An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. NSLS – II EFAC Review Conventional Facilities Briefing Marty Fallier Director for Conventional Facilities National Synchrotron Light Source – II Project October 19, 2006

  2. Outline • Conventional Facilities Scope • Facility Overview Facility Program • Experimental Floor • Central Lab Office Building • Lab Office Building(s) • Differential Settlement • Vibration Mitigation • Utility Services • Temperature Stability • Schedule

  3. NSLS II Facility Overview

  4. Site Plan NSLS Conf. Center Service Bldg Typ 4 CLOB CFN Future JPsi RF-LINAC AREA Future Guest House LOB Typ 4 Ring Bldg Loading Underpass

  5. Building Program

  6. Experimental Floor Concept • Divided into 5 clusters • Service Bldg supports all services within the cluster • Six sectors/Cluster • CLOB & Service Bldgs contain all Accelerator systems • Ring, CLOB, LOB 1 & service bldgs are base scope • LOB’s 2,3,4 can be added as needed w/o interruption

  7. Experimental Floor Arrangement

  8. Experimental Floor - Ring Building Section

  9. CLOB Features • Space for 190 Offices, 8 labs • Nominally 30 User Offices, 5 User labs from the total • Possible 400 seat Conference Center addition w/ vendor area and three breakout rooms • Lobby and User Reception area • 2nd floor viewing gallery overlooking experimental floor • Bridge to electrical mezzanine and control room & RF/LINAC areas • Close Proximity to future: • JPSI Building • Guest house

  10. Floor Plan – CLOB 1st

  11. Floor Plan - CLOB 2nd

  12. Floor Plan – CLOB 3rd

  13. LOB Features • Modular design – can be added when needed without interrupting operation • 11,000 SF each – Serves six sectors • 30 offices w/ conference space, interaction areas, lavs, showers • 5 labs intended for shared use • Shipping/Receiving/Storage area & chemical storage area • Potential for expansion for more offices if needed • Egress provided for personnel and large items at each LOB • Loading area with exterior roll-up door • Roll-up door from each lab onto the experimental floor • Designed to minimize impacts to future long beamlines

  14. Lab – Office Building

  15. Differential Settlement • Measures to reduce potential for differential settlement include: • Thorough geotechnical analysis of site to identify problem areas • Minimize footprint over disturbed areas • Set finished floor elevation for maximum cut and minimum fill • Early site preparation contract for maximum time to cut, fill, compact and observe settlement prior to building contract. • Monolithic slab design for tunnel and experimental floor • High slab stiffness, Tunnel 36”; Experimental Floor 18” • Building loads isolated from tunnel and experimental floor slab • Access corridor isolated from experimental floor slab

  16. Vibration Mitigation • Measures to be implemented in conventional design include: • “Monolithic” slab for accelerator and experimental floor • Slab thickness and section changes will be based on vibration modeling results • Possible use of polymer admixtures for enhanced damping characteristics – likely use for access corridor • Isolation of bldg structure from tunnel and slab • Inertial bases and isolation of machinery • Low flow velocity design for ducts and piping • Limited use of duct and piping isolation to avoid conversion & transmission of low frequency vibration • Commissioning of equipment and systems to include alignment, balancing & vibration measurement

  17. Utility Support • Utilities run underground in center of ring and distributed to five service bldgs (one in CLOB RF/LINAC area) • Minimizes pipe runs and pipe size in bldg proper • Only needed service piping will be run in experimental area • Minimizes potential noise and vibration impacts • Services provided at each BL include: • Electric Power Panel at Ratchet Wall, 75-95kW/Cell, 120/208V • Cooling Water, HVAC Supply Air, Exhaust • Compressed Air, LN2, GN2 • DI Water (Copper and Aluminum) by Accelerator Group

  18. Utility Support

  19. Temperature Stability • Key temperature stability requirement is tunnel air @ +/- 0.1C at a given location with respect to time. • Requires high resolution industrial grade instruments and controls with excellent repeatability. • Space temp setpoint of 85 F is nominally equivalent to process cooling water supply setpoint to minimize temperature gradients • Should be readily achievable provided loads to accelerator components are relatively steady-state • Experimental Floor Temperature • Cooling: 75 F +/- 1 F, 50% RH +/- 10% RH • Heating: 75 F +/- 1F, 30% RH +/- 10% RH

  20. Experimental Floor Air Distribution

  21. Schedule • Construction sequencing will enable • Availability of Ring Bldg for LINAC, booster and storage ring installation to begin as early as March 2010 • Beneficial Occupancy of Ring Building & LOB - June 2011 • Control/Computer room availability & CLOB BO - August 2011 • Conventional Construction complete - October 2011