1 / 17

Project Management BA 4320

Project Management BA 4320. Richard Fisher The University of Texas at Dallas. Project Management. A PROJECT is a set of tasks (activities) with a definite beginning and ending point. Phases Project Planning Project Scheduling Project Tracking. Steps in Project Management Network Analysis.

andrew
Download Presentation

Project Management BA 4320

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Project ManagementBA 4320 Richard Fisher The University of Texas at Dallas

  2. Project Management A PROJECT is a set of tasks (activities) with a definite beginning and ending point. • Phases • Project Planning • Project Scheduling • Project Tracking

  3. Steps in Project ManagementNetwork Analysis • Task Definition and Decomposition • Define Relationships • Estimate Task Times • Construct Diagram • Network Evaluation • Project Tracking and Revision

  4. Tasks • Task (Activity) --A work component needed to be accomplished; a task within the overall project that has a definite beginning and ending point. The activity consumes time. • Decomposition - outlining • Unit measure for tasks • Resources required for task

  5. PM Networks ACTIVITY (TASK) --A work component needed to be accomplished; a task within the overall project that has a definite beginning and ending point. The activity consumes time. EVENTS -- Designates the beginning and / or ending of activities. A point in time. Also shows the precedence relationships of the activities. NETWORK -- A combination of Activities and Events that describe the logic of the project. There is one definite starting and ending point.

  6. Relationships • Relationships determine task sequencing • Finish-to-Start • Task B cannot start until Task A is finished • Most common type • Start-to-Start • Task B cannot start until Task A is started • A delay is often used in this relationship A B A B

  7. A B A B Relationships • Finish-to-Finish • Task B cannot finish until Task A is finished • Start-to-Finish • Task B cannot finish until Task A is started

  8. Precedence Relationships A Task C may not begin until both A and B have been completed. A and B may occur concurrently and are parallel tasks. C D B B D Task D may begin after B is completed. Task E may begin after C is completed. A-B-D-F and A-C-E-F are parallel paths. A F C E

  9. CPM- Critical Path Method CRITICAL PATH -- The path through the network consisting of several activities whose total activity times are the longest of any path through the network. The most pressing, dangerous, risky path through the network. Usually denoted by heavy lines through the activities on the Critical Path. CRITICAL PATH TIME -- Total time of all activities on the critical path.

  10. CPM Terminology T ES EXPECTED TIME of a task (activity) EARLIEST START -- Earliest time expected to complete all previous tasks. EARLIEST FINISH = ES + T for a task. LATEST FINISH -- Latest time a task can finish and still allow the project to finish on time. LATEST START = LF - T for a task. SLACK TIME = LF - EF or LS - ES(there is NO slack on the CP) EF LF LS S

  11. Steps in Project ManagementNetwork Analysis • Task Definition and Decomposition • Define Relationships • Estimate Task Times • Construct Diagram • Network Evaluation • Project Tracking and Revision

  12. Network Evaluation Steps • Construct network diagram showing tasks, relationships and task times using standard format • Define the various paths through the network • Moving from left-to-right calculate the ES (Earliest Start) and EF (Earliest Finish) time for each task • Define Critical Path • Moving from right-to-left calculate the LF(Latest Finish) and LS (Latest Start) for each task • Note Slack Times

  13. Sample Laboratory Example

  14. T 1. Description of Task goes here (Expected Task time) ES EF LS LF Task (Activity) Diagramming On the critical path: ES = LS & EF = LF

  15. Sample Laboratory CMP 3.Inspect lab 2. Build lab 8. End project 7. Pilot eval 1. Beginproject 4.Install equip 5.Recruit staff 6. Train Staff

  16. Gantt Charts • Use Horizontal Bars to represent Tasks on a Horizontal Time Line

  17. Project Tracking Tips • Update Project as needed • Make sure tasks are broken down enough to see progress (or lack of progress) • Poor “task status” communication often means poor progress • Watch for changes in Critical Path • Make sure that there are no “resource conflicts”

More Related