BWI Comprehensive Runway Safety Area Program. Runway Intersection Scope of Work Pavement Rehabilitation Profile and Smoothness Adjustment Modification of Existing Lighting New Lighting Infrastructure New Pavement to Accommodate Future Runway Shift. alp. Proposed conditions.
E N D
BWI Comprehensive Runway Safety Area Program Runway Intersection Scope of Work • Pavement Rehabilitation • Profile and Smoothness Adjustment • Modification of Existing Lighting • New Lighting Infrastructure • New Pavement to Accommodate Future Runway Shift
Runways 10-28 and 15R-33L Intersection Pavement Rehabilitation and Standards Compliance Project Pre-Bid Meeting March, 2011
BWI Comprehensive Runway Safety Area Program • RW 10-28 RSA, Pavement Rehabilitation & Standards Compliance • RW 15R-33L RSA, Pavement Rehabilitation & Standards Compliance • RWYS 10-28 & 15R-33L Intersection Pavement Rehabilitation & Standards Compliance • Miscellaneous Taxiway Rehabilitations
BWI Comprehensive Runway Safety Area Program Runway Intersection Design Aspects • PG+ 76-22 Polymer Modified P-401 Bituminous Concrete • Design Surface from Computer to be provided to Contractor • Design Surface to be verified by Contractor by Survey • Test Strip to evaluate conformity to Design Surface
BWI Comprehensive Runway Safety Area Program PHASING/SECURITY • Night work (11PM – 6AM) • 54 Hour Intersection Closure • Contractor Provided Safety Guards (trained by MAA Operations) • TOTAL: 133 Calendar Days
BWI Comprehensive Runway Safety Area Program PHASING SCHEDULE • MOBILIZATION: 60 DAYS • PHASE 1 (32): 1A- 14 Nights; 1B- 18 Nights • PHASE 2: 4 DAYS (96 HOURS) • PHASE 3: 54 HRS (9/9 – 9/12) or (9/16- 9/19) • PHASE 4: 10 Nights • PHASE 5(6): 5A- 2 Nights; 5B – 4 Nights • WEATHER DAYS PER GP’S • TOTAL: 133 DAYS
BWI Comprehensive Runway Safety Area Program SECURITY • PHASE 1, 4, &5: GATE G, STANDARD ESCORTING (SEE X-1) • PHASE 2: GATE 55 • PHASE 3: GATE 0 • AKAL – Sub to GC – Russell Wesley