The Kazakh Operator of Electric Power and Capacity Market KOREM JSC Republic of Kazakhstan
Description of the Kazakhstan Electric Power System
Power generation Electric power plants–56. Total installed capacity -18981 (MW), including: thermal electric powerplants – 15817 (83,3%) gas turbine units – 916 (4,8%) hydro-electric power plants– 2248 (11,9%) Power generation: 2005 г. – 67,6 bil.kW*h 2006 г. - 71, 5 bil.kW*h 2007 г. – 76,4 bil.kW*h
Transmission grid Total length of transmission lines with voltage from 220 kV to 1150 kV is 228 100 km
Power consumption in2007 Total consumption of electric power in Kazakhstan is71, 8 bil.кW*h
Reforms in the Electric Power Industry
The Stages of Reforms Istage (1994-2000) • December 1995 - Law on Electric Power Industry • TheNational Company (voltage from 220 kV to 1150 kV)- “KEGOC” JSCwith responsibility of System Operator was established • All Electric Power Plantswere privatized • Regional Electric NetworkCompanies (<220 кV) were established and privatized • The Wholesale Power Market began to function, where the free market price on electric power appeared • State‘s Refusal of price regulation for Electric Power Plants
The Stages of Reforms IIstage (2000- present) • July 2000 – Kazakh Operator of Electric Power and Capacity Market (КОREM JSC) was created • June 2004 – new Law on Electric Power Industry was accepted • Power Supply Companies were established • January 2008 –Balancing Market started work in a simulation routine
The Structureof Wholesale Electric Power Market • Bilateral Contract Market • Centralized Auction Market • Balancing Market • System & Ancillary Services Market
Participantsof Wholesale Electric Power Market • System Operator • MarketOperator • Electric Power Producers (Plants) • Electric Network Companies • PowerSupply Companies • Consumers
Information on Centralized Electric Power Market in Kazakhstan
History of KOREM JSC • July 10, 2000 – KOREM JSC was created • February 18, 2002 - the First Spot Auctions “day ahead” took place in “KOREM” JSC. • September 28, 2004 - The First Forward Auctions took place
At the “KOREM” marketplace there are 2 types of auctions: • “Day ahead” auctions • Forward auctions (medium-term for a week, month and long-term for a quarter, year)
65 members for“day ahead” auctions 116 members for forward auctions Market Participants
The volumes of Centralized Market in 2007 • 15%of the Wholesale Electric Power Market • Total volumes of deals - 9 508 611thousandkW*h
Future projects • “Intra day” auctions • Clearing Center • Central Asian Power Exchange • Financial Derivatives Market