1 / 14

BOND PROGRAM UPDATE Building Tomorrow Today

BOND PROGRAM UPDATE Building Tomorrow Today. Long Beach Community College District Citizens’ Oversight Meeting. October 9, 2006. AGENDA. Quarterly Expenditure Report Contractor Outreach Update Completed Construction Projects Current & Upcoming Construction Projects

eytan
Download Presentation

BOND PROGRAM UPDATE Building Tomorrow Today

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. BOND PROGRAM UPDATEBuilding Tomorrow Today Long Beach Community College District Citizens’ Oversight Meeting October 9, 2006

  2. AGENDA • Quarterly Expenditure Report • Contractor Outreach Update • Completed Construction Projects • Current & Upcoming Construction Projects • South Quad Complex – Bid #2 • LAC Central Plant Structure • LAC Learning Resource Center - Interim • South Quad Complex Structure • PCC Central Plant & Utilities • PCC Learning Resource Center • PCC Industrial Tech Phase 1 • PCC Industrial Tech Phase 2 • PCC Economic Development & Culinary Arts Facility • Q & A

  3. QUARTERLY EXPENDITURE REPORT Budget * The expenditure amounts reflected above in the 6/30/06 and 9/30/06 columns were generated from PeopleSoft as of September 30, 2006. All other Budget and Committed Amounts are extracted from Expedition. Therefore, column (c) “Accrued Payments” of the attached report reflects the un-audited payment requisitions tracked in Expedition and thereby will not be the same as reported above.

  4. COMPLETED CONSTRUCTION PROJECTS Various Projects • PCC CDC – 4/06 • District Facilities & Warehouse Complex – Opened 1/17/06 • Men’s Gym Boiler Replacement – 4/06 • PCC MM/NN Lighting Upgrade – 4/05 • LAC Athletic Field – 3/06 • South Quad Complex Bid Pkg. #1 – 12/05 • LAC/LRC Utilities–6/06 • LAC Men’s Gym Façade Replacement (FEMA & Insurance Funded)

  5. CURRENT & UPCOMINGCONSTRUCTION PROJECTS South Quad Complex – Bid Package #2 • Construction 80% Complete • Relocation of Water Main and Reclaimed Water Lines • Coordinated with Central Plant • Relocates Major Utilities Out of Golf Mall • Clears Way for Structures

  6. CURRENT & UPCOMINGCONSTRUCTION PROJECTS LAC Central Plant – Structure • In Plan Check • Part of Infrastructure Master Plan Improvements • Early Utility Package Under Construction • Anticipate Bidding Fall ‘06 • Soliciting DBOM Proposals With Energy Incentives

  7. CURRENT & UPCOMINGCONSTRUCTION PROJECTS LAC/Learning Resource Center – Interim Facilities • In Plan Check • Modular Buildings in Procurement • Utility Installation Complete Under Previous Phase (Bid Pkg. #1)

  8. CURRENT & UPCOMINGCONSTRUCTION PROJECTS South Quad Complex Structure (Bid Pkg. #3) • Construction Begun; Grading Underway • Overlaps Central Plant Early Piping Due to Utility Conflicts • Additional Modern Classrooms, Multi-purpose Rm., Offices, etc.

  9. CURRENT & UPCOMINGCONSTRUCTION PROJECTS PCC Central Plant & Utilities • Part of Infrastructure Master Plan Improvements • Early Utility Package Under Construction; Approx. 69% Complete. • Allows Utility Installation while Structure is in Plan Check • Clears Way for Structure • Soliciting DBOM Proposals with Energy Incentives

  10. CURRENT & UPCOMINGCONSTRUCTION PROJECTS PCC Learning Resources Center • In Plan Check • Construction 1st Quarter 2007 • Modern Facility with Computer Lab and Multimedia • Expanded Facility

  11. CURRENT & UPCOMINGCONSTRUCTION PROJECTS PCC Industrial Technology Center Phase 1 • Replaces Existing Antiquated Structures • Bid 3rd Quarter 2006 • Modern Facility Houses Machine Tools and Welding Depts. • Campus “Bookend” • S.E. Interim Bungalow Construction Underway to Clear Tech 1 Site (80% Complete)

  12. CURRENT & UPCOMINGCONSTRUCTION PROJECTS PCC Industrial Technology Center Phase 2 • Replaces Existing Antiquated Structures • Construction Underway; Approx. 23% Complete • Modern Facility Houses Aviation and Automotive Depts. • Impacted by DF&WC

  13. CURRENT & UPCOMINGCONSTRUCTION PROJECTS PCC East Campus Economic Development & Culinary Arts Facility - Demolition • Demolition Underway; Hazmat Abatement Complete • Structure to Bid Spring 2007

  14. QUESTIONS & ANSWERS Prepared By: Bond Management Team October 9, 2006 BUILDING TOMORROWTODAY

More Related