1 / 15

Bond Construction Update Citizens’ Oversight Committee

Bond Construction Update Citizens’ Oversight Committee. Cordoba Corporation. Long Beach Community College District April 21, 2008. BUILDING  TOMORROW  TODAY. Agenda. Completed Construction Projects Current & Upcoming Construction Projects South Quad Complex Structure

adrian-goff
Download Presentation

Bond Construction Update Citizens’ Oversight Committee

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Bond Construction UpdateCitizens’ Oversight Committee Cordoba Corporation Long Beach Community College District April 21, 2008 BUILDING TOMORROW TODAY

  2. Agenda • Completed Construction Projects • Current & Upcoming Construction Projects • South Quad Complex Structure • LAC Central Plant Structure • LAC Learning Resources Center – Structure • LAC Building A, Student Services Retrofit • PCC Central Plant • PCC Learning Resources Center • PCC Industrial Tech Phase 1 • PCC MDAB (Multi-Disciplinary Administration Building) • Q & A

  3. Construction Progress

  4. Completed Construction Projects Various Projects – Completed in 2006 & 2007 • PCC Industrial Technology Center Phase 2 – 7/07 • PCC Central Plant Utilities, LAC Central Plant & SQC Utilities – 6/07 • LAC/LRC Interim – 5/07 • East Campus Demo – 12/06 • LAC Men’s Gym Façade Replacement (FEMA & Insurance Funded) – 8/06 • LAC/LRC Utilities – 6/06 • PCC CDC – 4/06 • Men’s Gym Boiler Replacement – 4/06 • LAC Athletic Field – 3/06 • District Facilities & Warehouse Complex – 1/06

  5. LAC Facility Site Plan l i b e r a l a r t s

  6. Current and UpcomingConstruction Projects LAC Central Plant – Structure • Part of Infrastructure Master Plan Improvements • Awarded to Siemens on DBOM Contract • Construction 82% Complete • Completion Anticipated Summer 2008

  7. Current and UpcomingConstruction Projects Construction 55% Complete Combined into Single Construction Phase Completion Anticipated December 2008 LAC/Learning Resources Center – Structure

  8. Current and UpcomingConstruction Projects Construction Approx. 52% Complete Additional Modern Classrooms, Multi-purpose Rm., Offices, etc. Shifts Campus Center South of Carson off Lew Davis Completion Anticipated December 2008 South Quad Complex Structure (Bid Pkg. #3)

  9. Current and UpcomingConstruction Projects Martinez Architects received Board Approval as the Architect of Record Contract was negotiated/signed and Notice to Proceed was issued Programming work began on April 10, 2008 LAC Building A – Student Services Retrofit

  10. PCC Facility Site Plan p a c i f i c c o a s t

  11. Current and UpcomingConstruction Projects Part of Infrastructure Master Plan Improvements Early Utility Package Construction Complete DBOM Contract Awarded to Siemens; Finalizing Value Engineering Negotiations Construction Approximately 36% Complete Completion Anticipated Summer 2008 PCC Central Plant

  12. Current and UpcomingConstruction Projects PCC Learning Resources Center • Construction 78% Complete • Modern Facility with Computer Lab and Multimedia • New Facility • Bridge to Bldg. EE • Completion Anticipated July/August 2008

  13. Current and UpcomingConstruction Projects PCC Industrial Technology Center Phase 1 • Replaces Existing Antiquated Structures • Construction is 12% Complete • Modern Facility Houses Machine Tool and Welding Departments • New Northern Face of the Campus • Completion Anticipated Spring 2009

  14. Current and UpcomingConstruction Projects PCC MDAB (Multi-Disciplinary Academic Building) • Programming is completed and submitted to the State for Approval • Schematic Design was completed in February 2008

  15. QUESTIONS & ANSWERS Cordoba Corporation Prepared by Bond Management Team April 21, 2008 BUILDING TOMORROW TODAY

More Related