2 sks. Manajemen Proyek Perangkat Lunak. IF 3507. Elisati Hulu Department of Informatics elisatih@gmail.com elisati.hulu@yahoo.com. Simbol. D: Task Duration ES: Early Start EF: Early Finish LS: Late Start LF: Late Finish. Task#/D. ES. EF. LS. LF. ES,EF,LS,LF. 7. D/6. 13. B/5.
E N D
2 sks Manajemen Proyek Perangkat Lunak IF 3507 Elisati Hulu Department of Informatics elisatih@gmail.com elisati.hulu@yahoo.com
Simbol D: Task Duration ES: Early Start EF: Early Finish LS: Late Start LF: Late Finish Task#/D ES EF LS LF
ES,EF,LS,LF 7 D/6 13 B/5 2 7 2 7 4 13 0 A/2 2 13 F/3 16 13 16 0 2 E/4 5 9 C/3 2 5 9 13 6 9 Critical Path
Free Slack dan Total Slack • Free slack • Difference between early finish (EF) time of an activity and the earliest of the early start (ES) times of all its immediate successors • Total Slack • Difference between late start (LS) and early start times (ES)or • Difference between latest finish (LF) and earliest finish times (EF)