This document discusses the plans and current status of the thermal mock-up for the Belle.II VXD. It includes details about the test setup, access to the XFEL CO2 Cooling System, and the design and production schedule for the mock-up. The document also mentions the ongoing tasks and team members involved in the project.
E N D
Belle II VXDStatus and plans for thermal mock-up SuperKEB / Belle II Session KEK@DESY Meeting 19.-20.03.2012 SVD Configuration (Markus Friedl)
Thermal Test Setup in DORIS Hall • we have access to the XFEL CO2 Cooling System built for AGIPD detector • courtesy of Heinz Graafsma • there are some constraints • system not identical to MARCO / IBBelle • simplified control system • Experience will tell if we need to build our own system • Setup has to stay in DORIS hall Test Setup Support XFEL AGIPD Lab XFEL CO2Cooling System DORIS Access Gas Containment
XFEL CO2 Cooling System XFEL CO2 Cooling System CO2 Distributor
CO2 Transfer line production 4 x 8m PXD lines
Add heavy metal here Add more if not too heavy 6mm gap for cabling VXD Cold Box (Dry Volume) Request by BG simulation Otherwise BG showerreach PXD directly gap for Cooling pipe/ BPM cable VXD design heavymet(Tanaka)
VXD Cold Box Thermal Mock Up define boundary conditions for the real dry volume -> design Cold Box
Test Setup Cold Box Thermal Mock Up (Dry Volume) VXD dry volume end caps PXD CO2 lines Beam pipe heatingline Beam pipe coolinglines
Beam Pipe Thermal Mock Up Stainless Steel Aluminium Paraffin Chiller 6 liter Paraffin Oil
PXD Thermal Mock Up End flange prototypes received from Karlsruhe (3 of 4)
B2GM 16.3.12 New concept for cooling pipe fixation SVD Thermal Mock Up • Geometry of SVD almost frozen (except layer 3) • Write-up of requirements and design of cooling system in preparation • AnneKatrinFrankenberger • Still have not yet decided which level of sophistication adequate for thermal mock-up • some work sharing with Cracow intended • e.g. CFRP ribs etc. Simplified ladder structure
Closed-loop CO2 Cooling Plant(Markus Friedl) Developed commonly by PXD and SVD together with experts from CERN
Production Schedule for Thermal Mock Up • most topics are extended
DESY Belle II Task / Team ongoing Tasks: design and production of Thermal VXD Mock-Up design and test of cooling strategy design and production of the VXD Cold Box (Dry Volume) optional Tasks: design and production of VXD installation Mock-Up design and test of VXD infrastructure integration Team: Carsten Niebuhr Team Leader / Communication KarstenGadow Mock-Up Design / Test Robert Volkenborn Mock-Up Design / Simulation 1 Technician ( March ?) Mockup Production work has started and increase in speed!
SVD (Markus Friedl) Sensor underneath flex circuit End ring (support) APV25 chips Origami ladder Pitch adapter bentaround sensor edge Cooling pipe
SVD Readout Chain (Markus Friedl) Finesse Transmitter Board (FTB) FADC+PROC 1902APV25chips ~2mcoppercable Junctionbox ~10mcopper cable Unified opticaldata link (>20m) COPPER Front-endhybrids Rad-hardvoltageRegulators Analog level translation,datasparsificationandhit time reconstruction Unified Belle IIDAQ system