An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. ICT 2011 Reliability Assessment and Construction Plan Evaluation Entergy Transmission SummitAugust 11, 2010SheratonNew Orleans, Louisiana

  2. Overview • Background • Scope • Draft Construction Plan • Results

  3. Background • Reliability Assessment is performed pursuant to Entergy’s Open Access Transmission Tariff (OATT) Attachment K. • Objectives: • Assess of the ability of the Entergy transmission system to perform according to the Planning Criteria. • Evaluate the Construction Plan’s ability to mitigate any performance deficiencies found. • Provide basis for development of the Base Plan.

  4. Background

  5. Background • Draft report was made available for stakeholder review and comment • Posted on Entergy’s OASIS July 1, 2010 • Presentation made at LTTIWG July 21, 2010 • Final report is posted on Entergy’s OASIS. • Detailed spreadsheets not included in report are posted on Entergy’s oasis • Background models, data, and other information is posted on Entergy’s oasis

  6. Entergy Planning Criteria • Planning Criteria • NERC Planning Standards • SERC Supplements • Entergy’s Local Planning Criteria • Entergy’s Business Practices (Planning Guidelines) • Posted on Entergy’s OASIS • NERC Planning Standards being revised

  7. Reliability Assessment Scope • Models (2009 Series Update 1) • Near-Term Period: Summer & Winter 2012 & 2016 • Longer-Term Period: Summer 2019 • Construction Plan Projects • Initial Scan: Approved Projects from 2010-12 Construction Plan (CP) • CP Evaluation: Approved and Proposed Projects from 2011-13 CP • System Intact Review – Category A • Contingency Scan – Category B • Breaker-to-Breaker analysis • ICT’s 100MW rule (Bus-to-Bus analysis)

  8. Reliability Assessment Scope (cont) • Sensitivities • Specific Load Pocket Criteria • Low Hydro Sensitivity

  9. Entergy’s Draft Construction Plan 2011-2013 • May 7, 2010: Original Draft Posted • July 28, 2010: Update 1 Posted • 2 New Projects (1 replaced) • 2 Delayed Projects • 5 projects changed from Proposed to Approved • 2010 BP and 2010-12 CP Differences Report • No differences

  10. Map Legend Contingency Scan Results with Entergy’s Draft Construction Plan Projects Included Key to Map Highlights Annotations Overloads and Low Voltages Planned Upgrade from Entergy’s Draft Construction Plan Year Color Key Other Notes Solution being investigated

  11. Arkansas CPE Results Brandon Hentschel

  12. (2016) Norfork-Calico Rock : Upgrade 161 kV Line (2015)Calico Rock-Melbourne - Upgrade 161kV Line Holland Bottoms Project

  13. (2019)Truman-Truman West- Upgrade 161 kV Line

  14. Helena Op-guide Clarksdale op-guide (2016)AECC L&D 2 to Gillett: Construct new 115 kV Line

  15. (2016)AECC L&D 2 to Gillett: Construct new 115 kV Line

  16. (2016)Hot Springs Hamilton (Albright) - Bismarck: Construct new 115 kV Line and convert Bismarck and Mountain Pine South to ring bus stations. Add capacitor bank at Milton

  17. (2019)Mayflower - Morgan 115 kV Line: Upgrade (2016) NLR Levy - NLR Dixie: Reconductor 115 kV line (2016) NLR Westgate - NLR Levy: Reconductor 115 kV Line

  18. (2016) Monticello East to Reed construct new 115 kV line

  19. (2016)Ebony SS 161 kV (Phase 2): Install, 24 MVAR capacitor bank (2016)Getwell Area Improvements

  20. Low Hydro • Simulate reduced availability of SPA hydro units during summer peak (2012, 2016, and 2019) • Conway (Arkansas) Area • Little Rock • Truman

  21. Low Hydro (cont)

  22. Low Hydro (cont)

  23. Load Pocket Criteria • 2016 Summer • Application of Specific Load Pocket Criteria • Western • Amite South • Downstream of Gypsy (DSG) • G-1, N-1 • No new problems identified.

  24. Mississippi CPE Results Eric Burkey

  25. (2016)Getwell Area Improvements: • Construct new 230 kV line from Getwell to new Senatobia Industrial 230-115 kV substation. • Add new 230-115 kV autotransformer at new Senatobia Industrial substation. • Cut in Senatobia to Sardis 115 kV line into new substation.

  26. (2013)Ray Braswell - Wyndale 115kV Line

  27. (Target)Upgrade South Jackson - East Jackson 115kV line (2017)Braswell to Forest Hill 115 kV Line Upgrade (2014)Rankin Industrial – Airport 115 kV Line Upgrade (2013)Ray Braswell - Wyndale 115kV Line

  28. (2016)Lake Village Bagby to Reed 115 kV Line Upgrade

  29. Louisiana CPE Results James Lyle

  30. (2015)Vatican 138 kV Substation: Cut in Scott to Acadia 138 kV line to Vatican 138 kV, and add breakers at Vatican. Vatican-Scott 138kV

  31. (2019) Champagne – Add 138kV Capacitor Bank

  32. (2014) McManus to Brady Heights – Upgrade 69kV Line (2014) Jackson – Tejac 69kV Line (2015) Port Hudson – 69kV Area Improvement (2015) Port Hudson – Zachary REA 69kV Upgrade Line

  33. (2014) Jackson – Tejac 69kV Line (2014) McManus to Brady Heights – Upgrade 69kV Line (2015) Port Hudson – Zachary REA 69kV Upgrade Line (2015) Coly Area Improvement – Upgrade 230/69kV Autotransformers

  34. (2016) Sorrento Upgrade 138/115kV Auto & upgrade Gonzales-Sorrento 138kV Line (2015) St. James – Add 230kV Capacitor Bank

  35. (2018) Raceland – Cut Waterford to Valentine 230kV line in/out of Raceland Valcherie – Waterford 230kV

  36. Cleco Project: Var support

  37. (2016) Mt. Olive to Arcadia – Construct new 230kV line (Operate at 115kV)

  38. (2016) Mt. Olive to Arcadia – Construct new 230kV line (Operate at 115kV) (2019) Arcadia to Sailes – Construct new 230kV line (Operate at 115kV)

  39. Lake Charles Bulk Transformers (2017) LC Bulk: Construct 230kV facilities & add 230/69kV Autotransformer

  40. Canal-LA - Mossville Chlomal - Lacassine

  41. Texas CPE Results Eddie Filat

  42. Create normally open point at Batson

  43. Create normally open point at Batson

  44. Transfer of load from Atlantic Bulk 69 kV to the 230 kV system at Gulfway.

  45. (2016) China – Stowell 138 kV Line South Beaumont to Lovells Lake

  46. (2016) Conroe Area Switching Station

  47. (2015) Upgrade Jacinto-Splendora 138 kV Line

  48. (2012) New Caney capacitor bank expansion (2018) Expand cap bank at Dayton Bulk

  49. Brandon HentschelEngineer II, ICT Planning501-688-1603bhentschel@spp.org Questions?