1 / 20

UKNF/MICE Oversight Committee Open session Integration of the MICE project

UKNF/MICE Oversight Committee Open session Integration of the MICE project. Background & local history Progress since 2007 Schedule & planning considerations Re-defining the UK project Electrical engineering Future plans. Andy Nichols, Tim Hayler, STFC 22nd June, 2010.

mihaly
Download Presentation

UKNF/MICE Oversight Committee Open session Integration of the MICE project

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. UKNF/MICE Oversight CommitteeOpen sessionIntegration of the MICE project • Background & local history • Progress since 2007 • Schedule & planning considerations • Re-defining the UK project • Electrical engineering • Future plans Andy Nichols, Tim Hayler, STFC 22nd June, 2010

  2. ......Circa 2007 But this is what we’re aiming for...........>> Circa 1963......

  3. ........Installation of MICE Step VI in R5.2

  4. Progress since 2007 • Starting at the bottom: • Demolish old floor • Install new false floor • Acts as base for whole cooling channel • Conventional construction, but has to be reasonably flat & true • Able to withstand 50 tonne quench force • And, most important, able to be fiddled with extensively in future!

  5. Progress since 2007 • Next level: • Provision of baseplates for spectrometers 1 & 2 • Accurate and repeatable locations for detectors • Able to withdraw from beamline for servicing • Magnets move on airpads • Non-magnetic construction • Able to react 50 tonne quench force

  6. Progress since 2007 • Provision of two magnetic shield walls • Act as return yoke for cooling channel • Protect ISIS Linac and MICE control room from stray fields • 150 tonnes of magnet iron, delivered on time by UK industry • And supporting framework/galleries

  7. Progress since 2007 • Have also done much routine but essential infrastructure work: • Provision of CCR cooling water system • Uprated compressed air system • Provide air conditioning • Uprated the domestic power, lighting & fire detection • Compliance of R5.2 to all safety & local rules • Extract fans • Accommodation for 28 CCR compressors and services • General civil engineering work • Much help here from Building Projects Group (BPG) and ISIS at RAL • Formal handover from BPG 16th June – many thanks indeed

  8. MICE compressed air system Behind R5.1 70 MeV plant room Guaranteed line 5.5bar (actual 6.5 - 7.2psi) MICE Trench

  9. Schedule and planning considerations • All this brings us to June 2010: • Have been ready for Steps II &III for a few months • Were geared towards Step II start in Mid-May, 2010 • Won’t happen till later in 2011, • What to do........?

  10. Re-defining the UK project • Steps II & III are delayed for at least one year • UK installation team and infrastructure construction were very carefully geared towards spectrometer solenoid #1 arriving at May 15th • We want to hold the installation team together, so: • Advance work on the LH2 system - see also Matt’s talk • Vent system • Civil engineering • Pipe/valve & gas panel work • RF power work • Design of waveguide/power/cooling infrastructure, placement of amplifiers • ‘Hands on’ work at DL with RAL team – second LBNL amplifier • Both RF & LH2 projects contain open issues – better to find out early

  11. LH2 external infrastructure All this has to be designed & built outside R5.2.

  12. RF Power • Two RF amplifiers from LBNL are being reconditioned at DL • One is complete, the other is waiting • Plan to deploy some of existing team on second amplifier • Important to do this early while we have time • Led by Daresbury Lab • Very beneficial DL/RAL relationship • RF amplifiers quite big, 4m high and 1 tonne – we have to fit four of them in a very confined space

  13. Need to fit all this........ .....Under here!

  14. Electrical Engineering • Also led by Daresbury Lab: • All detector wiring and cabling • Electrical services in general • Complete implementation of PPS (Personnel Protection System) • Contribution to electrical substation upgrade project • Conventional and S/C magnet power supplies • Cooling Channel controls project • Target power, readout & controls • Major contribution from BPG: • Power for heating, lighting • Implementation of fire detection • A/C power • Electrical substation upgrade project

  15. Electrical substation progressThe problem: • The electrical supply in R5.2, the MICE Hall, needs to be upgraded to 2MVA, certainly to run at Step IV and probably at Step III • Most of the power is required for CCR compressors, latest predictions are (5+1)x2 for spectrometer solenoids and 3x2 for coupling coils • The present layout in R5.2 gives 1.25MVA and is based on fifty-year old equipment that has not been used to full capacity for many years • The ingoing cable to R5.2 has adequate capacity and does not require any work • Historically, this has been treated as a host-lab contribution and has never appeared MICE’s costed plan • But we understand the need for a discussion

  16. Point at which we’re In trouble Present power Rating (1.25MVA) STEP I

  17. What all the fuss is about: Cryomech two-stage Closed Cycle Refrigerator Present configuration of Spectrometer sol 3 x 2 stage CCR + 1 single stage Proposed configuration: 4 (or 5) 2 stage CCR + 1 single stage Coupling magnet will likely need Three instead of two 2-stage CCRs MICE something of a pioneer here Not usual to cool large magnets with CCRs

  18. Electrical substation • Four technically viable solutions have been identified by BPG and DL • Varying degrees of cost/technical capability • We have been asked to follow up the two cheapest options • Meet again with STFC Management on 8th July • Hope to know which version then • Lead time is dominated by major components (around one year), but we also need to add design & installation time • So if we begin now, might just be OK for Step III in late 2011

  19. Future Plans • Between now and 2014, MICE has to successfully build and install several large and complex subsystems, for example: • Two spectrometers • Three absorber-focus coils • Two RF-coupling coil magnets • And all their services and ancillaries • In a very confined space to a reasonable degree of accuracy • Also have to accommodate several different engineering ‘cultures’ and standards • Have demonstrated that a more rigorous engineering approach pays dividends – eg, the MICE target • Now want to read that across to the other subsystems • Easier said than done.......

  20. Future plans • So we’re changing the emphasis slightly, from infrastructure and surroundings to the subsystems and interfaces • Top level assembly now successfully driven by one (large!) Solid Edge CAD assembly • RAL engineering team is being reinforced • Full time integration engineer is appointed • Am now working on support for him • Monthly MICE Technical Board will be forum for integration issues • Integration activity will be centralised at RAL - important • Discussions just beginning with subsystem owners to encourage information flow

More Related