1 / 18

Northgate Link Project: Transmission Line Relocation Update

Northgate Link Project: Transmission Line Relocation Update. Haller Lake Community Club, March 6 , 2014. 16 miles of light rail with 13 stations currently in service University Link under construction; opens 2016 ST2 Plan funded extensions to Overlake, South King County, and Lynnwood

eileen
Download Presentation

Northgate Link Project: Transmission Line Relocation Update

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Northgate Link Project: Transmission Line Relocation Update Haller Lake Community Club, March 6, 2014

  2. 16 miles of light rail with 13 stations currently in service • University Link under construction; opens 2016 • ST2 Plan funded extensions to Overlake, South King County, and Lynnwood • 54 mile system Link Light Rail System 2

  3. 4.3-mile light rail extension • Stations at U District, Roosevelt, and Northgate • Open for Service: 2021 • 62,000 daily boardings added to system by 2030 Northgate Link Extension 3

  4. Northgate Station Area Update • Portal construction underway; first tunnel boring machine (TBM) launched in late May/early June • Northgate Station design 90% complete; public open house on March 12th • Station and guideway construction begins in early 2016 • Early utility relocations in 2014-2015 4

  5. Public Involvement – December 5th Open House • Over 740 meeting notices delivered to residents within 1 block of proposed route • Project newsletter also sent to Northgate area residents • 31 people attended open house • Over 90 written comments since meeting 5

  6. Transmission Lines Conflict with Elevated Guideway 6

  7. 115kV Transmission Lines Relocation • Elevated guideway conflicts with SCL transmission line on 1st Ave NE • Alternatives east of I-5 considered; SCL conceptually approved Meridian Avenue N. & N. 115th Street route • Scope of transmission line relocation: • - relocate ~ 4,000’ of 115kV line • - install 13 new poles in street right-of-way • - taller pole height to avoid treeimpacts • - steel poles will replace some wood poles 7

  8. Initial concept shown on Dec. 5th • 7 existing wood poles to be replaced, mostly along N 115th St • - heights (75’ to 115’) • 5 new poles proposed along Meridian Ave N • - heights (110’ to 130’) 8

  9. Community Feedback • Poles out of character with residential neighborhood and not appropriate for non-arterial street: • Too tall • Too wide • Steel 9

  10. Design Modifications along N. 115th Street • Sound Transit in cooperation with Seattle City Light and Seattle Department of Transportation have modified the design along N. 115th Street: • Reduced Pole Heights (5 to 20 ft.) • Replaced Steel with Glued-Laminated (Glu-Lam) Wood Poles • Reduced Pole Widths 10

  11. Project Improvements • Modified 3 poles from steel to wood poles • Reduced heights along N.115th Street down to 95 feet (up to 20 foot reduction) • Modified pole placements to avoid utility conflicts 11

  12. N. 115th Street at Corliss Avenue N. Looking East MODIFIED EXISTING INITIAL

  13. 2100 Block – N. 115th Street EXISTING MODIFIED 13

  14. Summary Response to Community Feedback - Design Modifications on N. 115th 14

  15. Next Steps • Geotechnical Investigations – Summer 2014 • Final Design – Fall/Winter 2014 • Replace Poles – 2015 15

  16. Questions? 18

  17. For more information • Sign Up to Receive Email Updates • www.soundtransit.org/subscribe • Sound Transit Website • www.soundtransit.org/northlink • Contact Rhonda Dixon: • 206.398.5300 • northlink@soundtransit.org 17

More Related