FESS ZEBRA MUSSEL TREATMENT PLAN RUN II PROJECT MANAGEMENT GROUP Victor Kuchler. Run II PMG Meeting - 4.20.06. 1 of 13. V. Kuchler. FESS ZEBRA MUSSEL TREATMENT PLAN. SOME BACKGROUND INFORMATION Shells First Observed at the Fermilab Site in November, 2004

aitana
Download Presentation

Run II PMG Meeting - 4.20.06

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. FESS ZEBRA MUSSEL TREATMENT PLAN RUN II PROJECT MANAGEMENT GROUP Victor Kuchler Run II PMG Meeting - 4.20.06 1 of 13 V. Kuchler

  2. FESS ZEBRA MUSSEL TREATMENT PLAN • SOME BACKGROUND INFORMATION • Shells First Observed at the Fermilab Site in November, 2004 • Actual Veligers (Larva) Have Probably Been Here for 4-5 Years • Originally Infested the Great Lakes Region from the St Lawrence Seaway • Also Confirmed in the Fox River System • Can be Transferred by Birds, Boats and Fishermen and Tackle Run II PMG Meeting - 4.20.06 2 of 13 V. Kuchler

  3. FESS ZEBRA MUSSEL TREATMENT PLAN 4 Yrs - 1.25” Storm Water Discharge Culvert at Casey’s Pond Run II PMG Meeting - 4.20.06 3 of 13 V. Kuchler

  4. FESS ZEBRA MUSSEL TREATMENT PLAN • ICW SYSTEM/TREATMENT FACTS • Approximately 12 Miles of Distribution Piping • 5% is > 14” Diameter • 31% is 14” Diameter • 41% is 8” or 10” Diameter • 23% is 6” Diameter • 170 Valves and Hydrants • Flushing Always Begins at Casey’s Pond and Extends Outward Through the Distribution System • Normal Flushing Uses 20 Sectors • Treatment Flushing Uses ~60 Sectors Run II PMG Meeting - 4.20.06 4 of 13 V. Kuchler

  5. FESS ZEBRA MUSSEL TREATMENT PLAN • MARCH ’06 NON-TREATMENT ICW • SYSTEM FLUSH • Duration Was 11 Days (3 Crews/Day) • Approximately 500 lbs of Shells Were Removed • 20 Sectors (Hydrants) Exercised • Shell Size Indicated Maximum 2 Year Growth • Relatively Uneventful with No Pipe Ruptures or Valve Malfunctions • Flushing Was Completed Without Interruption to On-Going Operations or Equipment Run II PMG Meeting - 4.20.06 5 of 13 V. Kuchler

  6. FESS ZEBRA MUSSEL TREATMENT PLAN Run II PMG Meeting - 4.20.06 6 of 13 V. Kuchler

  7. FESS ZEBRA MUSSEL TREATMENT PLAN • MUSSEL REMOVAL AT CASEY’S POND • Removal Process Began Mar 9 (14 Days) • Diver Used a Combination High-Pressure Hose and Vacuum System • Casey’s Pond Intake Structure, Intake Piping and Pump House Well Were Cleaned • 10,000 lbs of Shells Were Removed • 80% of the Shells Were Empty (ie Dead) • Shells Reflected a Broader Size Range But the Largest is Still the 2 Year Size Run II PMG Meeting - 4.20.06 7 of 13 V. Kuchler

  8. FESS ZEBRA MUSSEL TREATMENT PLAN Run II PMG Meeting - 4.20.06 8 of 13 V. Kuchler

  9. FESS ZEBRA MUSSEL TREATMENT PLAN • ICW SYSTEM/TREATMENT FACTS • Chemical to be Used is Nalco EVAC an Oxidizing Molluscicide • EVAC has a 19 Hour Half-Life but is Not Dispersive and Decomposes Microbially • Not Harmful to Fish or Other Wildlife • Not Harmful to Piping or Equipment • Other Treatment Options Were Investigated But Eliminated Primarily Due to Application Requirements and System Size • Biggest Constraint to Effective Treatment is Water Temperature - Opt. 65oF to 75oF Run II PMG Meeting - 4.20.06 9 of 13 V. Kuchler

  10. FESS ZEBRA MUSSEL TREATMENT PLAN Run II PMG Meeting - 4.20.06 10 of 13 V. Kuchler

  11. FESS ZEBRA MUSSEL TREATMENT PLAN • PROPOSED TREATMENT FLUSHING PLAN • Current Start Date Planned as May 8 • May 9 - Complete Treatment Chemical • May 10-11 - Treatment Process (26 hrs) • May 12-23 - Best Case Duration (11) • May 12-Jun 1 - Worst Case Duration (21) • May 12-26 - Most Likely Duration (15) • Pre-Exercising of Valves is not a Good Idea • Pipe and Other Repair Materials Have Been Stockpiled for Quick Response • Contracts are in Place to Support FESS Operations Personnel in Repair Efforts Run II PMG Meeting - 4.20.06 11 of 13 V. Kuchler

  12. FESS ZEBRA MUSSEL TREATMENT PLAN Run II PMG Meeting - 4.20.06 12 of 13 V. Kuchler

  13. FESS ZEBRA MUSSEL TREATMENT PLAN • Summary • Flushing Experience to Date is Encouraging • We are Well Prepared for the Process • Water Temperature is Not Likely to be Optimal, However Any Shells Removed Will Be Helpful to the ICW System • There is Evidence that the “Carrying Capacity of the System” (equilibrium) May be 2 Years • Experience is Gained with Each Flushing Cycle • Future Flushing Cycles Will Include Treatment and Become Routine System Maintenance Run II PMG Meeting - 4.20.06 13 of 13 V. Kuchler