An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. LBNL Accounting Changes October 20, 2005

  2. Division Director’s Salaries • No system changes or spend plan changes. • Move DD Salaries back to Organization Burden. • A portion of ALD’s salaries will remain in G&A (initial estimate is 20% of their time).

  3. Space • System Changes: • No space feeders will run. • Spend Plan Changes: • Do not include space. • Eliminate Space charge. • Move the following to Overhead (Site Support): • Leases • Custodial, non-metered utilities, etc. • Maintenance • The following rates change:

  4. Electricity • System Changes: • Electricity commodity will no longer get procurement burden. • Electricity will get LDRD. • Spend Plan Changes: • Electricity column should not include procurement or G&A, but should include LDRD. • Move electrical maintenance to Overhead (Site Support) • Remove procurement burden from commodity. • The following rates change: *Rate shown is subject to change.

  5. LDRD • Create separate rate to collect LDRD costs: • LDRD Operating • LDRD Equipment costs • Eliminate LDRD Equipment burden • Apply rate to Total Cost base (including burdens, excluding construction, UCDRD, Fellowships, Conference, Honorarium, Stipends). • The following rates change:

  6. LDRD • System Changes: • LDRD is on Total Costs EXCEPT S&S and FAC, S&S and FAC are applied to LDRD. • LDRD not applied to Honorarium (36000) and Stipends (35000). • LDRD not applied to Work Sent to Other Labs. • LDRD is applied to the following High Detail Project (HDP) Types (including work orders under them): CRADA, DOEIN, DOEOP, EQFAB, EQPUR, RMBNF, RMBOF, WFO • LDRD is not applied to the following at any level: CNSTR, CONFR, FELLW, GIFTS, OH**, ROYAL, UCDRD • In FMS, LDRD has been added to all projects with the above HDP Types. Any new projects with these types MUST include LDRD as a burden. • “LDR” is the new burden code. Resource Category is 90600. • Spend Plan Changes: • When inputting costs, INCLUDE LDRD at 2.9% on the appropriate costs. (Except AFRD) • The amount of LDRD burden appears as an additional row below the Travel burden in the spend plan template.

  7. Rate Changes NOTE: All rates are subject to change during the fiscal year. *Rates are shown without the effect of compounding burdens