OFFSHORE PIPELINE CONSTRUCTION PHASE. Pipe Laying : Normal S-Laying Method. OFFSHORE PIPE LAYING: Normal S-Laying Method. Lift the pipe out of the supply barge onto the incoming rack Pipe Tallying (pipe number, length, joint number) Making the J-Bevel on pipe ends for Auto welding.
E N D
OFFSHORE PIPELINE CONSTRUCTION PHASE Pipe Laying : Normal S-Laying Method
Lift the pipe out of the supply barge onto the incoming rack • Pipe Tallying (pipe number, length, joint number) • Making the J-Bevel on pipe ends for Auto welding Step 1: PIPE BEVELING
Preheat on pipe end prior to welding (based on approved WPS) • Fitting pipe ends to be aligned by means of internal clamp • Root weld followed by Hot pass Step 2: Station 1 (Fit up, Root and Hot Pass)
Filler passes on Station 2 and 3 • Cap welding on Station 4 • Visual Inspection on Station 5 Step 3: Station 2,3,4&5 Sta #4 Sta #2 Sta #5 Sta #3
Step 4: Station 6 (X-Ray) X-ray operators control the movement of the X-ray crawler inside the pipe Radiographic intrepeters from HHI, Client and Migas are reviewing the X-ray result Wrapping the film around the intended joint
Step 5: Station 7& 8 (Brush up and Cold Wrap) Sta #7: Brush up Sta #8: Cold Wrap
Foam Coating performed by OJS (Offshore Joints Service) Step 6: Station 9 (FIELD JOINT COATING) & PULLING
HD 423 Laying
HD 423 LINE PIPE ON SEA BED
P4 P2 P1 P5 S5 S1 S4 S2 How the Barge Moves
P4 P2 P1 P5 S5 S1 S4 S2
P4 P2 P1 P5 P5 S5 S5 S1 S4 S2
P4 P4 P2 P1 P5 S5 S1 S4 S4 S2
P4 P2 P2 P1 P5 S5 S1 S4 S2 S2
P4 P2 P1 P5 S5 S1 S4 S2