Progress at the RAL Front End Test Stand J. Pozimski Talk outline :

Progress at the RAL Front End Test Stand J. Pozimski Talk outline :. Overview Ion source development LEBT RFQ Beam Chopper MEBT. Ion source 70 mA, 2 ms, 10 % dc. 3 Soleniod LEBT. RFQ, 324 MHz, 3 MeV. MEBT, chopper. Overview – Experimental Parameters.

alena
Download Presentation

Progress at the RAL Front End Test Stand J. Pozimski Talk outline :

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Progress at the RAL Front End Test StandJ. PozimskiTalk outline : • Overview • Ion source development • LEBT • RFQ • Beam Chopper • MEBT

  2. Ion source 70 mA, 2 ms, 10 % dc 3 Soleniod LEBT RFQ, 324 MHz, 3 MeV MEBT, chopper Overview – Experimental Parameters Aim is to demonstrate a 60 mA, 2 ms , 50 pps chopped beam at 3 MeV It is a collaboration of several physics institutes: RAL/ISIS (chopper, ion source, engineering) RAL/ASTeC (beam dynamics, RF cavities) Imperial College HEP group (engineering, RFQ, diagnostics, LEBT) Warwick University HEP group (LEBT)

  3. Ion sourceD. Faircloth - ISIS Parameters of the ISIS source • Penning H- ion source • Surface Plasma Source (SPS) • 35 mA through 0.610 mm aperture ( 600mA/cm2) • 200-250 s, 50 Hz  1% duty cycle • 0.17  mm mrad (@ 665 keV, 35 mA, rms) Development Goals : • Double output current : • 35mA → 70mA • Increase pulse length : • 200μs → up to 2 ms • Improve (preserve) emittance • Maximize lifetime

  4. Ion source development -results In the experiments the nominal beam current of 70 mA was already reached and an pulse length of up to 1750μsachieved 70mA beam current !

  5. no of successful runs LEBT length [m] LEBTJ. Back – Warwick; S. Jolly - Imperial A 3 solenoid LEBT like in ISIS will be used. The parameter space was scanned by the use of a envelope simulation to search for possible solutions which fulfil the RFQ input requirements for the given source parameters. Now further simulations with GPT for a more detailed analyses of the found solutions to further optimize the beam transport are planned.

  6. Electromagnetic modelling of the RFQ using Mafia(A. Letchford – ISIS; A. Kurup, S. Jolly – Imperial) Theoretical Q value of the 4 vane RFQ ~12000 Theoretical Q value of the 4 rod RFQ model ~6400 • 4-rod or 4-vane ? • 4- rod 324MHz ? • start of particle dynamics calculations Model of the 4 rod RFQ and electric field distribution of the quadrupole mode near the electrodes Distribution of the magnetic fields of the quadrupole mode in the 4 vane RFQ.

  7. Beam Chopper(M. A. Clarke-Gayther – ISIS) To avoid a partial chopped beam, the fast chopper (t<2 ns) removes 3 bunches while the slow chopper (t<12 ns) rises to its max voltage and then chops for 240 ns-0.1ms

  8. Beam Chopper – Pulse generator - measurements Measurements show that the built fast pulse generator system already fulfils the requirements on the voltage and the rise- and fall time (t<2ns).

  9. MEBTFG - AsTec • Improvements compared to the ESS scheme : • chopped beam from fast & slow chopper is collected in 2 dedicated beam dumps, designed to take full beam power (no need for 2 identical chopper sections) • deflection of fast & slow chopper is optically increased by defocusing quadrupoles • now only 30% of original plate voltage for the slow chopper is required (6 kV -> 2 kV), -> faster rise time for slow chopper • larger apertures for all elements

  10. Conclusions • Encouraging progress at the ion source development • Particle dynamics design of the LEBT will finish this autumn and mechanical design started • Particle and electrodynamic design of RFQ started, cold models will be built next spring • Design of beam chopper and MEBT develops strongly • Electronics for the fast beam chopper on the test rig • Definition of new beam diagnostics started