Data Communications Implementation Team (DCIT) Departure Clearance Trials (DCL) Test Status DCIT Meeting # 22 Washington, DC. Presented to: D C I T By: Pete Muraca, FAA Date: March 13 - 14, 2013. Agenda. Test Activity to Date Boeing / Airbus Test Sessions
E N D
Data Communications Implementation Team (DCIT)Departure Clearance Trials (DCL)Test StatusDCIT Meeting # 22 Washington, DC Presented to:D C I T By: Pete Muraca, FAA Date: March 13 - 14, 2013
Agenda Test Activity to Date Boeing / Airbus Test Sessions E-E Functional and Operational Testing Environment Avionics Assets MEM Schedule Milestones Schedule Highlights DCL Trials – Test Status DCIT #22 (March 13 - 14, 2013)
Test Activity to Date • Latest Build 6 was delivered to WJHTC 3/4/13: • Build 6 WJHTC Installation Complete: March 4 • Build 6 WJHTC Functional Testing: March 4-20 • Build 6 MEM Functional/Pre-SAT Testing: March 11-20 • Build 6 MEM Site Acceptance Test (SAT): March 21-22 DCL Trials – Test Status DCIT #22 (March 13 - 14, 2013) 3
Boeing / AIRBUS Test Sessions • Boeing Test Sessions: • Boeing Test Session dates – 2/27, 3/1, 3/5, 3/6, 3/7, 3/8 • Boeing Test Benches utilized – B737, B747-800, B767, B777 • AIRBUS Test Sessions: • Airbus Test Session dates – 2/28, 3/5, 3/7 • Airbus Test Benches utilized – A340, A380 Week of March 11, 2013 MEM pre-SAT testing • MEM DTAP env with Tech Center avionics • MEM DTAP env with UPS / AOC • MEM DTAP env with FedEx / AOC MEM Pre-SAT Test Activities DCL Trials – Test Status DCIT #22 (March 13 - 14, 2013) 4
End to End Functional Testing • DTAP Build 6 • Run system test cases with Tech Center bench avionics • Run system test cases with Boeing and Airbus labs (multiple flight deck configs) • Exercised test scenarios with DCIT aircraft • Conducted Regression testing • Documented / Socialized Findings • New PTRs Opened • 118,120,122,124,125,126,127,128,133 • Closed PTRs • 88,93,100,101,102,103,104,105,106,118,125,124,126,127 DCL Trials – Test Status DCIT #22 (March 13 - 14, 2013) 5
Functional and Operational Test Env. • HADDS / FDIO connectivity and simulation capability • FNTB (via NESG) connectivity for external FAA communications • Ground/Ground and Air/Ground Communication service via ARINC • Ground/Ground and Air/Ground Communication service via SITA • Utilization of Boeing configurable flight deck • Utilization of Airbus configurable flight deck • Utilization of FAA Technical Center bench avionics • DCIT Aircraft Participation • Plans, Procedures and Personnel in place Lab Environment End to End Functional Testing End to End Operational Scenarios Testing (includes pilots & controller crew) FANS Avionics Platforms DCIT Aircraft (FedEx, United-Continental, UPS, Delta, AA, UsAir, Southwest) Site Acceptance Testing (Field Environment) Sub_set of Functional End to End Operational end to end scenarios FedEx Aircraft and AOC Participation 6
Avionics Assets (FANS) External • Boeing Flight Deck (via subnetwork infrastructure and service (ARINC and SITA) • B737-ng • B777 • B747-400 • MD-11 • B787 • B767 • Airbus Flight Deck (via subnetwork infrastructure and service (ARINC and SITA) • A320 • A330 • A350 • A380 (FANS) DCIT Aircraft • FedEx • UPS • Delta • United (ATN Baseline 1 & SC-214 v. H) • Rockwell Collins prototype Avionics (Real Hardware) • Honeywell Avionics (Real Hardware) • Thales Avionics (PC based) Note: Planning for Lab FMS integrated avionics solution (FANS) In-House CMU based FANS 1/A+ avionics end system • Connected to roof antenna representing a target aircraft Laptop based FANS 1/A+ avionics end system • Can be connected to real avionics hardware (A750 Radio, A739 MCDU, A758 CMU) via A429 card 7
MEM Schedule Milestones • The Milestone Schedule Outlook: • Build 6 WJHTC Installation Complete: March 4 • Build 6 WJHTC/MEM Functional/Pre-SAT Testing: March 4-20 • Build 6 MEM Functional/Pre-SAT Testing: March 11-20 • Build 6 MEM Site Acceptance Test (SAT): March 21-22 • MEM Limited Full Functionality Trials (3 Ops/day): March 26 – April 26 • MEM Full FANS Fleet 24x7 Trials Start: April 30 • 4pm Daily Build 6 Testing/PTR review telcon DCL Trials – Test Status DCIT #22 (March 13 - 14, 2013) 8
DCL Trials – Test Status DCIT #22 (March 13 - 14, 2013) 9