S-2361 3D Laser Scanning of Acropolis of ATHENS

S-2361 3D Laser Scanning of Acropolis of ATHENS. 3 D scanning of the Wall and the Rock of Acropolis Athens and 3D model creation. Technical Specifications Scan density for the walls 1-2cm Scan density for the Rock 5cm Triangulation network with < 5mm accuracy Leveling <3mm accuracy)

bandele
Download Presentation

S-2361 3D Laser Scanning of Acropolis of ATHENS

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. S-2361 3D Laser Scanning of Acropolis of ATHENS

  2. 3D scanning of the Wall and the Rock of Acropolis Athens and 3D model creation

  3. Technical Specifications • Scan density for the walls 1-2cm • Scan density for the Rock 5cm • Triangulation network with < 5mm accuracy • Leveling <3mm accuracy) • Supervisor authority of the project was YSMA (authority of Hellenic calture)

  4. Equipment • Trimble GPS 5800 • Trimble 5600 DR 200 total station • Trimble DiNi 0.3 digital level • Trimble GX laser scanner • External digital camera Canon EOS400D • Balloon with a Mamiya 22Mpixel camera

  5. Field Work Field Work

  6. Geodetic Background • Triangulation network consisted of 13 points (10 New triangulation points + 3 from National Coordinate Network) • Traverse points fully dependent on the triangulation network covering the whole area of interest • High accuracy leveling network

  7. Triangulation Network

  8. Triangulation Network Establishment

  9. Scanning location selection Scanning location selected according to the following principles: • Maximum possible coverage with least possible scans (sample photo) • Scanning angles acceptable according to the specs • Multi dimensional overlap of successive scans • Logging and mapping of the scanned area coverage from each scan • Scanning always using the basic geodetic background points

  10. Scanning location selection • Leveled stations • Unleveled stations • Targets

  11. Principles of scanning procedure – Scanning orientation • Certain procedures were followed in order to achieve maximum absolute and relative orientation accuracy when scanning was performed with: 1) Trimble GX in horizontal position 2) Trimble GX inclined

  12. Scanning • Scanner was leveled in known pre-surveyed position and oriented to a pre-surveyed point. • Additionally Trimble GX targets were used for orientation, which were previously measured with Trimble 5600 DR 200 Total Station. • Finally Trimble GX spheres were scanned which are ideal for relative orientation between scans. • Absolute orientation of successive scans was achieved using both first two methods while relative orientation was optimized by using common targets and spheres. • Significant overlapping also was usedin order to optimize relative orientation

  13. External photos (land shots, balloon shots) Image resolution of internal Trimble GX camera was not enough according to the project specs. • For this reason external digital camera Canon EOS400D was used with 10Mpixel image analysis. • Also balloon vertical and horizontal photos were taken with a Mamiya 22Mpixel camera. Object shooting followed the following basic principles: • Shooting according to the basic rules to take photos • Shooting the object in right angles if possible • Shooting of complex surfaces from multiple angles • Balloon shooting of horizontal and encrypted by the rough terrain surfaces for appropriate texturing

  14. Scan & Geodetic Statistics For the full coverage of the Wall internally and externally and the Rock: • 125 scans performed • more than 800 digital pictures were taken and used. • A total of 330.000.000 points were taken during scanning • The scan density was finally well above the specs • Better than 1cm accuracy For the geodetic network: • Triangulation network with < 3mm accuracy • Traverse points < 5mm accuracy • Leveling <2mm accuracy)

  15. External photos / balloon shots

  16. External photos (land shots, balloon shots)

  17. Supplementary and Vertical scans There were also gaps that were impossible to be covered with regular horizontal or inclined scans. • Gaps that were due to coverage errors were covered with supplementary scans. • Gaps that found and were due to the complex of the surface in most of the cases covered with two methods: 1) Vertical scans using a special installation to scan over the walls 2) DTM creation from photogrammetric models

  18. Horizontal scans

  19. Vertical scans

  20. Office Work Office Work

  21. Triangulation Network – Leveling Network - Traverse Network • Trimble Geomatics s/w • Triangulation network, levelling network and traverses network resolution was done simultaneously using Least Square Adjustment technique

  22. Scanning registration – Techniques applied • RealWorks s/w used for the processing of the scanning data. • Scans registering with: targets, spheres or by using overlapping scanned objects in successive scans. • RealWorks s/w ensures common resolution using different methods of registration to more than one scans simultaneously. • Memory limitations due to the huge model did not allow common resolution of the whole scanned object. • We used large common segments of it, with significant overlapping between them. • The mean orientation accuracy achieved was better than 1cm.

  23. Location of scanning gaps With the common registration and unification of successive scans we manage to locate scanning gaps. Those gaps were covered as described above. • DTM provided by photogrammetric models were integrated to the rest of the point cloud automatically as the common geodetic background had as result that DTM was fully compatible with the rest of the model.

  24. Filling with DTM scanning gaps

  25. Scanning data filtering • Before surface creation point clouds from successive scans checked and filtered in the overlapping areas. Common point cloud created from multiple scans • By unifying scans a common point cloud created. • In order to be able to process the data due to the huge memory needed they were separated in sub-models

  26. Common point cloud created from multiple scans

  27. External digital photo orientation • In order to achieve the best possible accuracy in image matching the full density point cloud has to be used together with laser intensity info. • This way point cloud describes objects like a 3D photograph giving user the possibility to recognize and match common points with digital photos with great accuracy.

  28. External digital photo orientation

  29. Equalise digital photos With Adobe Photoshop equalize digital photos. • This procedure eliminates the impact of different contrast and luminance due to different shooting environmental conditions • As a result texture differences coming from different photos are smoothed giving a homogeneous texturing to the object

  30. Point cloud generalisation • In order to create surfaces it is a prerequisite for memory limitation reasons to generalize the point cloud. • The point cloud density for the walls decided to be finally 10cm, while the relevant one for the rock 20cm

  31. 3D model creation Point cloud segmentation • The object complexity had as result a very careful procedure of surface structuring, which was related not only with the surface complexity, but also with the external image shooting angles. • All the above has as a result a procedure of structuring sub surfaces and tailoring them with suitable overlapping in order to create a final product able to represent the real world. • All sub-surfaces have been created by point clouds that have been segmented accordingly. • The above procedure proved very complicated, demanding and time consuming.

  32. 3D model creationPoint cloud segmentation

  33. Surface texturing • Surface texturing using the already matched external images was happening while we were creatring sub-surfaces. This way it was possible to control texturing to every single surface, and to select the most suitable image for this. Of course this is very complicated and time consuming. 3D model with texture • Following the above described procedure a 3D model of the walls and the rock of Acropolis Athens was createddescribingwithdetail and accuracy one of the most important and famousmonuments of the world.

  34. 3D model with texture

  35. 3D model with texture

  36. 3D model with texture

  37. 3D model with texture

  38. 3D model with texture

  39. Project Statistics • 3 months field work for Geodetic Infrastructure and Scanning (A team of two experienced surveyors) • 12 months (A team of one supervisor and two experienced RealWorks operators)

  40. Thank you for your attention…