20 likes | 140 Views
Construction plan for Concrete Block Tanks – EWB-Case. Move tools to location. Layout tank. Excavate tank. Set forms and rebar. Mix and pour foundation. Move rebar to location. Bend Rebar. Move gravel to location.
E N D
Construction plan for Concrete Block Tanks – EWB-Case Move tools to location Layout tank Excavate tank Set forms and rebar Mix and pour foundation Move rebar to location Bend Rebar Move gravel to location Move water to location – difficulty depends on final location, rainwater catchment off of nearby buildings is an option Move cement to location Move Sand to location
Cover foundation Let foundation dry Lay 1st layer of block Set forms for pipes Pour concrete for pipes Lay rest of block Move concrete block to location Move sand and cement for mortar Move pipes for input/output, overflow and drainage Next trip: Place baffle and weir in tank Build roof and attach to tank Build baffle and weir Waterproof Tank Move Supplies for roof