1 / 29

XYZ Port Facility Maritime Security Exercise

XYZ Port Facility Maritime Security Exercise. Controller Briefing. date. Port Facility Security Plan Exercise. Exercise PE12. Scope Schedule Aim Objectives Required attainments Controllers Participants Exercise Format Exercise Product Scenario Controller Tasks.

akirk
Download Presentation

XYZ Port Facility Maritime Security Exercise

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. XYZ Port FacilityMaritime Security Exercise Controller Briefing date

  2. Port Facility Security Plan Exercise Exercise PE12

  3. Scope • Schedule • Aim • Objectives • Required attainments • Controllers • Participants • Exercise Format • Exercise Product • Scenario • Controller Tasks • Master Events List • Communications • Code Words • Safety • Resources • Debrief

  4. Schedule • Start: • Estimated End: • Location: • Debrief: • Report by:

  5. Aim To review and test the PFSP in order to perform a thorough audit of the Plan

  6. Objectives • To update the Port Facility Security Plan, taking into account changes to the Port Facility • To practice the command, control, coordination and communications for security activities both within and beyond the Port Facility

  7. (under construction) IMO River Terminal 6 Basin E Basin F Terminal 5 Basin D Terminal 4 Basin C Terminal 3 Basin B Terminal 2 Basin A Terminal 1 PORT IMO Limit of Port jurisdiction O’Neil Basin Scale 1:2,500 Required Attainments On completion of the exercise, a revised PFSP should be submitted for endorsement verification and/or the issue of a Statement of Compliance by the DA

  8. Exercise Director • Senior Vice President, Operations Mr. BBB • Control Team • Chief Controller: Operations Mgr, Mr. AAA • High Controller (Ops): Facilities Mgr, Mr. DDD • Low Controller: Safety Supervisor, Mr. XXX

  9. Participants

  10. Exercise Format • A systematic planning process is to be employed to address the maritime security issues at the Port Facility

  11. Exercise Format • The review of the maritime security issues will be followed by a tabletop simulation “execution” phase where participants will respond to controller “injects” of incidents • Drills to be incorporated for a live exercise

  12. Exercise Product • Revisions to the PFSP should follow the recommendations and lessons learnt from this exercise

  13. Scenario • Narrative • Increasing maritime security threat both • locally and internationally • Government lacks finances and political • will to tackle the threat • Maritime security situation in the country • is slowly deteriorating • Theft, vandalism, unauthorised entry and • stowaways at the Port Facility

  14. Controller Tasks • PLANNING • To identify the general and local • characteristics of potential security incidents • To develop a comprehensive list of potential • security incidents that impact on this Port Facility • TABLETOP SIMULATION • To introduce injects to trigger participants’ • responses • To record observations and recommendations

  15. Master Events List

  16. Master Events List

  17. Master Events List

  18. Master Events List

  19. Master Events List

  20. Master Events List

  21. Master Events List

  22. Communications • Messages • Email • Telephone • Other communications means as required • for drills (if incorporated)

  23. Communications Plan

  24. Code words

  25. Safety • No special safety considerations for the • planning and tabletop simulation • Drill safety precautions and RAM to be • implemented if drills are incorporated as • part of a full scale or live exercise

  26. Resources

  27. Resources • Higher Controller (Ops) to arrange for: • Plan of the Port Facility • Map of the Port Facility precinct • Chart of the Port Facility harbour area • Laptop, projector and screen • Wyteboard and supply of wyteboard markers • Photocopier and stationery

  28. Debrief • Location: • Secretary: • Attendance

  29. end Any questions ?