EITI Progress in Mongolia. Presented by Dorjdari N., PWYP Mongolia Coordinator. Regional Meeting, Bishkek 29 October 2010. Where are we at in terms of EITI?. Mongolia has been announced ‘compliant’ during recent EITI Board meeting in Dar Es Salaam (October 19)

amadis
Download Presentation

EITI Progress in Mongolia

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. EITI Progress in Mongolia Presented by Dorjdari N., PWYP Mongolia Coordinator Regional Meeting, Bishkek 29 October 2010

  2. Where are we at in terms of EITI? • Mongolia has been announced ‘compliant’ during recent EITI Board meeting in Dar Es Salaam (October 19) • In April, Mongolia was designated ‘candidate country’ and ‘close to compliant’; given 6 months to show progress • Mongolia had problems with 5 indicators – indicators 11-15

  3. Validation • Mongolia validated in November-December 2009 • Coffee International was the validator • MSWG accepted the validator’s report • Initial report suggested Mongolia met all indicators – later revision revealed 5 indicators not met • PWYP Mongolia Coalition did self assessment – very helpful to prepare for the actual validation • Validation and the following EITI Board Decision to announce Mongolia ‘close to compliance’ let to increased activity of MSWG and the government • Validator shed light on some problems areas in MSWG, like formality of the process, clarity of definitions, etc.; helped understand some issues clearly at the MSWG level

  4. Around EITI reports • 3 EITI reports so far, covering 2006-08 • Auditors: Crane and White, Ernst and Young, Hart Group • Companies: Oil&Gas + Mining (exploration + producing); State owned+private; Chinese+Russian+all others • Reports not included in the official reconciliation: for 2007, Institute of Certified Accountants did reconciliation of 28 companies • Response from civil society: • 2006 Report: Full Response Paper, Press Conference, TV Interviews • 2007 Report: Open Letter, Press Conference, TV Special Interview • 2008 Report: Open Letter, Press Conference, TV and Newspaper Interviews, Full One Page Newspaper Special • Use of reports by civil society: Inadequate? -Tax policy?

  5. Summary Stats 2006-2009

  6. Beyond minimum EITI standards • Mongolia EITI – disaggregated; company by company and payment by payment • Some exploration companies included • Environmental reclamation costs and bond are included in the reports • Information on production is included in the reports • Two-tiered MSWG – National Council and Working Group

  7. Going forward • EITI Legislation • Includes contracts and licenses • Includes uranium, other minerals, oil • Sub-national EITI Pilot • Soum (subprovincial) level EITI piloted • MSG at soum level established • Templates are being developed • Reports of soum • EITI – from minimum standards to ‘high’ or ‘best international’ standards? • Overhaul of financial reporting – routine financial report by all companies involved?

  8. End of Presentation THANK YOU FOR YOU ATTENTION!