An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Tema IV: Procesos de Iniciación y Planificación Objetivos: • 2) Gerencia del Tiempo • Desarrollo del Cronograma (redes, ruta crítica, etc.) • (parte II, AON)

  2. Gerencia del Tiempo: Cronograma

  3. Diagramas de Redes

  4. Lista de Actividades

  5. Ruta Crítica/CPM I 5 B G J 19 4 7 23 3 7 4 K A 23 12 9 F 5 28 4 19 0 H 1 C 1 28 0 D E 5 5 8 18 3 10 5 8 18

  6. Diagrama de Precedencias: Conceptos

  7. Secuenciación de Actividades Tipos de Precedencias X

  8. Tipos de Precedencias A A A B B B Finish to Start

  9. Tipos de Precedencias A B Start to Start

  10. Tipos de Precedencias A B Finish to Finish

  11. Tipos de Precedencias A B Start to Finish

  12. Lista de Actividades

  13. AON: Early Start y Early Finish I B A K G J F C D E H

  14. AON: Early Start y Early Finish ES = 8 I 5 EF = 12 ES = 5 ES = 1 EF = 7 ES = 24 EF = 4 EF = 28 B 3 ES = 8 A 4 EF = 14 K 5 G 7 ES = 6 EF = 6 ES = 20 J 4 ES = 1 F 1 EF = 23 EF = 5 ES = 9 C 5 EF = 18 D 3 E 10 H 1 ES = 19 EF = 19 ES = 6 EF = 8

  15. AON: Late Start y Late Finish LS = 19 I 5 LF = 23 LS = 6 LS = 10 LF = 9 LF = 12 LS = 24 LF = 28 B 3 A 4 LS = 13 LF =1 9 K 5 G 7 LS = 19 LF = 19 LS = 1 J 4 F 1 LF = 5 LS = 20 LS = 9 LF = 23 C 5 LF = 18 D 3 E 10 H 1 LS = 19 LF = 19 LS = 6 LF = 8

  16. Diagrama de Precedencias: Holgura de Actividades H=LF-EF ó H=LS-ES

  17. AON: Ruta Crítica LS = 19 I 5 LF = 23 LS = 6 LS = 10 LF = 9 LF = 12 LS = 24 LF = 28 B 3 A 4 LS = 13 LF =1 9 K G 7 LS = 19 LF = 19 J F 1 LS = 20 LS = 9 LF = 23 C LF = 18 D E H LS = 1 LS = 19 LF = 5 LF = 19 LS = 6 LF = 8

  18. Ejercicio Diagrama de Precedencia

  19. DDP (AON): Cálculo de Early Start y Early Finish ES (AIi)= 1 EF (i) =ES(i) + DA(i)- 1 ES (j) = Max[EF(i) ]+1

  20. DDP (AON): Cálculo de Late Start y Late Finish LF(AFi)= Max (EF(AFi)) LS(i)= LF(i) - DA(i) +1 LF(j)= Min[LS(i)]-1