1 / 6

Material Procurement

Material Procurement. Construction material – All the material has been ordered with some spare (10%). Delivered material PNPI – M3R4 – Panels 70% - HV bars 100% - FR4 frames 100% PNPI – M2R4 – Panels 20% - HV bars 100% - FR4 frames 100%

Download Presentation

Material Procurement

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Material Procurement • Construction material– All the material has been ordered with some spare (10%) Delivered material PNPI – M3R4 – Panels 70% - HV bars 100% - FR4 frames 100% PNPI – M2R4 – Panels 20% - HV bars 100% - FR4 frames 100% PNPI – M4R4 – Panels 0% - HV bars 90% - FR4 frames 0% CERN – Panels 60% INFN – M3R3 completed – M2R3 ~ completed – M5R4 Panels 20% HV bars ~ 40% FR4 frames 100% Other elements 100% M1 panels 0% • Faraday cage– Final FEE board dimensions available  M3R3 FC is ready – All the others need the preparation of drawings (M3R4-M2R3-M5R4+....) • Honeycomb - We got samples for M1R3/R4 regions, cut at the right dimension and a quotation. Early 2005 we should go for the purchase and the production. • Wire– in last months it occured several times (in LNF and at CERN) that the wire broke during the winding. The problem is being investigated by the Luma company. Probably it is related to a bad spooling.

  2. Panel production rate A rate of 250/month is mandatory to match the chamber production schedule. To monitor the production yield a data base on each INFN site is operational. ~2600 panels have been produced  on average a very good rate The yield appears quite good: approximately 90% . Panels needed according to official plan We are here

  3. Chamber preparation prior to installation • 1. Preparation in labs: • FEE electronics, LV and Faraday Cage must be assembled on chamber (and tested). • Part of this work will be done at the production sites: • at Roma-2 and LNF for whole INFN production, at PNPI and at CERN. • The first chambers will be equipped as soon as the CARDIAC boards will be available. • 2. Shipping of MWPCs: INFN chambers to CERN: in special trolleys with shock absorbers stocked in a container (see photo). • Shipping of PNPI chambers: in wooden boxes (CSC-CMS like) • 3. Tests at CERN: • Storage at CERN: about 200 m2 available. Stored under gas flux. • Tests: check no-damage in transportation: test on FEE and last test with HV\ • We have yet to deploy a detailed plan for these tests: • check the time and the personnel needed; • logistics at CERN and the infrastructure needed (gas, HV, etc...)

  4. Trolleys and container for chamber storage and transportation Container with 6 trolleys of 18 chambers each = 108 chambers.

  5. Glue expiration date Axson France certifies that the glue can be used up to 24 months after fabrication La presente per inviare in allegato il certificato attestante ilprolungamento data scadenza del ns.prodotto Adekit A145/50 da Voi acquistato.Colgo l'occasione per informarVi che i ns. ProdottiAdekit A140 ed A145, a seguito di test effettuati presso la ns.Casamadre, hanno subito modifica di durata di vita che ora corrispondea mesi 24 dalla data di fabbricazione. Distinti saluti Raffaella Roncoroni AXSON Italia s.r.l.

  6. Conclusions

More Related