“What are some of our moving targets?”. FSD1 Building Program Growth. Ken Stevenson’s original program called for all three elementary schools to be a Pre-K through 5 th grade level with a capacity of 700 students. Therefore, please see the information below:. Relief School :
E N D
FSD1 Building Program Growth Ken Stevenson’s original program called for all three elementary schools to be a Pre-K through 5th grade level with a capacity of 700 students. Therefore, please see the information below: • Relief School: • Original Capacity 700 students now 948 students • Original Budget $17,697,919 now $18,900,000 • Original Size 84,000 sq. ft. now 92,000 sq. ft.
IV. New Middle School: • Original Capacity 750, core 900 now 1,352 students • Original Budget $20,033,361 now $24,736,381 • Original Size 91,000 sq. ft. now 155,000 sq. ft. • FSD1 Building Program Growth
FSD1 Building Program Growth • North Vista Elementary School: • Original Capacity 700 students now 1,226 students • Original Budget $17,697,919 now $20,027,581 • Original Size 84,000 sq. ft. now 106,561 sq. ft. **North Vista Elementary School four Pre-K classrooms are alternates. We are currently working through some site issues that could affect this budget.
FSD1 Building Program Growth • Royall Elementary School: • Original Capacity 700 students now 1,008 students • Original Budget $17,061,074 now $20,027,581 • Original Size 84,000 sq. ft. now 108,000 sq. ft. **Royall Elementary School has two more Pre-K classrooms than the Relief School in the base bid.
FSD1 Building Program Growth We don’t anticipate a cost increase in construction cost in the near future. However, Royall Elementary School could be affected by cost increases in the future.
Lucy T. Davis Expenses • Copiers • PE Equipment • Music Equipment • Art Equipment • Kindergarten Supplies/Equipment • Digital Signage • Security (cameras)/Intrusion Detection • Time Clocks • Telephone system • Reading Recovery supplies • Classroom startup costs (books) • Media Center books • Kiln • Playground Equipment • Media Center Equipment • School startup costs • Office supplies – (i.e. 3 hole punch, staplers, toner)
Sample Visualization Review Re-Use of existing North Vista Elementary Site Church
New North Vista Elementary School Schedule • Complete Design June 15, 2012 • Early Site Package Bid May 15, 2012 • Early Site Package May15, 2012 to August 15, 2012 • Bid Phase June 15, 2012 to July 15, 2012 • Construction Phase August 15, 2012 to December 15, 2013
“What are some Questions in house that have had financial implications?” • Outfitting labs needed at Lucy T. Davis Elementary? (* With consideration of the next new elementary school buildings.) • Should classrooms be supplied with instructional resources if not in use? • New facility opening day start up cost? • If not supplied now how would it be funded later? • Adequate workstations and resources per classroom?
Computer Warranty Expiration Dates Royall: 182 December - 2014 Moore: 187 - May 2015 North Vista:191 - March 2015 Replace middle school computers - August 2014
Future Capital Funding Needs to Refresh District Computers 2013-2014 – 1.5 Million 2014-2015 – 3.5 Million
Existing Moore Considerations • Up fit Moore to Code to comply with OSF for the Royall population
Mobile Units Relocation • Move from Royall to Moore • Relocate remainder of Mobiles from Royall • Transport & Setup Cost • Electricity • Plumbing • Water • Infrastructure • Data, Network, Potential Fiber Runs • Security • Sidewalks • Overhead Awnings • Decking
Input from Royall Design Committee • Possible areas for input from the design committee for the new Royall Elementary project would include the following: • Preferred locations for support spaces including Reading Recovery, Resource Rooms, Speech, OT/PT, HI/VI, etc. need to be fine-tuned. • The Guidance Suite and Administration Area need to be reviewed and fine-tuned. • Final assignment of classrooms within a particular area (which rooms will be Kindergarten vs. Pre-K for example) need to be made, but switching rooms from one floor to another will be limited by code and state regulations. • Final arrangement of spaces within the Media Center and Kitchen need to be confirmed • Number and locations for other support spaces such as storage, mechanical and electrical rooms need to be finalized.
New Royall Elementary School Schedule • Design Phase May 1, 2012 to February 1, 2013 • Bid Phase February 1, 2013 to April 1, 2013 • Contractor Mobilization May 1, 2013 to June 1, 2013 • Construction Phase Starts June 1, 2013 • Demolition Phase June 1, 2013 to August 1, 2013 • Construction Complete December 1, 2014 • Owner move-in December 1, 2014
The Puzzle begins to come together and we start to see the BIG PICTURE.
New Middle - Moore • Lucy T. Davis • New Royall • New North Vista