An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. MICE Construction:Responsibility and Resource Sharing Ken Long Mark Palmer May 8, 2013

  2. MIPO MICE RLS Review (RAL)

  3. MIPO • Provides a mechanism for: • Detailed and integrated scheduling • Assessing realistic budget constraints with contingency • A management chain integrated with the funding paths, thus providing a clear chain of responsibility • Comments: • A realistic and robust schedule cannot be achieved on the basis of a simplistic model of components being delivered to RAL for modular integration into a beam line • Risks and potential for contingencies are simply too great • Systems integration issues are significant • These issues have major budget and manpower impacts for the primary members of the construction effort • Construction and integration of a muon cooling channel requires a more holistic approach MICE RLS Review (RAL)

  4. Near Term MIPO Priorities • Detailed analysis of contingency issues • Requires integrated team • Requires integrated tools • Requires an agreed upon model for managing a project with significant technical risks still active • Thus providing a schedulewhich • Realistically assesses the budget and contingency constraints • Can specify the expected dates for experimental capabilities with a high degree of reliability • And also budget assumptions to complete each experimental step which are believable MICE RLS Review (RAL)

  5. MIPO Challenges • Have already discussed integrated scheduling and a mutually agreed upon model for assessing budget and contingency • Management of contingency across international funding boundaries remains challenging • Potential bias in the solutions chosen • Potential inefficient use of resources • Need a clear funding profile among all major participants that accounts for contingency so as to enable proper execution a Would like to negotiate with funding agencies how to implement this MICE RLS Review (RAL)

  6. MIPO: in operation • Many discussions on implementation of MIPO, how it operates, interface with MICE collaboration etc. • Realised when asked at RLSR that we were not clear amongst ourselves about the details of its operation • Propose to produce a one-page specification for the operation of MIPO in time for the MICE collaboration meeting at FNAL/IIT in 17—19 June 2013 • Andy Nichols has agreed to produce this document on this timescale MICE RLS Review (RAL)