Energy Efficiency Opportunities KML Expansion Project August 2013

Energy Efficiency Opportunities KML Expansion Project August 2013. Table of Contents. About Karara Iron Ore Basics Base Plant – Mine and Concentrator KML’s Magnetite Process Requirements for a Viable Project Operating Cost The Approach The Process and Outcomes Overall Outcome In Closing.

aggie
Download Presentation

Energy Efficiency Opportunities KML Expansion Project August 2013

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Energy Efficiency OpportunitiesKML Expansion ProjectAugust 2013

  2. Table of Contents About Karara Iron Ore Basics Base Plant – Mine and Concentrator KML’s Magnetite Process Requirements for a Viable Project Operating Cost The Approach The Process and Outcomes Overall Outcome In Closing
  3. About Karara Located in the Mid-West Region of Western Australia, 215 km east-southeast of Geraldton and 320km north-northeast of Perth Australia’s second magnetite project World class project with ~2.5bt resource and 30+ year mine life A Joint Venture and Partnership between Gindalbie and Ansteel
  4. Iron Ore Basics Not all iron ore projects are the same Hematite Magnetite Hematite Reddish – black mineral Chemical formula Fe2O3 Key property is that the mineral is Non Magnetic Found in large high grade deposits 55-62% Fe Low impurities – but these vary depending on the ore body No two ore bodies are the same Often referred to as DSO – Direct Shipping Ore Mining, crushing and screening required to produce lump and fines products
  5. Iron Ore Basics Magnetite Black grey mineral Chemical Formula Fe3O4 Occurs with other minerals, predominantly silica bearing minerals Ore grades vary 10-30% Fe KML ore averages 36.5% Fe Not commercially saleable in the raw state Key physical property is that the mineral is Magnetic Intensive processing is required to produce a commercially saleable product Liberation size 25-35 microns High energy input required to grind the ore Magnetite concentrates typically >64% Fe KML’s magnetite premium products 68% Fe, 4.75% SiO2 with low other impurities
  6. Base Plant - Mine and Concentrator Mining at a rate of 30mtpa, one of WA’s single biggest mining operations Commissioning completed and ramp-up well advanced Ability to produce 8mtpa premium magnetite concentrate
  7. Base Plant - Mine and Concentrator Flythrough
  8. The Magnetite Process High energy intensive process KML’s magnetite process involves the following unit processes: Primary crushing Secondary crushing and screening High Pressure Grinding (HPGR) and screening Rougher Magnetic separation Primary Grinding Intermediate Magnetic separation Fine Grinding Reverse flotation, regrind Concentrate thickening and filtration Tails thickening, filtration and stacking
  9. Requirements for a Viable Magnetite Project Ore body Large ore body - long life of mine to support the capital expenditure High magnetite grade with low impurities 36% Fe SiO2, AlO3 High metallurgical recovery Capable of generating a product that is commercially saleable 68% Fe, 4.75% SiO2 and low impurities Quality will dictate if the business is a price maker or taker Access to infrastructure Power Water Rail Port
  10. Requirements for a Viable Magnetite Project Financial Operating Cost < Product Revenue Payback capital (including interest) in an acceptable time Return value to shareholders Price volatility
  11. The Approach KML’s Approach Establish the overall expansion strategy for the company Develop a design concept Develop a design approach Establish the Owner’s team Expansion Strategy Board mandate was to expand magnetite production to >30Mtpa by approximately 2020 Design Concept Design a plant that is readily expandable in modules whilst causing minimal interruption to the operating plant during construction, commissioning and operation
  12. The Approach Design Approach Build on the “groups” collective design, construction and commissioning experience Learn from past mistakes Undertake all activities during the Feasibility Study to ensure a seamless transition into FEED and detailed engineering design (DED) No shortcuts, dot the “i”’s and cross the “t” approach Leverage of the current engineering design as far as practical Specifications, detailed drawings, 3D model, calculations Consider constructability during design Be able to construct without impacting on the operating plant Consider value engineering opportunities to reduce capital cost, improve operability and reduce unit operating cost.
  13. The Approach
  14. The Approach KML’s Owners Team Establish a core multidiscipline engineering team to manage the execution of the works Headed by the Project Director, the core team positions are Project Director Project Manager Principal Process Engineer Principal Mechanical Engineer Manager Optimisation Principal Civil / Structural Engineer The competency of the Owner’s team is key to delivering the project on-budget, on-schedule and to the required quality. As a project moves from the study phase into execution, the Owner’s team expands accordingly to deliver the project. Legal and Commercial Approvals Document control Scheduling Cost Control
  15. The Process Staged program centered around the evaluation of the Base Plant and equipment in order to identify value adding opportunities to reduce capital and operating costs Program of work Base Plant expandability review Concentrator process design review Mining – In pit crushing and conveying study Port and Rail capacity modeling Metallurgical testwork and simulations Value Engineering Definitive Feasibility Study
  16. The Process Base Plant Expandability Review High level expandability review of the Base Plant to ascertain if the plant can be upgraded or expanded to achieve the overall expansion strategy Outcomes A tightly constrained plant layout. Expansion of the mine concentrator is physically constrained by; Run of Mine pad to the East Rail to the West Tailings disposal to the South Incoming High Voltage power to the North
  17. The Process
  18. The Process Outcomes Bottlenecks identified in the process flowsheet. Bottlenecks are typically major capital equipment that cannot be easily upgraded, replaced by larger equipment, or additional equipment installed such as; High pressure grinding rolls Ball mills Concentrate and tailings thickening
  19. The Process Concentrator Process Design Review Detailed review of the Basis of Design to verify and establish a suitable BOD for the expansion The review involved a review of available data and additional metallurgical testwork Outcome(s) Modified process Basis of Design Simplified process flowsheet
  20. The Process In Pit Crushing and Conveying (IPCC) External consultant engaged to assess IPCC compared to conventional Haul To Surface (HTS) operation Previous study completed by Coffey Mining in 2008 reported a significant operatig cost saving for IPCC compared to HTS Cost savings increase with both rate of production and also in the event that fuel, tyres and labour costs increase at a rate in excess of other operational costs IPCC options considered Start 2016 stage 2 Expansion Start 2018 stage 3 Expansion
  21. The Process Port and Rail Capacity Modeling External consultancy engaged to model the rail and port system to estimate the true capacity at the port 16Mtpa capacity based on 60kt shipments at 100hrs average vessel TAT. KML’s modeling shows 18-20 Mtpa using combination of larger vessels - Panamax/Kamsarmax.
  22. The Process Value Engineering External engineering consultant engaged to: Rationalise a plant layout that is expandable with minimal interruption to the operating plant Identify, assess and rationalise equipment selection by considering upsize opportunities that were not available during the original design Reduce capital cost Reduce operating cost Improve performance and operability
  23. The Process Outcomes Improved concentrator layout Modular and expandable design to meet expansion schedule Engineering easily duplicated at minimal cost Improved maintainability Within existing KML tenements Fully incorporated magnetite and hematite stockpile, reclaim and train load out facility Process flowsheet retained with equipment alternatives and up-size opportunities considered Reduced flowsheet complexity Improved operability and maintainability Lower operating cost Lower capital cost
  24. The Process HPGR’s confirmed as the lowest power consumer compared to other commercially available equipment such as; SAG Mills AG mills Increasing the Ball Mill transfer size from the original design value of 55 µm to 120 µm and allowing for additional power in the Tower Mills reduces the overall installed power requirement by approximately 8.6 MW
  25. The Process Definitive Feasibility Study (DFS) External engineering consultant engaged to undertake the DFS Outcomes Robust modular design to meet the overall expansion methodology Capital and Operating cost estimate to 15± accuracy Approx 20% lower operating cost compared to the Base Plant due to improved design Economies of scale due to better use of existing infrastructure and contacts Improved utilisation and distribution of high power consuming equipment in the process plant
  26. Overall Outcome Viable plant design that meets the project objectices
  27. In Closing Mining projects are margin driven business The cost of production must be significantly lower than product revenue Efficiency (energy, process) is a key driver in the design phase of every project Lowest cost of production targeted at all times Highest operating cost area are the focus Improvement in efficiency for existing mining operations is difficult due to; High sunk capital cost Efficiency typically comes from economies of scale Bigger equipment Requires capital expenditure that needs to meet investment hurdles