Bond Construction Update Citizens’ Oversight Committee. Cordoba Corporation. Long Beach Community College District April 21, 2008. BUILDING TOMORROW TODAY. Agenda. Completed Construction Projects Current & Upcoming Construction Projects South Quad Complex Structure
E N D
Bond Construction UpdateCitizens’ Oversight Committee Cordoba Corporation Long Beach Community College District April 21, 2008 BUILDING TOMORROW TODAY
Agenda • Completed Construction Projects • Current & Upcoming Construction Projects • South Quad Complex Structure • LAC Central Plant Structure • LAC Learning Resources Center – Structure • LAC Building A, Student Services Retrofit • PCC Central Plant • PCC Learning Resources Center • PCC Industrial Tech Phase 1 • PCC MDAB (Multi-Disciplinary Administration Building) • Q & A
Completed Construction Projects Various Projects – Completed in 2006 & 2007 • PCC Industrial Technology Center Phase 2 – 7/07 • PCC Central Plant Utilities, LAC Central Plant & SQC Utilities – 6/07 • LAC/LRC Interim – 5/07 • East Campus Demo – 12/06 • LAC Men’s Gym Façade Replacement (FEMA & Insurance Funded) – 8/06 • LAC/LRC Utilities – 6/06 • PCC CDC – 4/06 • Men’s Gym Boiler Replacement – 4/06 • LAC Athletic Field – 3/06 • District Facilities & Warehouse Complex – 1/06
LAC Facility Site Plan l i b e r a l a r t s
Current and UpcomingConstruction Projects LAC Central Plant – Structure • Part of Infrastructure Master Plan Improvements • Awarded to Siemens on DBOM Contract • Construction 82% Complete • Completion Anticipated Summer 2008
Current and UpcomingConstruction Projects Construction 55% Complete Combined into Single Construction Phase Completion Anticipated December 2008 LAC/Learning Resources Center – Structure
Current and UpcomingConstruction Projects Construction Approx. 52% Complete Additional Modern Classrooms, Multi-purpose Rm., Offices, etc. Shifts Campus Center South of Carson off Lew Davis Completion Anticipated December 2008 South Quad Complex Structure (Bid Pkg. #3)
Current and UpcomingConstruction Projects Martinez Architects received Board Approval as the Architect of Record Contract was negotiated/signed and Notice to Proceed was issued Programming work began on April 10, 2008 LAC Building A – Student Services Retrofit
PCC Facility Site Plan p a c i f i c c o a s t
Current and UpcomingConstruction Projects Part of Infrastructure Master Plan Improvements Early Utility Package Construction Complete DBOM Contract Awarded to Siemens; Finalizing Value Engineering Negotiations Construction Approximately 36% Complete Completion Anticipated Summer 2008 PCC Central Plant
Current and UpcomingConstruction Projects PCC Learning Resources Center • Construction 78% Complete • Modern Facility with Computer Lab and Multimedia • New Facility • Bridge to Bldg. EE • Completion Anticipated July/August 2008
Current and UpcomingConstruction Projects PCC Industrial Technology Center Phase 1 • Replaces Existing Antiquated Structures • Construction is 12% Complete • Modern Facility Houses Machine Tool and Welding Departments • New Northern Face of the Campus • Completion Anticipated Spring 2009
Current and UpcomingConstruction Projects PCC MDAB (Multi-Disciplinary Academic Building) • Programming is completed and submitted to the State for Approval • Schematic Design was completed in February 2008
QUESTIONS & ANSWERS Cordoba Corporation Prepared by Bond Management Team April 21, 2008 BUILDING TOMORROW TODAY