitoring and surveillance • Access control and postings • Does not establish cleanup objectives or exposure scenarios

  8. Long-Term Stewardship Plans • Draft Plan – October 2007 (deliverable C.2.11.1) • Final Plan – 90 days before completion of contract requirements (deliverable C.2.11.3) • DOE approval is a condition precedent to completion of contract requirements

  9. Independent Closure Review Conduct closure review with independent experts to assure implemented remedies meet ROD requirements and that No Further Action Is Needed to Protect Human Health and the Environment • Separate reviews for 100 Area & 300 Area • Scheduled near anticipated contract end (~2012) • Pilot Closure review planned in mid-2007 • 100-B/C likely choice

  10. Data Management Systems • Overlies all WCH field projects • Supports internal and external database tools • GIS, SDT, ENRE, risk assessment • HEIS, WIDS • Key long-term stewardship deliverable elements