Islanding schemes southern region. SRPC, Secretariat. Ramagundam & Hyderabad IC 2600 MW Load 1400-1800 MW. RTPS 600 MW. Simhadri TPS IC 5 00 MW. Kothagudem TPS. Jindal 100 MW on House Load. BTPS Gen 300 MW. Vijaywada TPS. KAIGA12 670 MW KAIGA34 315 MW. Rayalaseema TPS
E N D
Islanding schemes southern region SRPC, Secretariat
Ramagundam & Hyderabad IC 2600 MW Load 1400-1800 MW RTPS 600 MW Simhadri TPS IC 500 MW KothagudemTPS Jindal 100 MW on House Load BTPS Gen 300 MW VijaywadaTPS KAIGA12 670 MW KAIGA34 315 MW Rayalaseema TPS IC 300-350MW VARAHI 230 MW CHENNAI KDPP Kuttiady Total Gen-60-230 MW Total Load 150-250 MW NEYVELI METTUR Idukki, LPeriyar , Chalakudy Total Gen 300-1200MW Total Load 900-1100 KUNDAH Kayamkulam, Sabarigiri , Kakkad Gen 300-600 MW Load 420-660 MW TUTICORIN
Jindal Back JINDAL WILL GO ON HOUSE LOAD
BTPS BTPS1 unit of 500 MW with reduced generation (300MW) Loads =290 MW BTPS UNIT 2 ON HOUSE LOAD Back
Lingasugur RTPS 100 MW Kushtagi 70 MW Sindhanur BTPS Gooty Gadag Lingapur Harthi Alipur 65 MW JSW Munirabad 55 MW HiriyurPGCIL BMM ISPAT Guddadahalli PGCIL Guttur The total load is about 290 MW BTPS Back
BTPS Back
KAIGA12 Back
Kollapur 40 MW Kuduchi 33 MW 65 MW Bagalkot Athani Chikkodi Belgaum 52 MW Supa110kV 55 MW Vajramatti Kanabargi Mahalingapur -55 MW Ambewadi 90 MW Ponda Tadas 55 MW 25 MW 70 MW Narendra Soundatti Kadra KSHally 65 MW Hubli Harti Bidnal Nagjari 55 MW Karwar Kaiga Unit-1 & 2 50 MW Sirsi 4 MW KaigaICTs The total load is about 670 MW SGS KAIGA 12 Back
KAIGA 12 Back
KAIGA34 Back
KAIGA34 Back
KAIGA 3 & 4 Back
VARAHI Back
Shanthigrama PGCIL MRS Shimoga 90 MW Kemar UPCL Varahi 90 MW Kavoor Kudremukh 50 MW Puttur Total Load is about 230MW VARAHI Back
VARAHI Back
RTPS Back
RTPS Back
RTPS Back
Rayalaseema TPS Back Details
Ramagundam & Hyderabad Back Details
Simhadri Back Details
Kothagudem TPS Back Details
Kayamkulam, Sabarigiri and Kakkad Total Generation 300-600MW Total Load 420-660 MW Back Details
Kayamkulam, Sabarigiri and Kakkad Back LOAD SHEDDING FROM 10-130 MW REQUIRED
Idukki, Lower Periyar and Chalakudy Total Gen 320-1200 MW Total Load 900-1110 MW Back Details
Idukki, L Periyar , Chalakudy LOAD SHEDDING FROM (-)50-600 MW REQUIRED Back
KDPP and Kuttiady Total Gen 20-90 MW Total Load 150-250 MW Back Details
KDPP Kuttiady Back LOAD SHEDDING FROM (-)20-100 MW REQUIRED