CIERRE TÉCNICO DEL EXCONFINAMIENTO DE RESIDUOS CYTRAR, HERMOSILLO, SONORA

CIERRE TÉCNICO DEL EXCONFINAMIENTO DE RESIDUOS CYTRAR, HERMOSILLO, SONORA. UBICACIÓN. KM 244+800 DE LA CARRETERA INTERNACIONAL NO. 15 GUAYMAS – HERMOSILLO, FRACCIONAMIENTO LAS VÍBORAS EN HERMOSILLO, SONORA. DISEÑO E INSTALACIÓN DE LA MEMBRANA (HYPALON).

anchoret
Download Presentation

CIERRE TÉCNICO DEL EXCONFINAMIENTO DE RESIDUOS CYTRAR, HERMOSILLO, SONORA

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. CIERRE TÉCNICO DEL EXCONFINAMIENTO DE RESIDUOS CYTRAR, HERMOSILLO, SONORA

  2. UBICACIÓN KM 244+800 DE LA CARRETERA INTERNACIONAL NO. 15 GUAYMAS – HERMOSILLO, FRACCIONAMIENTO LAS VÍBORAS EN HERMOSILLO, SONORA.

  3. DISEÑO E INSTALACIÓN DE LA MEMBRANA (HYPALON) 1.- Fondo de la celda compactada al 100 %. 2.- En su primer nivel cuenta con una capa de 20 cm de arcilla, casi impermeable 3.- Seguida de una capa de 15 cm de arena, como amortiguador 4.- Membrana Sintética 1 Milímetro de espesor, (Hypalon) 5.- Capa de 30 cm de arena 6.- Seguida de 15 cm de suelo de cemento, para dar estabilidad mecánica *Sobre esta última se depositan los residuos.

  4. DISEÑO E INSTALACIÓN DE LA TUBERIA DE CAPTACIÓN DE LIXIVIADOS Grava ¾ “ Tuvo de PVC Pendiente 2% Pendiente 2% Suelo Cemento 20 cm Arena Membrana Sintética Arena Arcilla DISTRIBUCIÓN DE PERFORACIONES EN LA TUBERIA DE CAPTACIÓN DE LIXIVIADOS 6.3 MM (1/4”) 15 cm 15 cm 10 Cm 20 Cm

  5. SISTEMA DE CAPTACIÓN DE LIXIVIADOS Y POZOS DE MONITOREO (Corte Longitudinal) Pozo de visita Tubería de FoGo. 3” de Diámetro Talud de la fosa Filtro de Grava y Arena Pendiente del Escurrimiento 15 cm Suelo Cementado 30 cm Limo Arena Base de Concreto Membrana Sintética Doble Registro de Cárcamo de Captación Tubo Colector de PVC de 6” de Diámetro

  6. ANTECEDENTES • 1984-1988.- CONFINAMIENTO CONTROLADO DE RESIDUOS PELIGROSOS POR FORD MOTOR COMPANY. • 1988-1993.- OPERADO POR EL GOBIERNO DEL ESTADO • 1994-1996.- SE OTORGA CONCESIÓN A CYTRAR. • 1997 DISPOSICIÓN DEFICIENTE DE RESIDUOS PELIGROSOS DE ALCO PACIFICO, DE MANERA IRREGULAR LA EMPRESA AMPLIO LAS DIMENSIONES DE LAS CELDAS SIN AUTORIZACIÓN, MOTIVO POR EL CUAL SE ORDENO SU CIERRE DURANTE 2001.

  7. 2004 Y 2005.- SE INICIARON LAS ACCIONES DE REMEDIACIÓN RETIRANDO 2,800 TONS DE RESIDUOS QUE SE ENCONTRABAN A LA INTEMPERIE, PARA SU DISPOSICIÓN FINAL EN UN CONFINAMIENTO CONTROLADO.

  8. TRANFERENCIA DE LOS RESIDUOS AL CONFINAMIENTO DE MINA, NUEVO LEON

  9. EN EL 2007, SE FIRMÓ UN CONVENIO DE COORDINACIÓN SEMARNAT/GOBIERNO DEL ESTADO DE SONORA, CUYO OBJETIVO FUE LLEVAR A CABO EL “ESTUDIO DE EVALUACIÓN DE RIESGO AMBIENTAL”, PARA LO CUAL EL GOBIERNO DEL ESTADO Y LA UNIVERSIDAD DE SONORA CONJUNTARON ESFUERZOS PARA REALIZAR DICHO ESTUDIO CON FONDOS PROPORCIONADOS POR LA SEMARNAT. • DE LA EVALUACIÓN DE RIESGO AMBIENTAL “ERA”, SE CONCLUYE QUE LA TRANSFERENCIA DE LOS CONTAMINANTES ES FACTIBLE SOLO POR VÍA EÓLICA Y PARA ELIMINARLA ES NECESARIO REALIZAR EL CIERRE TÉCNICO DE LAS CELDAS 1 Y 2, DEL EXCONFINAMIENTO, EVITANDO ASÍ PROBLEMAS DE SALUD HUMANA Y CONTAMINACIÓN DEL MEDIO AMBIENTE. • LA SEMARNAT, REALIZÓ EL PROYECTO EJECUTIVO DE LAS OBRAS DE INGENIERÍA CIVIL Y AMBIENTAL PARA EL CIERRE TÉCNICO DE LAS CELDAS 1 Y 2, MEDIANTE UN RECUBRIMIENTO SUPERIOR CON EL SISTEMA MULTIBARRERA Y SISTEMAS AUXILIARES.

  10. SOLO SE ENCONTRARON DOS PUNTOS CONTAMINADOS CON TPH (3 m3 cada uno)

  11. Muestreo Colecta de muestra. Perforación inclinada. 45° de la vertical. Longitud: 69m Toma de muestra: cada 4m Inicio de colecta: 25m Perforación vertical. Longitud: 68m Toma de muestra: cada 4m Inicio de colecta:8m

  12. CON BASE AL ESTUDIO DE EVALUACIÓN DE RIESGO AMBIRNTAL, SE CONCLUYÓ REALIZAR EL CIERRE TÉCNICO DE LAS CELDAS 1 Y 2, MEDIANTE OBRAS DE INGENIERÍA CIVIL QUE CONTEMPLA UN RECUBRIMIENTO SUPERIOR CON EL SISTEMA MULTIBARRERA Y SISTEMAS AUXILIARES

  13. CIERRE TÉCNICO DE LAS CELDAS 1 Y 2 CON EL SISTEMA MULTIBARRERAS • 2. CONSTRUCCION DE SISTEMAS DE MONITOREO DE EMISIONES • 3. CLAUSURA DE LA LAGUNA DE LIXIVIADOS Y FOSAS • 4. CONSTRUCCIÓN DE CANAL PARA AGUA PLUVIAL • 5. COLOCACIÓN DE MALLA CICLÓNICA PERIMETRAL A LAS CELDAS ETAPAS PRINCIPALES DE LA OBRA

  14. NIVELACIÓN DE LA SUPERFICIE DE LAS CELDAS 1 Y 2, POR MEDIOS MECÁNICOS

  15. CONSTRUCCION DE SISTEMAS PARA MONITOREO Y EXTRACCIÓN DE EMISIONES DE GASES Y LIXIVIADOS

  16. SISTEMA MULTIBARRERAS

  17. 1) 0.20 M. BARRERA DE GRAVA 2) 0.25 M. BARRERA DE ARCILLA.

  18. 3) BARRERA DE GEOTEXTIL DE 400 GR./M2. 4) BARRERA DE GEOMEMBRANA DE PAD. DE 1.5 MM. 5) BARRERA DE GEOTEXTIL DE 400 GR./M2.

  19. 6) 0.20 M. BARRERA DE ARCILLA. 7) 015 M. BARRERA DE GRAVA

  20. 8) 0.15. BARRERA DE ARCILLA. 9) 0.10 M. LOSA DE CONCRETO HIDRÁULICO F'C 250 Kg./cm2

  21. NIVELACIÓN DE LAS CELDAS 1 Y 2 Y COLOCACIÓN DE LA PRIMERA CAPA DE GRAVA

  22. COLOCACIÓN DE LA PRIMERA CAPA DE ARCILLA

  23. AVANCE DE LA COLOCACION DE LAS PRIMERAS CAPAS DE GRAVA Y ARCILLA

  24. AVANCE HASTA EL DÍA 20 DE MARZO DE 2009

  25. PLANTA DE TRATAMIENTO DE LIXIVIADOS

  26. POR SU ATENCION ¡¡ GRACIAS !!