1 / 10

ARRA Project Oversight

ARRA Project Oversight. 2010 WTBA Contractor/Engineer Conference 1/21/2010. ARRA Project Oversight Structure. Project team Region/Bureau Change Management Team Division Change Management Team Executive Change Management Team – Oversight Committee. ARRA Project Oversight Key Elements.

ashley
Download Presentation

ARRA Project Oversight

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. ARRA Project Oversight 2010 WTBA Contractor/Engineer Conference 1/21/2010

  2. ARRA Project Oversight Structure • Project team • Region/Bureau Change Management Team • Division Change Management Team • Executive Change Management Team – Oversight Committee 2010 WTBA Contractor/Engineer Conference

  3. ARRA Project Oversight Key Elements • Scope/cost change management • Project closeout control 2010 WTBA Contractor/Engineer Conference

  4. Scope/Cost Change Management • Each project will have a set cost • Contract amount + • Construction delivery + • Construction reserve • Project cost must be monitored by anticipating • Overruns/underruns • Scope changes • Contract modifications 2010 WTBA Contractor/Engineer Conference

  5. Scope/Cost Change Management • Scope/Cost strategies: • Shortening project limits • Eliminating low risk work • Considering contractor cost saving proposals • Strategies should be developed early in a project and saved in a ‘cost savings contingency plan’ • Strategies should ‘not’ be included that impact overall quality or reduce safety objectives 2010 WTBA Contractor/Engineer Conference

  6. ARRA Training - July 2009

  7. Change Management Request Form 2010 WTBA Contractor/Engineer Conference

  8. Project Closeout Control • Project Closeout Goals • Finals to project manager 1 month after project completion • Tentative/final estimate – 4 months after Final Acceptance • Final Estimate – 6 months after Final Acceptance 2010 WTBA Contractor/Engineer Conference

  9. Project Closeout Control • To meet project closeout goals • Quantity Management • Measure as items are completed • Complete earthwork comps as work is done • Verify quantities with contractor • Materials • Require tests/certifications prior to installation • Dispute/Claim Avoidance • Resolve disputes as you go 2010 WTBA Contractor/Engineer Conference

  10. ARRA Project Summary To Date 2009 Construction 2010 Construction Planned Let Projects – Planned Let Dollars – 2009 Carryover Projects – 2009 Carryover Dollars – 147 Projects $147 Million 44 Projects $140Million Let Projects – Let Dollars – Completed Projects– Completed Dollars – 133 Projects $320 Million 89 Projects $180 Million 2010 WTBA Contractor/Engineer Conference

More Related