Volusia TPO Board Meeting January 22, 2013

Volusia TPO Board Meeting January 22, 2013. Project A: US 1 FM No: 2409922 At: Dunlawton Ave. And: Herbert St. Year Funded: 2013; $535,000 Workmix: Intersection Improvement Phase: Construction. Project B: US 1 FM No: 2409925 At: Canal St. Year Funded: 2015/2018

aliya
Download Presentation

Volusia TPO Board Meeting January 22, 2013

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Volusia TPO Board MeetingJanuary 22, 2013

  2. Project A: US 1 FM No: 2409922 At: Dunlawton Ave. And: Herbert St. Year Funded: 2013; $535,000 Workmix: Intersection Improvement Phase: Construction

  3. Project B: US 1 FM No: 2409925 At: Canal St. Year Funded: 2015/2018 Workmix: Intersection Improvement Phase: ROW (‘15) $1.9 million Construction (‘18) $3.4 million

  4. Project C: US 1 FM No: 2409927 At: Reed Canal Rd. Year Funded: 2015/2018 Workmix: Intersection Improvement Phase: ROW (‘15) $1.7 million Construction (‘18) $1 million

  5. Project D: US 1 FM No: 2409928 At: Big Tree Rd. Year Funded: 2015/2018 Workmix: Intersection Improvement Phase: ROW (‘15) $268,000 Construction (‘18) $1 million

  6. Project E: US 1 FM No: 2409929 At: LPGA Blvd. Year Funded: 2015 $370,000 Workmix: Intersection Improvement Phase: Construction

  7. Project F: SR 483 (Clyde Morris Blvd.) FM No: 4081781 From: SR 400 (Beville Rd.) To:SR 600/International Speedway Blvd. Year Funded: 2018 $28 million Workmix: Widening Phase: ROW

  8. Project G: SR 472 FM No: 4336681 From: Kentucky Ave./MLK Jr. Blvd. To: Graves Ave. Year Funded: 2015 $800,000 Workmix: Widening Phase: PD&E Kentucky Ave/MLK Blvd

  9. Project H: SR 15/US 17 FM No: 4336691 From: SR 40 To: Putnam County Line Year Funded: 2015 $1.8 million Workmix: Widening Phase: PD&E

  10. Project I: AlternativeAnalysis StudyFM No: TBD From: DeLand Sunrail Station To: Daytona Beach International Airport Year Funded: 2015 $3 million Workmix: PD&E Phase: PD&E

  11. Project J: I-95FM No: 4068696 From: North of SR 44 To: South of I-4 Year Funded: 2015 $94 million Workmix: Add Lanes & Rehabilitate Pavement Phase: Construction

  12. Project K: I-95FM No: 2427152 From: South of I-4 To: North of US 92 Year Funded: 2013 & 2016$38.7 million Workmix: Interchange Phase: ROW

  13. Work Program PublicHearing Website: www.d5wpph.com/2012