CS 260 Build Sequence – Summary . 2. 1. 2. 1. 2. 3. CRN. CRN. CRN. LH. LH. LH. RH. RH. RH. CS 260 Build Sequence – Day 1. Position 1 Drill BCD/RH Door, pre-fit LH Door, Drill Keel frames, Drill/Install RH frames, pre-fit LH frames. Position 2
E N D
CS 260 Build Sequence – Summary 2 1 2 1 2 3 CRN CRN CRN LH LH LH RH RH RH
CS 260 Build Sequence – Day 1 • Position 1 • Drill BCD/RH Door, pre-fit LH Door, Drill Keel frames, Drill/Install RH frames, pre-fit LH frames Position 2 • Install STR22, Door Straps, pre-fit BCD/RH Door • Install drill plates, pre-fit keel/RH frames, drill stringer end fittings CRN CRN LH LH RH RH
CS 260 Build Sequence – Day 2 Position 2 • Deburr BCD Position 1 • Keel FRM full install, pre-fit LH Door • Drill LH Door, Install RH Door, Pre-fit crown frames, install RH frames, Stringer insulation, Stringer end fittings • Install LH Door, RH sills/9G/shear tie, pre-fit crown frames, Stringer insulation, Stringer end fittings CRN CRN LH RH RH LH
CS 260 Build Sequence – Day 3 Position 2 • Install BCD, RH clips/splice, Install crown/keel/side frames Position 3 • LH splices, crown/keel frame install, • LH splice/sills, RH splice, crown/keel frame install, stringer end fitting CRN CRN LH LH RH RH
CS 260 Build Sequence – Day 4 • Position 3 • RH/LH/BCD splices/sills/shear ties, install keel frames • Shear ties, 9G fittings, BCD splices, intercostals, stringer end fittings • LH/RH window frames, shake, unload barrel CRN LH RH