An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Town Hall RedevelopmentBy: Faith Box

  2. In The Beginning • 2003, Development the Gallery and Sculpture Court. • $750,000 ($500,000 Grant from CASA) • Upgrade Identified the Need for the Hall to also be Renovated to the same standard

  3. Planning (Stage 1) • Consultation. Initial Public Meetings to Determine Support & Future Venue Needs • Community Working Party Established • Structural Engineering Assessments Completed • Funding Sought & Won to Conduct a Feasibility Study ($70k). • Council Reports Submitted throughout duration of the Project (in principle support at this stage)

  4. Planning (Stage 1 Continued) • Draft Concept Design & Drawings Developed • Market Cost Analysis Completed • Initial Community Consultation • Further Consultation with Draft Design Drawings (2 months) written feedback and Public Meetings • Collate Feedback & Report Back to Council • Re-draft Plans in Response to Public Feedback

  5. Planning (Stage 2) • Extensive Budget Planning • Extensive Business Plan Developed • Final Report to Council for Approval • Tender Documentation, Award Contract to Builder • Plan Relocation of Staff and Community Groups • 300 page application for Funding RLCIP (due 23.12.09) • Commence Build and Manage through 12 Months • Plan Major Opening (Certificate of Occupancy Awarded 2 days Prior to Opening) Whewww! • Project Continues – Development of Systems, Staff, Marketing and Venue Management

  6. Funding Won • $20k Feasibility Study • $500k Rural Town Development Fund • $750k Regional Centre of Culture • $250k Capital (Arts SA) • $75k Private Business Sponsor • $30k Burke Urban (Illuminart Town Hall)

  7. Key Success’s Local Heritage Icon - Now A First Class Multipurpose Visual & Performing Arts Centre • 4 additional staff (full time and part-time) • As a consequence - CBD Urban Design Feasibility Study Initiated • Ripples (2010 Regional Centre of Culture) • Stated “Best Regional Gallery in SA” (3000 attended R. Hannaford) • Local Economic Stimulus (Visitor Audiences/Tourism) • Strengthened collaborative partnerships • Illuminart – Town Hall Projected Light Show • Community Development Team move to Upstairs Office Space

  8. Learning Experiences • Plan, Plan and Plan Some More! • Expect Not Everything Will Go to Plan! • The Need to Take Risks! • Can’t Please Everyone! • Effective Consultation ‘A MUST’ • The Need For Support! • Expect Politics & Confrontation! • Tenacity a must! Never Give Up!!

  9. Questions