ARRA Project Oversight 2010 WTBA Contractor/Engineer Conference 1/21/2010
ARRA Project Oversight Structure • Project team • Region/Bureau Change Management Team • Division Change Management Team • Executive Change Management Team – Oversight Committee 2010 WTBA Contractor/Engineer Conference
ARRA Project Oversight Key Elements • Scope/cost change management • Project closeout control 2010 WTBA Contractor/Engineer Conference
Scope/Cost Change Management • Each project will have a set cost • Contract amount + • Construction delivery + • Construction reserve • Project cost must be monitored by anticipating • Overruns/underruns • Scope changes • Contract modifications 2010 WTBA Contractor/Engineer Conference
Scope/Cost Change Management • Scope/Cost strategies: • Shortening project limits • Eliminating low risk work • Considering contractor cost saving proposals • Strategies should be developed early in a project and saved in a ‘cost savings contingency plan’ • Strategies should ‘not’ be included that impact overall quality or reduce safety objectives 2010 WTBA Contractor/Engineer Conference
Change Management Request Form 2010 WTBA Contractor/Engineer Conference
Project Closeout Control • Project Closeout Goals • Finals to project manager 1 month after project completion • Tentative/final estimate – 4 months after Final Acceptance • Final Estimate – 6 months after Final Acceptance 2010 WTBA Contractor/Engineer Conference
Project Closeout Control • To meet project closeout goals • Quantity Management • Measure as items are completed • Complete earthwork comps as work is done • Verify quantities with contractor • Materials • Require tests/certifications prior to installation • Dispute/Claim Avoidance • Resolve disputes as you go 2010 WTBA Contractor/Engineer Conference
ARRA Project Summary To Date 2009 Construction 2010 Construction Planned Let Projects – Planned Let Dollars – 2009 Carryover Projects – 2009 Carryover Dollars – 147 Projects $147 Million 44 Projects $140Million Let Projects – Let Dollars – Completed Projects– Completed Dollars – 133 Projects $320 Million 89 Projects $180 Million 2010 WTBA Contractor/Engineer Conference