An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Presentation of Project’s Timetable and Partners’ Responsibilities National Technical University of Athens Unit of Environmental Science and Technology By: Simos Malamis Athens, 25 October 2005 Kick-off MeetingLife-Environment Project Sustainable Construction in Public and Private Works through IPP Approach (SUSCON)

  2. General Remarks Project duration = 36 months Start date: 01/10/2005 End-date: 30/09/2008 7 Tasks in Total implemented by 6 partners

  3. Task 1: Task management & reporting to the EC • Action 1:Task Management • NTUA is legally & financially responsible for the project implementation & the management of the tasks • All partners shall participate in the coordination group • Action 2: Reporting to the EC • NTUA is responsible for submitting reports to the EC • Action 3: Project Meetings • 3 in Greece & 3 in Cyprus + kick-off (NTUA) • Action 4: Monitoring & Evaluation • All partners through the co-ordination group • NTUA & EPTA shall develop the performance indicators • Action 5:Advisory Board • EPTA and UCY are responsible for the organisation and the co-ordination of the Advisory Board in each country.

  4. Task 2: Analysis and Documentation of the Construction Sector in Greece, Cyprus & EU level • Action 1:Analysis of the construction sector in Greece & Cyprus • Co-ordinated & implemented by EPTA and EDRASIS (Greece) and by CYBARCO and ETEK (Cyprus) • Action 2:Environmental Impact Assessment from the construction activities • Implemented by EPTA

  5. Task 3: LCA in two construction activities • Action 1: Data collection for the two construction categories • EDRASIS & CYBARCO shall provide data • NTUA responsible for the co-ordination • Action 2:Conduction of a LCA study • NTUA is responsible

  6. Task 4: Development of eco-design criteria • Action 1: General assessment of eco-design strategies • EPTA is responsible • Action 2: • Creation of an eco-design matrix and an eco-design checklist • NTUA is responsible • Action 3:Development of eco-design criteria • UCY responsible

  7. Task 5: Application of eco-design criteria in construction • Action 1: Software production for the evaluation of the environmental performance of construction works • NTUA is responsible for subcontracting the software design • Action 2:Application of the software to the construction projects in the companies • EDRASIS & CYBARCO shall apply the software tool to their construction projects • Comparison of their environmental performance • Action 3:Drafting National Institutional Arrangements • Participation of all partners

  8. Task 6: Online Database for the Construction Industry • Action 1:General Specifications and functional requirements • UCY is responsible • Action 2:Web-site structure design and implementation • NTUA & UCY • Action 3:Creation and Operation of the database • NTUA shall sub-contract the data-base development • UCY responsible for the continuous up-grading of the data-base

  9. Task 7:Dissemination Activities • Action 1:Web-site design & development • NTUA is responsible; all partners shall provide input for updating the web-page • Action 2:Organization of a national annual competition for ‘sustainable construction project’ • EPTA & UCY • Action 3a:Organization of one-day informational events • EDRASIS and CYBARCO • Action 3b: Final Conference Organization • Co-ordination by NTUA & EDRASIS with all partners involved • Action 4:Newsletters • Template development by EPTA • NTUA responsible for their production • All partners involved in their distribution • Action 5:Advertisement Campaign • All partners involved

  10. One task manager shall be assigned for each Task Each task manager shall be responsible for the successful and on-time submission of the Task