Clean Energy Projects 101 Permitting Overview

Clean Energy Projects 101 Permitting Overview. November 7, 2010 Generate 2010 Susan Wilkins, VP Operations Pottinger Gaherty Environmental Consultants. Overview. Ministry of Natural Resource Operations (formerly ILMB) guidebook process

arden
Download Presentation

Clean Energy Projects 101 Permitting Overview

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Clean Energy Projects 101Permitting Overview November 7, 2010 Generate 2010 Susan Wilkins, VP Operations Pottinger Gaherty Environmental Consultants

  2. Overview • Ministry of Natural Resource Operations (formerly ILMB) guidebook process • Provincial Environmental Assessment Office (EAO) process • Federal CEAA and MPMO process

  3. MNROGuidebook

  4. MNRO Guidebook Process • If BC Environmental Assessment Act doesn’t apply (<50MW) • Clean Energy Projects Office • Development Plan is submitted for provincial and federal approvals (by referral to agencies) • Different agencies permit independently and may follow different timelines

  5. Common Provincial Permits • Land Tenure (MNRO) • Water Licence (MOE) • Occupant Licence to Cut (MOF) to clear on Crown Land • ROWs and Licences of Occupation • Many others depending on interaction with mining claims (MEM), highways (MOT), etc.

  6. Common Federal Permits • Fisheries Act Habitat Authorization from DFO • Navigable Waters Protection Act (NWPA) Approval from Transport Canada • Canadian Environmental Assessment Act (CEAA) review • See p. 50 of Guidebook

  7. Provincial EA Process As per BCEAA… • A Provincial EA review is required if: • project will generate >50MW • transmission lines >500 kV and >40 km on a new RoW • Provincial Environmental Assessment Office (EAO) • Concurrent permitting regulation for other Provincial permits

  8. Differences - BC and federal EA

  9. Federal CEAA CEAA triggered if federal authority: • is the proponent of the project • provides financial assistance to project (e.g., ecoENERGY) • grants an interest in land • exercises a regulatory duty (e.g., Fisheries Act authorization or NWPA approval)

  10. Does CEAA Apply? no Do you have a project? yes yes • On the Exclusion List or otherwise excluded? no no Do you have a Federal Authority yes yes no Act applies Do you have a s.5 trigger? Act does not apply (Ref: L. Bruce, 2009)

  11. Federal CEAA • CEAA Screening is most common level of review • Comprehensive Study for >200MW or transmission line > 345 kV and > 75 km on a new RoW, or • Review Panel for most complex • Coordinated by CEA Agency with decision making authority held by Responsible Authority (RA) • no legislated timelines

  12. Federal MPMO • Major Project Management Office (MPMO) (est. 2007) coordinates EAs for major resource projects • Purpose is to improve federal review process for large resource projects • Applies if: • Comprehensive Study/Review Panel under CEAA, or • the project is a “large or complex multi-jurisdictional screening”

  13. First Nations • First Nations play important role in project permitting in all levels of government and may conduct their own process to review a project

  14. Public & Stakeholders • Proponents and regulators conduct consultation to understand issues and resolve conflicts • Best practices in public consultation: Authenticity Accountability Inclusiveness Transparency Commitment Integrity

  15. Summary – Permitting Overview • Provincial MNRO guidebook process for <50MW • Provincial EAO process for >50MW • Federal CEAA triggered by federal agency • Federal MPMO process for >200MW (or “complex”) • First Nations are an integral part of project development in BC • Public stakeholder involvement is critical

  16. Questions? Susan Wilkins swilkins@pggroup.com 604-895-7621