An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. NEXT and ABBIX projects Steve Hulbert Beamline Project Manager NSLS-II Project Advisory Committee Meeting March 29, 2012

  2. Outline • NSLS-II EXperimental Tools (NEXT) Project • Advanced Beamlines for Biological Investigations with X-rays (ABBIX) Project • Overview, Goals • Scope, External Dependencies • Project Milestones • Staffing, Costs, Funding • Endstation numbers: total, simultaneous

  3. NEXT Project overview, goals ESM -- Electron Spectro-Microscopy FXI -- Full-field X-ray Imaging ISS -- Inner Shell Spectroscopy ISR -- Integrated In-Situ & Resonant X-Ray Studies SIX -- Soft Inelastic X-ray Scattering SMI -- Soft Matter Interfaces Project Goals • Design and build 6 state-of-the-art insertion-device-based beamlines for NSLS-II • Leveraged by extensive auxiliary supporting infrastructure developed by NSLS-II Project • Support scientific programs complementary to 6 NSLS-II Project Beamline programs • Expand the BES beamline portfolio at NSLS-II facility • Increase usage of NSLS-II in early operations phase

  4. ABBIX project overview, goals AMX -- Flexible Access and Highly Automated Macromolecular Crystallography Beamline FMX -- Frontier Macromolecular Crystallography Beamline LIX -- High Brightness X-ray Scattering for Life Sciences Project Goals • Design and build 3 state-of-the-art beamlines insertion-device-based beamlines for NSLS-II • Leveraged by extensive auxiliary supporting infrastructure developed by NSLS-II Project • NIH funded project • Scientific programs that address NIH mission needs • First elements of biological sciences beamline portfolio at NSLS-II facility • Increase usage of NSLS-II in early operations phase • Timeline is similar to NEXT Project, with symbiotic benefits AMX/FMX LIX

  5. NSLS-II Beamline Technique Matrix Matrix of techniques and photon energy ranges to be provided by the NSLS-II Project (black), NEXT Project (red), ABBIX (green), and Type II (blue) beamlines

  6. NEXT Project Base Scope • Beamlines: Develop (design, engineering, fabrication/procurement, assembly, testing, installation) best-in-class insertion-device-based beamlines. Beamline hardware installed and ready for commissioning with X-ray beam. • Beamlines to match best-in-class properties of ID sources. • Beamlines + sources, taken together, to match beamline scientific requirements • World class science capability will be delivered by the NEXT beamlines in the base scope • Base scope includes provisions for future upgrades and continued development • Endstations: Provide all hardware required to bring beam to the experimental endstations, including endstation enclosures, utilities, interlocks, safety systems

  7. NEXT External Dependencies • IDs and FEs • Requirements, specifications, and interfaces (RSI) to be prepared by NEXT Project • Assume IDs and FEs will be provided by NSLS-II funds • SIX endstation satellite building • RSIs to be prepared by NEXT Project • Assume building to be designed and constructed by NSLS-II funds • Endstations • Much NEXT endstation hardware exists at NSLS today and will continue to be developed and enhanced prior to being moved to NSLS-II in FY2014-5 • Potential funding for future endstation upgrades, to enhance the NEXT experimental programs: • NEXT project cost contingency, which can be freed up as NEXT project procurements proceed and associated risk is retired • Investments from potential Partner Users for NEXT beamlines • NSLS-II operations funding

  8. NSLS-II,NEXT, and ABBIXInsertion Devices † For canted IDs/FEs, ( ) shows canting angle in mrad * Depending on location within ID straight section ** Off-center canting magnet location in ID straight section ‡or EPU190 (EM), Kmax~8 PPM: Pure Permanent Magnet EM: Electro Magnet H: Hybrid Magnetic Design

  9. SIX Beamline Layout focusing optics sample chamber monochromator exit slit 15 m detector spectrometer optics ~100 m

  10. NEXT Project Management Team 2.01 NEXT Beamlines Project Management S. Hulbert ES&H – S. Hoey QA – C. Porretto Project Controls – J. O’Connor Admin – E. Morello WBS 2.0 NEXT Beamlines S. Hulbert NEXT Beamline Advisory Teams 2.02 Conceptual Design R. Reininger 2.03 Common Beamline Systems A. Broadbent 2.09 SMI: Soft Matter Interfaces beamline E. DiMasi 2.05 FXI: Full-field X-ray Imaging beamline W.-K. Lee 2.06 ISR: Integrated In-Situ and Resonant X-ray Studies beamline C. Nelson 2.07 ISS: Inner Shell Spectroscopy beamline K. Attenkofer 2.08 SIX: Soft Inelastic X-ray Scattering beamline I. Jarrige 2.04 ESM: Electron Spectro-Microscopy beamline E. Vescovo

  11. NEXT Project Major Milestones • CD-0 (Mission Need) Planned: 3Q10 Actual: May 27, 2010 • CD-1 (Alternative Selection) Planned: 4Q11 Actual: Dec. 19, 2011 • CD-2 (Performance Baseline) Planned: 1Q13 • CD-3A (Long Lead Procurement) Planned: with CD-2 • CD-3 (Start Construction) Tentative*: 4Q13 • Early Project Completion Tentative*: 4Q16 • CD-4 (Project Completion) Tentative*: 3Q17 *Pending re-planning to accommodate new funding profile Short term schedule • DOE CD-1 review Planned: Aug. 30–Sept. 1 Actual: Aug. 31–Sept. 1 • CD-1 approval Planned: Oct. 2011 Actual: Dec. 19, 2011 • ALD’s CD-2 (PDR) review Planned: Jul 17-19, 2012 • DOE CD-2 review Planned: Sep 11-13, 2012

  12. NEXT Project Staffing • Scientific staff • All 6 permanent Level 2 Manager positions have been filled: 5 are on board (ESM, FXI, ISR, ISS, and SMI), and the 6th(SIX) will begin ~May 2012. • Beamline scientists • 6 positions are being posted, with the goal of filling them in the first half of FY13. • Mechanical Engineers • 3 mechanical engineering positions have been filled: 2 arein place and the 3rd will start in April 2012. • Mechanical engineering for a 4th beamline is being accomplished via an MOU with BNL’s Condensed Matter Physics and Materials Science Department. • A 5th mech. eng. position is posted and interviews are underway, with the goal of filling it during FY12. NEXT Staffing Plan Total estimated FTEs = 143 • Management staff • Project Manager, ES&H Manager, QA Manager, Project Controls Specialist, and Admin all filled with permanent staff • Support staff • Support staff will be matrixed from existing PS staff

  13. NEXT Funding Profile at CD-1 • FY13 budget request and out-year guidance flattens the funding profile and stretches it into FY16 • Result: extension of NEXT CD-4 by a full year, to 3Q17, with early completion in 4Q16. ($M)

  14. ABBIX Project Scope Base Scope (hardware installed and ready for commissioning with X-ray beam) • Insertion Devices & Front Ends • Beamlines(optics, vacuum system, diagnostics, controls) • Radiation enclosures (incl. utilities, interlocks, safety systems) • Design & engineering of endstation components • Capabilities • Beamlines to match best-in-class properties of ID sources • World class science capability enabled by the ABBIX beamlines in base scope Scope Contingency (could be added after base scope risk is retired) • Endstation components • Capabilities: • Endstations to match best-in-class properties of sources + beamlines • Endstations + beamlines+ sources to match beamline scientific requirements • Provisions for future upgrades and continued development

  15. External Dependencies External == items outside scope of ABBIX project • Common Beamline Systems • Utilities, Safety Systems, Control Stations • NSLS-II funded • Endstation components • To the extent that scope contingency is not available to procure endstation components, transfer endstation components from NSLS X9, X25, X29 for commissioning and world-class initial science program • Sources of potential funding for future endstationenhancements: • Investments from potential Partner Users for ABBIX beamlines • ABBIX beamline operations funding

  16. ABBIX project team organization & WBS 5.01 ABBIX Project Management and Support S. Hulbert ES&H – S. Hoey QA – C. Porretto Project Controls – T. Mennona Admin – E. Morello WBS 5.0 ABBIX Project S. Hulbert ABBIX Project Beamline Advisory Teams 5.02 Conceptual Design R. Reininger 5.03 Common Beamline Systems A. Broadbent 5.04 & 5.05 AMX: Flexible Accessible and Highly Automated Macromolecular Crystallography beamline& FMX: Frontier Macromolecular Crystallography beamline D. Schneider*, R. Sweet* 5.06 LIX: High Brightness X-ray Scattering for Life Sciences beamline L. Yang 5.08 Front Ends L. Doom 5.07 Insertion Devices T. Tanabe 5.09 Control Systems B. Dalesio * Interim

  17. ABBIX project major milestones • Conceptual Design Complete 2Q FY12 (CDR held Jan. 17-18) • Begin Insertion Device Procurement 2Q/4Q FY12 (AMX-FMX/LIX) • Preliminary Design Complete 4Q FY12 (PDR sched. June 26-27) • Begin Long Lead Procurement 4Q FY12 • Final Design Review 2Q FY13 • Start Installation 1Q-2Q FY14 • Receive ABBIX Insertion Devices 2Q/3Q FY14 (AMX-FMX/LIX) • Start Sub-system Testing 4Q FY14 • Install ABBIX IDs and FEs 3Q FY15 • Commission ABBIX IDs and FEs 4Q FY15 • Start Integrated Testing 1Q FY15 • Complete Integrated Testing 4Q FY15 • Early Project Completion 4Q FY15 • Project Closeout 3Q FY16 * * approx. 9 monthsschedule float at end of project

  18. ABBIX Project Staffing • Scientific staff • The LIX beamline Level 2 Manager position has been filled and is in place • Interviews for the AMX/FMX Level 2 Manager position have been completed and a decision is expected soon. • Beamline scientists • 3 positions are being posted, with the goal of filling them in the first half of FY13. • Mechanical Engineers • 2 engineering positions have been opened, one for FMX/AMX and one for LIX. Interviews are underway. • Management staff • Project Manager, ES&H Manager, QA Manager, Project Controls Specialist, and Admin all filled with permanent staff ABBIX Staffing Plan Total estimated FTEs = 80 • Support staff • Support staff will be matrixed from existing PS staff

  19. ABBIX project funding • NIH ARRA funding (12M$) for Insertion Devices and Front Ends received – 2010 • ABBIX project beamline partial funding received from NIH – August 2011 • Common beamline systems (PPS, EPS, Utilities, Control Station), totaling ~3M$, to be provided by NSLS-II • Assumed Funding Profile • ABBIX project is forward-funded : no problem matching cost profile, which will peak in FY13-14

  20. ABBIX project cost & funding profile

  21. Numbers of endstations • Total number of Endstations(TE)  capabilities • Number of Simultaneous Endstations (SE)  users Beamline Construction Projects SE TE NEXT MIE Beamlines • Photoemission-Microscopy Facility (ESM) 2 3 • Full-field X-ray Imaging (FXI) 1 1 • In-Situ & Resonant X-Ray Studies (ISR) 1 2 • Inner Shell Spectroscopy (ISS) 1 1 • Soft Inelastic X-ray Scattering (SIX) 1 1 • Soft Matter Interfaces (SMI) 1 2 ABBIX Beamlines • Frontier Macromolecular Crystallography (FMX) 1 1 • Flexible Access Macromolecular Crystallography (AMX) 1 1 • X-ray Scattering for Biology (LIX) 1 1 TOTAL 10 13