1 / 7

HP BY PASS WARM UP

HP BY PASS WARM UP. METHODS: (A) Equalising line with orifice (B) Drain line at upstream side of valve connected to downstream side of Main Steam line strainers. Method (A):

bennett
Download Presentation

HP BY PASS WARM UP

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. HP BY PASS WARM UP METHODS: (A) Equalising line with orifice (B) Drain line at upstream side of valve connected to downstream side of Main Steam line strainers

  2. Method (A): This method results in certain amount of loss of heat energy and increases HP By Pass downstream temperature and some times causes problems in proving emergency operation of HP By Pass. Method (B): This method is suitable for short HP By Pass upstream line

  3. SUGGESTIONS • To effectively warm up Main Steam line it is preferable to take tap off for HP By Pass near to strainer or after the strainer similar to LP By Pass • The lines are to be taken to the higher elevation . The horizontal portion of the line to be kept as minimum as possible to prevent condensate collection in the upstream side of HP By Pass

  4. SUGGESTIONSContd…. • It is preferable to have a drain pot at the downstream side of individual Hp By Pass with provision to drain condensate through level switches • Water collection in the downstream side orifice plate is expected at Simhadri since the orifice dia. is more than the pipe size.Such deviations are to be prevented

  5. 60.3 *12.5 (STUB AT BOTTOM OF THE PIPE) FE TE HP BP VAV 200 MM TO MAIN STEAM STRAINER DOWN STREAM Nb 50 LINE DIRT TRAP MSL LOCK OPEN CRH HP BYPASS WARMUP SCHEME -1

  6. 60.3 *12.5 (STUB AT BOTTOM OF THE PIPE) FE TE HP BP VAV 200 MM Nb 50 LINE MSL LOCK OPEN CRH TO TURBINE FLASH TANK 10M min. HP BYPASS WARMUP SCHEME -2

  7. THANKS