An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. MICE CONSTRUCTION PROJECTin the US Alan Bross Fermilab May 7, 2013

  2. Outline • Project Team • Scope of Effort • Execution Plan • Phase I & II Deliverables • Some historical context • Schedule details • Critical Dates • L2 Management Team • Organizational Implementation Moving Forward • Conclusion Alan Bross | MICE Resource Loaded Schedule Review (RAL, May 7-8, 2013)

  3. L2 Management Team • Magnet Fabrication • Spectrometer solenoids and Coupling Coils • RF Fabrication • 201 MHz cavities & components • Vacuum vessels • Detector • Trackers • Trackers to be integrated with SS when they arrive at RAL • Cerenkov • Magnetic shielding • Partial return yoke • US component integration • US liaison for installation and commissioning • Likely stationed at RAL • + LiH absorbers (Fermilab) Alan Bross | MICE Resource Loaded Schedule Review (RAL, May 7-8, 2013)

  4. Scope of Effort • Detectors (Complete) • Two fiber trackers with readout & cryogenics • Two Cherenkov detectors • Absorbers • LiH Disk (complete) • LiH Wedges • Two superconducting spectrometer solenoids • Two large-aperture (1.5m), 2.5T SC solenoids, Coupling Coil Magnet (CCM) • CCM Prototype will be used in MuCool Test Area • Two needed for MICE Step VI • RF System • Eight 201 MHz cavities with tuners and vacuum vessels • Integrated with CCM • RF power components (through NSF MRI) • Commercial products • Magnetic Analysis and stray-field mitigation • Design and engineering of partial return yoke Alan Bross | MICE Resource Loaded Schedule Review (RAL, May 7-8, 2013)

  5. Deliverables StepIV: Fiber Trackers Alan Bross | MICE Resource Loaded Schedule Review (RAL, May 7-8, 2013)

  6. Deliverables Step IV: LiH • Deliverables • Detector components (Complete) • Absorbers: LiH disks (complete) and wedges • In process of establishing a CRADA with STFC which will allow us to ship the LiH to RAL (through Y12) • Since 6Li enriched, considered nuclear material Alan Bross | MICE Resource Loaded Schedule Review (RAL, May 7-8, 2013)

  7. Step IV Deliverables: SS • Cryogenically the magnet now operates to spec • Approximately 3 W heat load (=original calc.) • Total cooling capacity » 6.5 W • SS2 - Vetted • SS1 nearing completion • Ship • SS2 in July ‘13 • SS1 in Sept. ‘13 Alan Bross | MICE Resource Loaded Schedule Review (RAL, May 7-8, 2013)

  8. Step IV Deliverables: Magnetic shielding Shield sections: 100mm [4”] thick Backing plates: 50mm [2”] thick (front & back at vertical joint) Floor template for pre-drilling holes 15” x 50 lb/ft S-beams. Bolted into floor, 100 mm away from wall • Analysis to determine if partial yoke can contain stray fields in the hall so that there are no effects on any equipment • YES • Engineering design of yoke • Conceptual design complete • Performance looks excellent • Full design work initiated Alan Bross | MICE Resource Loaded Schedule Review (RAL, May 7-8, 2013)

  9. Step IV Deliverables: MICE 201 MHz Production Cavity Test • Production component system test • Fixturing • Integration/assembly • Tuner control testing • Vacuum and alignment Fall 2013 Ports, supportsand tuners Alan Bross | MICE Resource Loaded Schedule Review (RAL, May 7-8, 2013)

  10. Step IV Deliverable: Prototype Coupling Coil Magnet (MuCool) • The first Coupling Coil Magnets (CCM) is considered a prototype and will be used in the MuCool program, but will test MICE hardware • Cold mass produced at Qi Huan Co (Beijing) & prepped at LBNL • First complete, 3 more to be fabricated. All SC in hand • New test facility (Solenoid Test Facility) complete • ORC and commissioning starting in 2 weeks • Cryostat fabrication at LBNL • Final assembly • At Fermilab with Technical Division (detailed plan under development) Alan Bross | MICE Resource Loaded Schedule Review (RAL, May 7-8, 2013)

  11. MICE RFCCliteTest in MTA Alan Bross | MICE Resource Loaded Schedule Review (RAL, May 7-8, 2013)

  12. Step VI deliverables: MICE Coupling Coil Magnets with integrated RF (RFCC) • The MICE cooling channel requires two Coupling Coils • Plan to build 3 windings • 2 Cryostats • Four vacuum vessels • Hold two RF cavities each • Eight 201 MHz cavities • Complete save for EP • RF power couplers, tuners, etc. Alan Bross | MICE Resource Loaded Schedule Review (RAL, May 7-8, 2013)

  13. Resource Loaded Schedule

  14. Major Milestones US FY13 FY14 FY15 FY16 FY17 FY18 SS#2 Ready to Ship – July `13 SS#1 Ready to Ship – Sept `13 CCM Prototype Tested and ready to move to the MuCool Test Area (MTA) for Testing with RF in the RFCC_Lite Configuration – April `15 RFCC#1 Ready to Ship – Sept `16 RFCC#2 Ready to Ship – Nov `17 Does not include contingency Alan Bross | MICE Resource Loaded Schedule Review (RAL, May 7-8, 2013)

  15. Step IV: Spectrometer Solenoids Alan Bross | MICE Resource Loaded Schedule Review (RAL, May 7-8, 2013)

  16. Step VI: RF Alan Bross | MICE Resource Loaded Schedule Review (RAL, May 7-8, 2013)

  17. Step VI: RFCC RFCC-Lite Alan Bross | MICE Resource Loaded Schedule Review (RAL, May 7-8, 2013)

  18. Magnetic Mitigation Alan Bross | MICE Resource Loaded Schedule Review (RAL, May 7-8, 2013)

  19. US Risk Register I Alan Bross | MICE Resource Loaded Schedule Review (RAL, May 7-8, 2013)

  20. US Risk Register II Alan Bross | MICE Resource Loaded Schedule Review (RAL, May 7-8, 2013)

  21. Now Add Contingency and Stretch 13-05-02-MAP-WBS5-Only.mpp 23,918 K$ 17,716 K$ 24,383 K$ Almost achieves FY18 completion – BUT… Sums of then-FY K$ Alan Bross | MICE Resource Loaded Schedule Review (RAL, May 7-8, 2013)

  22. Under These Assumptions… Note: no approved NSF Funding for Ops & Exp beyond FY13 DOE Operations & Experimental support still under development Alan Bross | MICE Resource Loaded Schedule Review (RAL, May 7-8, 2013)

  23. Conclusions • We now have a complete RLS for the US-MICE construction project • Some more work to be done • Contingency and risk included and we have shown impact on MICE schedule given US funding constraints • US carries majority of the technical risk • We will know much more in 4-5 months • Expect both spectrometer solenoids to be complete • Testing of first CCM cold mass complete • Begin testing of MICE production cavity in MTA Alan Bross | MICE Resource Loaded Schedule Review (RAL, May 7-8, 2013)