1 / 25

Direct Reduction Iron Plant

Direct Reduction Iron Plant. Group Golf Selimos, Blake A. Arrington, Deisy C. Sink, Brandon Ciarlette, Dominic F. (Scribe) Advisor : Orest Romaniuk. Table of Contents. 3 – Previous Questions 4 – Design Basis 5 – Block Flow Diagram 6 – Overall ASPEN Simulation

balin
Download Presentation

Direct Reduction Iron Plant

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Direct Reduction Iron Plant Group Golf Selimos, Blake A. Arrington, Deisy C. Sink, Brandon Ciarlette, Dominic F. (Scribe) Advisor : Orest Romaniuk

  2. Table of Contents 3 – Previous Questions 4 – Design Basis 5 – Block Flow Diagram 6 – Overall ASPEN Simulation 7 – Closer look: Primary Reformer and Heat Exchangers 8 – ASPEN Sim: Primary Reformer and Heat Exchangers 9 – Energy Sinks and Loads: Primary Reformer 10– Energy Sinks and Loads: Heat Exchangers 11– Energy Sinks and Loads: Overall Process 12– Equipment Sizing 13-14 – ASPEN Process Economic Analyzer 15– Profit Economics 16– Transportation 17– Shipping & Storage

  3. Previous Questions • What type of catalyst will we be using in the primary reformer? • What is the lowest purity of oxygen the oxygen fuel booster can operate with? • Impurity concerns iron ore feed.

  4. Design Basis • 106 thousand lbmols/day of natural gas feedstock will be supplied for process from Gas Treatment Plant; natural gas is the main source for Carbon for the reformer. • Supply portion of top-gasCO2 to Industrial Gases Plant, 148.8 thousand lbmols/day. • Air Separations and Syngas Plant will supply 0.5 thousand lbmols/day of O2 for the Oxy Fuel Booster.

  5. Block Flow Diagram

  6. Overall ASPEN Simulation

  7. Closer look: Heat Exchangers & Primary Reformer

  8. ASPEN simulation: Heat Exchangers & Primary Reformer 1650 F 75 psi 77 F 14.7 psi 180 F 75 psi 1878 F 14.7 psi 420 F 14.7 psi 724 F 14.7 psi 438 F 14.7 psi 1076F 75 psi 180 F 14.7 psi 615 F 14.7 psi 180 F 75 psi

  9. Energy Sinks and Loads: Primary Reformer 1650 ºF 75 psi 1076ºF 75 psi 438º F 14.7 psi 1878 ºF 14.7 psi Q= 280 mmBtu/hr Q= - 280 mmBtu/hr

  10. Energy Sinks and Loads: Heat Exchangers 1076º F 75 psi 77º F 14.7 psi 724º F 14.7 psi 420º F 14.7 psi 1878º F 14.7 psi 724 ºF 14.7 psi 1650 F 75 psi 180º F 75 psi Q=113 mmBtu/hr Q=27 mmBtu/hr

  11. Energy Sinks and Loads:Overall process

  12. Equipment Sizing Primary Reformer Tubes: 10 in. Diameter, 26 ft. length f = Maximum heat flux thorough tube walls = 21,000 Btu/ft2*hr d = Heat duty through primary reformer (from Aspen) = 279,515,872 Btu/hr a = Total needed surface area of reformer tubes = d/f = 14,167 ft2 t = a / 73 ft2 per tube = 194 tubes needed

  13. ASPEN Process Economic Analyzer Units analyzed • Primary Reformer • Heat Exchanger

  14. Profit Economics

  15. Transportation Costs By Rail For Feed/Product • Basis of 1.84 mm ton produced 5,041 (ton/day) • Average rail car holds 80 tons. With a maximum load per train of approximately 15,000 ton and 150 cars • Plant will need a train every 2 days of approximately 130 cars. • Average cost to ship by rail 0.03($/ton mile) • Assuming a discounted rate of 25% for large volume of material transported. • Using northeast Minnesota for iron oxide source and northwest Indiana for product shipment. • Cost to ship 23.00($/ton) to ship product 12.00($/ton) import raw material.

  16. Shipping/Storage • Installed equipment cost for a private rail line with loading/unloading site at our capacity will be around $15 million. • Storage facility with installed in-loading/out-loading conveyor system, a negative pressure dust/climate management system, and a 150 ton capacity will cost around $10 million.

  17. Summary • Producing 1.84 mm Ton/year DRI. • Heat from combustion drives primary reformer and preheats gas entering primary reformer and combustion. • Typical primary reformer size: 57600 ft2. • Cost of reformer & heat xers: $38 million. • Yearly profit: $240 million. • Transportation: 130 car train every 2 days. • Storage: 2-week buffer for unexpected delays.

  18. Work in Progress • Finish process simulation in ASPEN. • Run ASPEN economic analysis on whole process. • Size all equipment.

  19. Questions

  20. Typical Plant layout

More Related