270 likes | 394 Views
City of Greencastle Flood Protection Plan. Presented by, United Geotech, LTD. Introduction. Team Overview Project Overview Design Requirements Project Approach Final Design Questions. Team Overview. Sarah Bireley– Project Manager Amee Wicks – Project Engineer
E N D
City of GreencastleFlood Protection Plan Presented by, United Geotech, LTD
Introduction • Team Overview • Project Overview • Design Requirements • Project Approach • Final Design • Questions
Team Overview • Sarah Bireley– Project Manager • Amee Wicks – Project Engineer • Brad Pickering – Project Engineer • Troy Cunat – Project Engineer
Project Overview • Greencastle Water Treatment Plant • Located in Greencastle, Indiana south of Big Walnut Creek • Six wells provide 4,000 gpm peak • Serves population of 10,000 • Site subject to flooding • Located in the flood plain • Rains on Labor Day flooded site
Project Overview (cont.) Big Walnut Creek Well field Lagoon Filter Facility US-231
Project Overview (cont.) Taken September 16, 2003 Taken September 2, 2003
Design Requirements • Confirm finished floor elevation of filter facility • Confirm base flood elevation • Investigate flood protection options • Investigate security options • Deliverables • Proposal • Progress report • Final report
Project Approach • Site assessment • Codes and regulations • Research design options • Flood protection • Security • Choose final design • Complete final design
Site Assessment • Topographic map • Finished floor elevation = 688.54 feet (MSL) Big Walnut Creek Lagoon Filter Facility
Site Assessment (cont.) • Watershed area obtained • 216 mi2 • Determined base flood elevation • Obtained Big Walnut Creek topographic map • 100-year flow determined • Q = 21,400 cfs • Maximum flows used in HEC-RAS to determine base flood elevation • 690.0 feet (MSL)
Site Assessment (cont.) Finished floor elevation Low head dam
Codes and Regulations • Cannot raise base flood elevation more than 0.15 feet • Water tower must be enclosed in fence • Maximum levee side slope of 1:2.5 • No levee construction restrictions
Design Options • Flood control options Levee under construction Floodwall under construction
Design Options (cont.) • Flood control options (cont.) Dry floodproofing Elevated structure
Design Options (cont.) • Decision based on four criteria • Initial cost • Lifespan • Maintenance • Constructability
Levee Design • Obtained soil borings & performed tests B6 B5 B3 B2 B4 B1 • Clay (CH), silt (MH), and sand (SW) present • Suitable for levee
Levee Design (cont.) Lagoon Expansion Filter Facility
Levee Design (cont.) • Levee cross sections
Seepage Analysis • Used SefDam to calculate seepage Elev. 692’ Elev. 690’ 13’ • Total seepage is 0.0244 ft3/day
Slope Stability (cont.) • XSTABL utilized to analyze slope stability • Eroding slope improved by Greencastle • Additional load from levee analyzed • Additional load does not cause failure
Security • Fencing, lighting, and cameras investigated • Lighting and cameras may be added in future
Security (cont.) Filter Facility
Cost • R.S. Means Manual used to estimate costs • Levee • $71,500 • Security • $24,000 • Total cost • $95,500
Conclusion • Flood levels warrant need for flood protection • Levee chosen as protection option • Seepage and slope stability not a problem • Fencing with barbed wire chosen for security • Cameras and lighting may be added • Total cost of $95,500 • Levee - $71,500 • Security - $24,000