Financing Renewable Energy Projects

Financing Renewable Energy Projects. OVERVIEW OF PROJECT DEVELOPMENT ISSUES. Tony Colonnese Director of Engineering Services. 5 June 2014. Ameresco Renewable Energy Experience. DOE Savannah River Site – Biomass Arizona State University – PV Landfill Gas to Energy Fort Detrick – PV .

amina
Download Presentation

Financing Renewable Energy Projects

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Financing Renewable Energy Projects OVERVIEW OF PROJECT DEVELOPMENT ISSUES Tony Colonnese Director of Engineering Services 5 June 2014

  2. Ameresco Renewable Energy Experience • DOE Savannah River Site – Biomass • Arizona State University – PV • Landfill Gas to Energy • Fort Detrick – PV

  3. Homework Prior toIssuing an RFP • Economic Viability of a Project • Current Utility Rates • State Incentives – Renewable Portfolio Standard (RPS) • Condition of Existing Infrastructure • Internal Support for a Project • Surplus Land Suitable for Development • NEPA Environmental Assessment

  4. Sample of Major Development Steps • Utility Interconnection Study and Agreement • Load Integration Study (Behind the Meter) • State Environmental Permitting • Storm Water Management & Erosion Control • Emissions Controls • Wetlands, Floodplain • Endangered Species • Cultural Resources, Historic Preservation • Other Unique to State – e.g. Afforestation • NEPA Environmental Assessment • Site-Specific Conditions

  5. Other ImportantDevelopment Steps • Local Planning • Cyber Security • Site Lease Issues • Title • Encumbrances • Access

  6. Development Timeline Utility Interconnect Study – 3 to 6 months Environmental Permitting – 4 to 12 months NEPA Environmental Assessment – 6 to 12 months Title Search / Land Survey – 2 to 4 months Final Contract Negotiations – Ongoing Other DoD Approvals – 2 to 6 months. After All Else Done but Preparatory Work Important