1 / 41

Arrowhead - Weston Transmission Line Project Dave Van House Minnesota Power

Arrowhead - Weston Transmission Line Project Dave Van House Minnesota Power. Description & Overview. 220 mile 345,000 volt electric transmission line Approved by the Minnesota and Wisconsin regulators in 2001 Construction Began in Minnesota February 2004

asa
Download Presentation

Arrowhead - Weston Transmission Line Project Dave Van House Minnesota Power

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Arrowhead-WestonTransmission LineProjectDave Van HouseMinnesota Power

  2. Description & Overview • 220 mile 345,000 volt electric transmission line • Approved by the Minnesota and Wisconsin regulators in 2001 • Construction Began in Minnesota February 2004 • Construction to Begin in Wisconsin Fall 2004 • Construction scheduled to be completed in 2008

  3. Why was it proposed? Reliability!! • Improves Regional System Security • Provides Maintenance & Operational Flexibility • Allows Customers Greater Access to Generation Sources

  4. Minnesota • Minnesota’s electric network is tied to neighboring states. • If Wisconsin has a problem, Minnesota has a problem. • Minnesota Power customers have been knocked off line by electric system disturbances related to the weak Minnesota-Wisconsin connection. www.powerupwisconsin.com

  5. Recent Regional Problems • June 11, 1997 • June 25, 1998 • June 10, 1999

  6. IMPACT OF June 25, 1998 DISTURBANCE • IN MAPP • 60+ TRANSMISSION LINES TRIPPED • 4,000+ MW OF GENERATION LOST • More Than 39,000+ CUSTOMERS AFFECTED • IN NW ONTARIO • BLACK OUT TO 113,000 CUSTOMERS • 650 MW OF LOAD LOST • 270 MW OF Generation Lost

  7. Wisconsin Actions • 1997 events raise concerns about electric supply reliability in Wisconsin • Wisconsin utilities and regulators form Wisconsin Reliability Assessment Organization (WRAO) • WRAO forms engineering group to study alternatives - WIRES group

  8. PERFORMANCE EVALUATION • DETAILED POWER FLOWS SIMULATION • GENERATOR RESPONSE • DYNAMIC STABILITY • VOLTAGE STABILITY • IMPACT ON MAPP • CONSTRUCTION COSTS • LOSS EVALUATION

  9. Power Flow Analysis • Reactive Voltage Support Requirements • Steady State Maximum Transfer capability • Sensitivity to Modeling Assumptions • Transmission System Loss Analysis

  10. Generator Response • Mechanical Stress on Weston Generator Shaft • Large Phase Angle Across MAPP MAIN Interface • Eau Claire Arpin Line Switching • Instanteous change in Power output

  11. Dynamic Stability • Ability of Systems Generators to remain synchronized and recover from Major System Disturbance • MAPP WUMS Disturbances • Loss of New Facilities • Impact on Existing Limiting Conditions • Dynamic Reactive Support Requirements

  12. Voltage Stability • Ability of the System to Maintain Adequate Voltage Following a Disturbance • Without Adequate Voltage Support System can Experience • Increased Current Demand (P = VI) • Slowly Declining Voltage • Loss of Voltage Sensitive Loads • Voltage Collapse

  13. Engineering to Support Permitting • Calculation of; • AUDIBLE NOISE • ELECTRIC FIELD • MAGNETIC FIELD • Analysis of Potential Farm Impacts • Stray Voltage • Earth Currents

  14. EMF Issues • Magnetic Field • Electric Field • Spark Discharge • Multiple Routes • Multiple Structures • Multiple Circuits • Multiple Flows • Future Years

  15. Transmission Line Noise • Due to Corona Discharge • Electric Field at surface of the conductor exceeds the breakdown strength of air • Generates light, audible noise radio noise and energy losses • Mitigation • Increase Conductor Surface area • Larger Conductors • Multiple conductors

  16. Substation Noise Monitoring • Long Term • Short Term • ExistingEquipment • Impact ofAdditions

  17. Arrowhead Substation Noise

  18. Other Engineering Issues • Differential GPS Interference (Precision Farming) • Electric & Magnetic Field • Impacts on Pacemakers and implantable Defibulators • Impacts on Railroad, Pipeline and AM Radio Transmitter sites

  19. Opposition to the project: • Save Our Unique Lands • Citizens Utility Board • Wisconsin Environmental Decade • North American Water Office • Hillside Dairy • World Organization of Landowner Freedom

  20. Common Utility Corridor

  21. Visual Impact Of Crossing

  22. Existing 161 kV H-Frame

  23. 954 ACSR 2-ConductorBundle with Shield Wire

  24. Single 3M Composite Conductor

  25. Post Permit Studies • Equipment Specification • Construction Support Analysis • Operating studies

  26. Equipment Specifications • Transient studies • Breaker Switching Duties • Shunt Reactor • Shunt Capacitor • 345 & 230 kV line breakers • Capacitor Bank Switching Issues • Voltage Magnification • Insulation Coordination • Surge Arrester rating & placement • Equipment BIL requirements • Line Insulation

  27. Constructability Line outage concerns Maintenance issues Ownership Issues Increased Cost Landowner Opposition Construction Impact Studies

  28. Operating Studies • Determination of Operating Limits • Reactive Support Requirements • Shunt Capacitor location optimization • Line Loadability Issues • System Intact and Post Contingency • Phase Shifter Requirements • Line load sharing optimization • Post Contingency requirements • New Flow-Gate Limits • System Intact and Post Contingency

  29. Summary • Operating experience has shown there is a significant risk to electrical reliability in the upper Midwest and Wisconsin • Engineering study commissioned through Assembly Act 204 • WRAO recommendation Arrowhead Weston 345 kV Line

  30. Summary • The Arrowhead-Weston Project will substantially alleviate the reliability problems being experienced due to the weak electrical tie between the upper Midwest and Wisconsin. • It will also provide import capability for Wisconsin to meet its emergency power supply requirements.

More Related