The Greek Muon Chambers (BIS). The three Greek Laboratories: 112 (90 BIS30 +22 BIS36 ) chambers ALL CHAMBERS @CERN since Sept 04. • University of Athens (UoA) Tube wiring/assembly (30,000 tubes finished Dec.2003 ) • National Technical University of Athens(NTUA)
E N D
The Greek Muon Chambers (BIS) The three Greek Laboratories: 112 (90 BIS30 +22 BIS36) chambers ALL CHAMBERS @CERN since Sept 04 • University of Athens (UoA) Tube wiring/assembly (30,000 tubes finished Dec.2003) • National Technical University of Athens(NTUA) Quality Assurance/Quality Control of tubes (30,000 tubes finished Mar.2004) • University of Thessaloniki (AUTh) Chamber assembly (112 chambers finished April 2004)
The Greek ATLAS Muon Collaborating institutes • NTUA • • M.Dris • • A. Filippas • • E. Gazis • • T. Alexopoulos • • E. Katsoufis • • T. Papadopoulou • • E. Fokitis • • Y. Tsipolitis • • S. Maltezos • • A. Tzamarioudaki • P. Savva UoA • C. Kourkoumelis • P. Ioannou • D. Fassouliotis • I. Hatziantonaki • K. Nikolopoulos • D. Pappas • AUTh • •Ch.Petridou • • T. Liolios • • M. Manolopoulou • • S. Dedousis • • M. Chardalas • • D. Sampsonidis • T. Lagouri • • K. Ypsilantis • • A. Krepouri • • C. Lamboudis • • K. Economou • • K. Filippousis
…providing the servicesthe procedure • Preparation activitieshome (gas bars, cables +29 chambers at Thessaloniki) FINISHED summer 2004 • Stage 1 (Blg 184 :equip with gas bars, FC’s, HH’s+MECCAtest 78 chambers at CERN, test for gas leak OK) STARTED March 2004 - FINISHED Sept 2004 (but 7 chambers) • Stage 2 NOW HALF_FINISHED • Electronic Noise test NOW • Cosmic Ray test NOW • Database NOW
Blg 283 (ALL 112 CHAMBERS) Test facilities shared with BIL team
Stage 2 (Bldg:283 started Oct 2004 after gas leak test) Equip chambers with: • gas supply brass tubes, plugs, valves etc • Mezzanines boards +FC covers • alignment platforms + cables + measure them • HV and readout cables (stiff cables/support!!) • B field platforms +cables • T sensor cables • Protective covers FINISHED 56 CHAMBERS A team of 2 technicians working on them since Oct Since Dec. 3 technicians + ½ physicist (since Jan.) Expect to finish by Easter RATE IS : 4 min to 5 max chambers/week (Greek)
…providing the servicesStage II-Blg 283 (ALL CHAMBERS) Noise test/ Cosmic Ray Test (10 chambers before Xmas+restarted last week) Data base Leak test/certification A team of 1 physicist –S.Vlachos (since Jan.) +½ physicist (Ph.D.student) (from March)
CONCLUSIONS…providing the services+commissioning the chambers Stage I- Blg 184 Finished 6 months ago (but 7 chambers are still bare) Stage II-Blg 283 (ALL CHAMBERS) Half are fully equipped, rest by May Integration has just restarted MAIN EFFORT NOW Expect to finish by July